Salford City Council
Property / Regeneration Briefing, Monday 23 January 2023 at 3.00pm

Crescent - Site Business Plan and Development Agreement for Salford Rise

Agreed Committee 1 paper

Property / Regeneration Briefing agreed this item on Monday 23 January 2023. Below is the council's own wording, with the papers it was decided on.

Item3b

Resolved

Salford City Council - Record of Decision I Councillor Tracy Kelly, Deputy City Mayor , in exercise of the powers contained within the City Council constitution do hereby: 1. Note and endorse the Site Business Plan and Development Agreement for Salford Rise. 2. Give delegated authority to the Strategic Director, Place, and the Assistant Director, Regeneration, to approve the Site Business Plan for Salford Rise, and agree the relevant conditions associated with the approval with the English Cities Fund and the University of Salford to enable the project to be brought forward for delivery. 3. Give delegated authority for the Strategic Director, Place, City Solicitor, Chief Finance Officer and the Assistant Director, Regeneration, to enter into a Development Agreement with ECF and negotiate all financial, commercial and contractual documents and arrangements with ECF associated with the delivery of the Salford Rise project. 4. Authorise the City Solicitor to enter into and complete all necessary agreements or documents to give effect to the above recommendations. The Reasons are this will allow for S alford City Council to enter into a development agreement with ECF (English Cities Fund) as Salford Rise related to the delivery of a key piece of infrastructure on Council owned land, rather than development on a site which would be drawn down by ECF. In this instance, ECF would be appointed as Development Manager for Salford Rise, with the development agreement setting out the terms of this arrangement. Assessment of Risk : Low The source of funding: The council have successfully secured a levelling up grant £13.170m, which must be spent by March 2025. The fund is being administered via a Memorandum and Understanding (MOU) which was signed on the 8 th February. Approval to enter into a grant funding agreement with ECF for the provision of onward funding to a maximum sum of £13,710,933 was secured at Property and Regeneration Briefing on 28 th March 2022. Legal Advice obtained : Lauren Armstrong, Shared Legal Service Financial Advice obtained : Natalie Birchall, Finance Manager Procurement Advice obtained: Deborah Derbyshire, Category Manager Level 2, Procurement. HR Advice: n/a Climate Change advice: Dan Welsh, Principal Programme manager, Development Team The following documents have been used to assist the decision process. · Report of the Strategic Director, Place, to Property and Regeneration Briefing (Approval of the Crescent Development Framework 2021), 25 th January 2021. · Report of the Strategic Director, Place, to Property and Regeneration Briefing (Approval of the Crescent Strategic Master Programme and Delivery Plan), 26 th April 2021. · Report of the Strategic Director, Place, to Property and Regeneration Briefing (Salford Rise - Approval to enter into a Grant Funding Agreement with English Cities Fund), 28 th March 2022 · Report to Property/Regeneration Briefing 23 rd January 2023 Contact Officers: Kurt Partington, Head of Development [email protected] Daniel Welsh, Principal Programme manager, Development Team [email protected] * This decision is not subject to consideration by another Executive Lead Member /Director * The appropriate scrutiny committee to call-in the decision is the Growth and Prosperity Scrutiny ...
Word for word from the decision Salford published for this meeting. Source: sccdemocracy.salford.gov.uk

Follow this further

Built from Salford's papers

What the report saysPro

Report to Property / Regeneration Briefing

Recommendations

That the Deputy City Mayor:

1. Notes the content of this report; 2. Provides delegated authority for the Strategic Director, Place, and the Assistant Director, Regeneration, to approve the Site Business Plan for Salford Rise, and agree the relevant conditions associated with the approval with the English Cities Fund and the University of Salford to enable the project to be brought forward for delivery; 3. Provides delegated authority for the Strategic Director, Place, City Solicitor, Chief Finance Officer and the Assistant Director, Regeneration, to enter into a Development Agreement with ECF and negotiate all financial, commercial and contractual documents and arrangements with ECF associated with the delivery of the Salford Rise project; and 4. Authorises the City Solicitor to enter into and complete all necessary agreements or documents to give effect to the above recommendations.

Executive summary

In April 2021 the Council approved the Strategic Master Programme and Delivery Plan (SMPDP) for the Crescent. This approval resulted in the Overarching Umbrella Agreement (OUA) between the Council, ECF and University of Salford, becoming unconditional and taking full effect, providing ECF with the contractual certainty needed to begin the process of preparing Site Business Plans (SBP’s) for the various sites across the Crescent area.

A Site Business Plan has now been submitted to the Council and University for the Salford Rise project, which sits within the Crescent Innovation Zone. This report provides an overview of the content of the SBP and recommends that the Council approves the Site Business Plan.

This report also seeks approval for the Council to enter into a Development Agreement with ECF as Salford Rise relates to delivery of a key piece of infrastructure on Council owned land, rather than development on a site which would be drawn down by ECF. In this instance, ECF will therefore be appointed as Development Manager for Salford Rise, rather than Developer and the Development Agreement will set out the terms of this arrangement.

BACKGROUND DOCUMENTS: - Report of the Strategic Director, Place, to Property and Regeneration Briefing (Approval of the Crescent Development Framework 2021), 25th January 2021. - Report of the Strategic Director, Place, to Property and Regeneration Briefing (Approval of the Crescent Strategic Master Programme and Delivery Plan), 26 th April 2021. - Report of the Strategic Director, Place, to Property and Regeneration Briefing (Salford Rise – Approval to enter into a Grant Funding Agreement with English Cities Fund), 28th March 2022.

KEY DECISION: YES

The Strategic Master Programme and Delivery Plan relates to the area covered by the Crescent Development Framework which includes sites within 4 wards (Blackfriars and Trinity, Broughton, Ordsall and Pendleton and Charlestown). However, the Salford Rise site itself sits solely within the Pendleton and Charlestown ward.

DETAILS:

Background

1.1In March 2020 the City Council and University appointed the English Cities Fund as Private Sector Partner to deliver the Crescent Masterplan and all parties subsequently signed the Overarching Umbrella Agreement (OUA) – the main contract between the parties to manage implementation of the Crescent masterplan. The Umbrella Agreement is currently conditional upon:

(i) ECF preparing and submitting a new planning framework for the Crescent area. The new Crescent Development Framework was approved by the Council in January 2021 satisfying this condition. (ii) The approval of the Strategic Master Programme and Delivery Plan (SMPDP) to demonstrate how the programme will be brought forward over the next 10 years and beyond. The SMPDP, was approved in April 2021.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Crescent: Site Business Plan and Development Agreement for Salford RiseReport 339 KB DownloadRead as text

At this meeting

Whole meeting
3aPothole Action Fund 2022/23 and 2023/24Approved
3bCrescent - Site Business Plan and Development Agreement for Salford RiseThis decision

Who was there

5 of 13 attended
SA
Sharmina AugustCommittee Member, apologies
BB
Barbara BenthamCommittee Member, present
JC
Jim CammellCommittee Member, apologies
PD
Paul DennettCommittee Member, apologies
JH
Jane HamiltonGuest, expected
BH
Bill HindsCommittee Member, apologies
TK
Tracy KellyCommittee Member, present
DL
David Lancaster MBEGuest, present
MM
Mike McCuskerCommittee Member, expected
JM
John Merry CBECommittee Member, apologies
TP
Teresa PepperGuest, present
MR
Mike RelphSecretary, expected

All 13 on the meeting page

On this subject at Salford

Search all
  1. Crescent - Site Business Plan and Development Agreement for Salford RiseThis decision
  2. Approval to Award the Contract for Better Bus Routes/ Improving Journeys - Salford Crescent to MediaCityUK - Site Investigation (Matthew Mollart)Approved
  3. Crescent - Farmer Norton Site Business PlanApproved

More from Salford Property / Regeneration Briefing

All decisions
MeetingDecisionOutcome
14 Sep 2026 Retail Unit1 1 New BaileySalford City Council - Record of Decision I, Councillor Mike McCusker, Deputy City Mayor and Lead Member for Planning... Approved Open
14 Sep 2026 Housing Development at Robert Hall Street, Ordsall - Appointment of ContractorsSalford City Council - Record of Decision Affordable Housing Development - A2 Robert Hall Street, Ordsall I Councillo... Approved Open
24 Aug 2026 One New Bailey, ProposalSalford City Council - Record of Decision I Councillor Mike McCusker, Deputy City Mayor and Lead Member for Planning,... Approved Open
24 Aug 2026 One New Bailey, 2023 Rent ReviewSalford City Council - Record of Decision I Councillor Mike McCusker, Deputy City Mayor and Lead Member for Planning,... Agreed Open
24 Aug 2026 Two New BaileySalford City Council - Record of Decision I Councillor Mike McCusker, Deputy City Mayor and Lead Member for Planning,... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies