2025/26 CRSTS Consolidated Highways Programme.

Approved Planning 2 papers

Planning, Transport and Sustainable Development and Regeneration approved this item on Wednesday 12 March 2025. Below is the council's own wording, with the papers it was decided on.

Item3d

Resolved

Salford City Council - Record of Decision I, Councillor Mike McCusker, Lead Member for Planning, Transport & Sustainable Development, in exercise of the powers contained within the Council Constitution , do hereby approve: The 2025/26 CRSTS Consolidated Highways Programme The Reasons are : To enable the delivery of the projects detailed within the programme in the 2025/26 financial year. Options considered and rejected were: N/A Assessment of Risk : Failure to spend Capital Allocations on initiatives in line with Government guidelines may impact on future settlement levels, both for the City Council and for AGMA as a whole The source of funding is : 2025/26 CRSTS Consolidated Highways Legal Advice obtained : Supplied by Tony Hatton, Principal Solicitor Date: 18/02/2025 Under Part V of the Highways Act 1980 (“the Act”), the Council acting in its capacity as the highway authority, shall have general and express powers in relation to any highway maintainable at public expense by them, any work for the improvement of the highway other than the work of lighting which is expressly provided for under Section 97 of the Act. Under s41(1) the Act the authority who are for the time being the highway authority for a highway maintainable at the public expense are under a duty subject to subsections (2) and (4) to maintain the highway. Subsection (2) and (4) do not apply to the proposals contained within this report. Under s329 of the Act ‘maintenance’ includes repair. In that regard, there are no legal implications as the Council, as highway authority, is acting within its powers. However, failure to maintain the highway may have adverse implications. The proposals in the report for the programmes, once finalised scheme details within each of the specified categories of work have been submitted, will strengthen the Council’s position in defending 3 rd party highway/tripping claims. Whilst it is legally accepted that it is not possible to maintain the highway completely free of all defects, section 58 of the Highways Act 1980 provides a possible defence to a claim if it can adequately show that there was a sufficiently robust regime in place to inspect and maintain the highway provided it is adequately carried out and the Council had no prior knowledge of the defect before an alleged incident. The proposed schemes will also improve road safety, pedestrian/public safety, and encourage the further use of safer cycle routes. In relation to any proposed Traffic Regulation Orders, these should not give rise to any legal implications provided the works are carried out in accordance with the appropriate statutory requirements set out in the Road Traffic Regulation Act 1984. The proposed dropped crossings can be introduced without delay because no Traffic Regulation Order is required for these. To ensure all users have the ability to safely access and use dropped crossing facilities that the Council has installed, the Council has powers subject to exemptions under the Traffic Management Act 2004 to fine and remove vehicles that are parked at dropped crossings within any special ...
Word for word from the decision Salford published for this meeting. Source: sccdemocracy.salford.gov.uk

Follow this further

Built from Salford's papers

What the report saysPro

Report to Planning, Transport and Sustainable Development and Regeneration

Recommendations

That the Lead Member for Planning & Sustainable Development approves the 2025/26 CRSTS Consolidated Highways programme.

Executive summary

This report presents the proposed CRSTS Consolidated Highways Programme for 2025/26 for approval, providing details of the funding allocations across six categories. Two future years are also presented in the programme, giving detail of the proposed funding allocations in 2026/27 and 2027/28. Approval is not being sought for the later years at this stage to retain flexibility, but they are indicative of the potential future direction.

BACKGROUND DOCUMENTS:

- 2025/26 CRSTS Programme (Appendix ‘A’ of this report) - Report to Property & Regeneration Board: ‘CRSTS update and Strategic Maintenance Priorities’ 27/03/2023 - CRSTS Funding Settlement Letter for Greater Manchester 01/04/2022

KEY DECISION: No

1 DETAILS:

Background

1.1The Department for Transport (DfT) announced the award of the City Regions Sustainable Transport Funding (CRSTS) to the Greater Manchester Combined Authority (GMCA) on 1st April 2022. This is a five-year settlement from DfT to GMCA for all ten regions of Greater Manchester.

1.2A component of the CRSTS funding is an annual allocation for Highways Maintenance projects. This replaces the annual settlement formerly known as Block 3 received from DfT and consolidates other sources of funding into a single pot.

1.3The amount of funding allocated to Salford City Council in the CRSTS for Highway improvements per financial year is £3.143m, which has been allocated to the projects/programmes identified in this report.

1.4The funding is provided for minor infrastructure improvement projects such as: road safety schemes; structure/bridge improvements; schemes to improve walking & cycling facilities, etc.

Proposals

2.1The programme has been split into the following categories and allocations for 2025/26:

Category Allocation Local Safety Schemes £553,000 Structures & Bridges £1,390,000 Highway Maintenance £345,000 Schemes to Assist Walking & Cycling £445,000 Other Minor Works £10,000 Community Committee Schemes £400,000 TOTAL 2025/26 Allocation £3,143,000

2.2Details of the significant project allocations within the above categories are provided below. NB: lower value, self-explanatory items are not shown below but can be seen in the detailed programme which is enclosed in Appendix A.

2 2.3 Details of the proposed programme for the following two years are provided as an indication of the potential future direction. This is reflective of strategic planning and current priorities, but may change prior to approval being sought in later years. NB: The current CRSTS runs until the 2026/27 financial year. It is anticipated that it will be renewed for a further five years, with the allocation for Highways Maintenance projects remaining at the same, or an increased level.

2.4Local Safety Schemes

• Bury Old Road/Singleton Road - £300k

Delivery of a junction improvement scheme, the development of which has been funded in previous years. The works will introduce controlled pedestrian facilities at the junction, where there are currently none. NB: the estimated delivery cost has been across the following financial year to reflect the likely timescales for the works.

• A6 Manchester Road/Cleggs Lane/Armitage Avenue - £125k

Delivery of a junction improvement scheme, the development of which has been funded in previous years, similar to the above. The works will improve the pedestrian and cycle facilities at the junction. A S106 contribution of £775k from the Logistics North development is to be utilised.

• School Lane/Chapel Road Mini Roundabout - £50k

Installation of a mini roundabout at this junction to calm traffic and provide improved pedestrian facilities adjacent to Irlam Endowed Primary School.

• Broughton Road/Lissadel Street/South Langley Road - £50k

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2025/26 CRSTS Consolidated Highways Programme.Report 110 KB DownloadRead as text
PDF
2025_26 Consolidated Highways ProgrammeAppendix A 217 KB Download

At this meeting

Whole meeting

Who was there

1 of 3 attended
PC
Philip CusackInvitee, in attendance
JH
Jane HamiltonInvitee, in attendance
MM
Mike McCuskerCommittee Member, present

On this subject at Salford

Search all
  1. 2025/26 CRSTS Consolidated Highways Programme.This decision
  2. 2024-25 CRSTS Consolidated Highways Programme.Approved

More from Salford Planning, Transport and Sustainable Development and Regeneration

All decisions
MeetingDecisionOutcome
9 Sep 2026 Traffic Regulation Order 2453 - Chapel Street / Trinity Way / St Stephen Street & Ford Street, Blackfriars & Trinity and Ordsall) - Phase 1.Salford City Council - Record of Decision I, Councillor Mike McCusker, Deputy City Mayor and Lead Member for Planning... Refused Open
9 Sep 2026 City of Salford (Camp Street, Grecian Street, Neptune Gardens, & Trojan Gardens, Broughton) (No Waiting At Any Time) Order 2025.Salford City Council - Record of Decision I, Councillor Mike McCusker, Deputy City Mayor and Lead Member for Planning... Refused Open
12 Aug 2026 Irwell River Park Floating Wetland Habitats - Section 106 Contribution Expenditure.Salford City Council - Record of Decision I, Councillor McCusker, Deputy City Mayor and Lead Member for Planning, Tra... Approved Open
22 Jul 2026 Conservation Area Appraisals and Management Plans - Approval for Consultation, Proposed Boundary Changes, and Addition of a New Conservation Area.Salford City Council - Record of Decision I, Councillor Mike McCusker, Deputy City Mayor and Lead Member for Planning... Approved Open
22 Jul 2026 Update of the Salford City Council Local List of Heritage Assets, to include updates to existing entries, removals from the list and new additions as well as amendments to the selection criteria.Salford City Council - Record of Decision I, Councillor Mike McCusker , Deputy City Mayor and Lead Member for Plannin... Approved Open