Carriageway Patching Programme 2020/21.

Approved Planning 3 papers

Planning, Transport and Sustainable Development and Regeneration approved this item on Tuesday 14 April 2020. Below is the council's own wording, with the papers it was decided on.

Item3b

Resolved

Salford City Council - Record of Decision I, Councillor Derek Antrobus, Lead Member for Planning & Sustainable Development , in exercise of the powers contained within the Council Constitution , do hereby: Approve the programme of works contained within this report . The Reasons are: The streets identified in this report have suffered a considerable amount of deterioration because of the extreme weather over the autumn and winter of 2019 and 2020. The council has made provision a sum of £230,000 within the Block Three allocation to address this deterioration. Options considered and rejected were : None Assessment of Risk : Low – The targeted spend of available funding will ensure that the City Council’s statutory obligations are met while at the same time facilitating continuous improvement of the highway infrastructure fostering a right first-time approach. The source of funding is Department for Transport Pothole Action Fund. Legal Advice obtained – Tony Hatton, Principal Solicitor. Financial Advice obtained - Alison Woods Finance Officer (Capital). Procurement Advice obtained – Tom Woods, Procurement Team The following documents have been used to assist the decision process: Lead Member Report. Contact Officer: Steve Mangan Tel No 0161 603 4034 This decision is not subject to consideration by another Lead Member. The appropriate scrutiny panel to call-in the decision is the Growth & Prosperity Scrutiny Panel. Signed: Councillor Antrobus Dated: 14 th April 2020 Lead Member for Planning & Sustainable Development FOR DEMOCRATIC SERVICES USE ONLY This decision was published on 17 th April 2020. . This decision will come in force at 4.00 p.m. on 24 th April 2020, unless it is called-in in accordance with the decision-making process rules.
Word for word from the decision Salford published for this meeting. Source: sccdemocracy.salford.gov.uk

Follow this further

Built from Salford's papers

What the report saysPro

Report to Planning, Transport and Sustainable Development and Regeneration

Part 1: Open to the Public

REPORT OF STRATEGIC DIRECTOR PLACE

TO LEAD MEMBER PLANNING AND SUSTAINABLE DEVELOPMENT

ON 14TH APRIL 2020

TITLE: CARRIAGEWAY PATCHING PROGRAMME

RECOMMENDATIONS: That the Lead Member for Planning and Sustainable Development approves the programme of work identified in this report.

EXECUTIVE SUMMARY: The streets identified in this report have suffered a considerable amount of deterioration because of the extreme weather over the autumn and winter of 2019 and 2020. The council has made provision a sum of £230,000 within the Block Three allocation to address this deterioration.

BACKGROUND DOCUMENTS:

Appendix One Provisional Carriageway Patching List 2020/21 Appendix Two- Carriageway Patching programme 2020/21 Proposed Treatments

KEY DECISION: NO (no significant impact)

1 DETAILS:

1.0Carriageway Patching Programme

1.1The streets contained in Appendix One of this report have been identified for repairs. It should be noted that these sections of highway are not yet considered in any current works programme. The reason for this is because they do not yet meet the criteria for inclusion in the Highway Investment Programme. This is because the Highway Investment Programme seeks to predominantly tackle areas on the Highway Network that could benefit from overlay and inlay surface treatments and there is also an emphasis to some emphasis to tackle footway condition. 1.2 The cost to undertake this type of work would also be prohibitive from the revenue budget point of view. Again, this is because the areas requiring replacement are greater than localised repairs that would be usually authorised by the Highway Inspector, in accordance with the Highway Inspection and Repair Code of Practice.

1.3Nevertheless, work is required to repair the areas identified on the streets, in order to ensure that the highway safe.

1.4Funding has been identified from the Department for Transport Pothole Action Fund for this programme of work.

1.3Salford City Council has already followed the HMEP (Highway Maintenance Efficiency Programme) principles by undertaking planned, preventative and cost -effective repairs in previous works programmes and those principles shall continue with this programme of works.

1.7It is intended that along with conventional repair processes where appropriate, innovative and sustainable repair processes shall be also be used. These processes are identified in Appendix Two.

1.9The carriageways listed in Appendix One have been noted by highway inspectors who have identified defects in the carriageways during their safety inspection. Additionally, the defects in these carriageways have been subject to requests for service by members of the public, neighbourhood managers and elected members. Any actionable defects defined by risk assessment, (currently investigation level at 40mm in depth in the carriageway) have made safe, however there are adjacent areas of carriageway that require repair to prevent further deterioration.

1.10Any actionable defects that are noted within any cycle ways situated within the carriageways along the routes listed in Appendix One shall be repaired in accordance with the specified treatment identified in Appendix Two determined for that carriageway.

2 1.11 The streets shall, subject to future available funds, be included in a surface treatment programme which will seek to seal and protect the surface from deterioration thus further prolonging the service life and improve overall network condition.

1.12Some of the treatment types proposed provide innovative, sustainable solutions in the form of carriageway repairs. Where appropriate, these shall be used to carry out the repairs.

1.13A breakdown of the cost of these proposed works is as shown in Table 1 below. Work Element (£) Total (£)

Carriageway Patching Programme 2020/21 Direct Works Cost £195,500 Depot Overheads (15%) £34,500

Scheme Delivery Cost £230,000

Total Budget for programme £230,000 Table 1 Breakdown of costs

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Provisional Carriageway Patching Programme 2020_21Appendix One 77 KB Download
PDF
Carriageway Patching Programme 2020_21 Proposed TreatmentsAppendix Two 451 KB Download
PDF
Carriageway Patching Programme 2020/21.Report 82 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

1 of 2 attended
DA
Derek AntrobusCommittee Member, present
MM
Mike McCuskerCommittee Member, in attendance

On this subject at Salford

Search all
  1. Carriageway Patching Programme 2020/21.This decision
  2. Planned Carriageway Patching Programme - Local Highway Maintenance Fund 2026/27Approved

More from Salford Planning, Transport and Sustainable Development and Regeneration

All decisions
MeetingDecisionOutcome
9 Sep 2026 Traffic Regulation Order 2453 - Chapel Street / Trinity Way / St Stephen Street & Ford Street, Blackfriars & Trinity and Ordsall) - Phase 1.Salford City Council - Record of Decision I, Councillor Mike McCusker, Deputy City Mayor and Lead Member for Planning... Refused Open
9 Sep 2026 City of Salford (Camp Street, Grecian Street, Neptune Gardens, & Trojan Gardens, Broughton) (No Waiting At Any Time) Order 2025.Salford City Council - Record of Decision I, Councillor Mike McCusker, Deputy City Mayor and Lead Member for Planning... Refused Open
12 Aug 2026 Irwell River Park Floating Wetland Habitats - Section 106 Contribution Expenditure.Salford City Council - Record of Decision I, Councillor McCusker, Deputy City Mayor and Lead Member for Planning, Tra... Approved Open
22 Jul 2026 Conservation Area Appraisals and Management Plans - Approval for Consultation, Proposed Boundary Changes, and Addition of a New Conservation Area.Salford City Council - Record of Decision I, Councillor Mike McCusker, Deputy City Mayor and Lead Member for Planning... Approved Open
22 Jul 2026 Update of the Salford City Council Local List of Heritage Assets, to include updates to existing entries, removals from the list and new additions as well as amendments to the selection criteria.Salford City Council - Record of Decision I, Councillor Mike McCusker , Deputy City Mayor and Lead Member for Plannin... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies