Salford City Council
Property / Regeneration Briefing, Monday 9 March 2026 at 3.00pm

Pothole Action Fund 2026/27

Approved Committee 1 paper

AI summarySalford City Council approves £855,000 carriageway patching and surface repair programme for 2026/27, introducing a new in-house Hot Applied Patch Repair System delivered seasonally.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedFinal approval granted for 2026/27 Pothole Action Fund programme
Money£855,000Combined budget from three funding sources
What happens nextSeasonal delivery in 2026/27Hot-applied works in summer, conventional patching in winter
Who it affectsAll wards in SalfordCitywide highway network repairs

What was decided

The Deputy City Mayor approved the proposed programme of carriageway patching and surface repairs for 2026/27, funded through the Pothole Action Fund and associated allocations, including the introduction of a Hot Applied Patch Repair System and a seasonal delivery model. Report P1

A combined budget of £855,000 was approved, drawn from the CRSTS Pothole Action Fund, DfT transparency-return funding, and Council Revenue Reserves, to be applied as a unified patching and preventative repair programme. Report P2, P11

The Council will train and equip a dedicated team of operatives to deliver hot-applied repairs in-house, continuing the strategic shift away from outsourced delivery. Report P3, P21, P22

Why

The programme enables targeted repairs to address localised carriageway deterioration, improves durability and network resilience, and supports the Council's statutory duty to maintain the highway under the Highways Act 1980. Report P34

The Hot Applied Patch Repair System strengthens surface condition around previous safety repairs, reduces water ingress, and enhances long-term performance, while reducing waste and vehicle movements. Report P17, P24

Increasing in-house capability strengthens resilience, improves value for money and enhances quality assurance across the highways maintenance service. Report P22

What happens next

Hot-applied repairs will be prioritised during the summer period when dry, warmer conditions allow best technical performance; medium to large conventional patching will be delivered in winter when hot-applied work is not possible. Report P17, 1.3, P19

Location selection will follow established asset management procedures using condition data, inspection history and engineering judgement, with no prescriptive schedule published. Report P13, P14

Any individual project exceeding £150,000 will require a separate report to Procurement Board; external contractors may be engaged under the SCC Technical and Highways Works Framework for specialist techniques such as Hot Rolled Asphalt. Report P15, P44, P48

The money

  • £855,000 Total combined programme budget Report P2, P11, P28, P31
  • £250,000 CRSTS Pothole Action Fund allocation via DfT through GMCA Report P2, P10, P47
  • £333,000 DfT conditional maintenance uplift released following transparency return, via GMCA Report P2, P10, P47
  • £272,000 Highways off-programme funding from Council Revenue Reserves, second year of three-year £800,000 allocation Report P2, P10, P47
  • £114,804.35 Depot overhead costs at 15.51% Report P29
  • £740,195.65 Scheme delivery cost Report P30
  • £800,000 Three-year Highways off-programme revenue allocation to capital programme Report P2, P10, P47
  • £150,000 Threshold above which a separate report to Procurement Board is required Report P44

Options considered

  • Chosen: Proceed with the proposed combined programme as set out in the report. The combined funding allocations and the nature of the required works make this the most appropriate asset-led approach Report P11
  • Rejected: No alternative options. The report states no alternative options were considered

Implications

  • Financial: Programme funded by CRSTS grant, Highways Funding Block incentive grant, and Council Revenue Reserves; brings more works in-house to generate greater value for money. Report P47
  • Legal: Highways Act 1980 Section 41 duty to maintain; Section 58 provides a statutory defence provided the Council has taken reasonable care. Procurement must comply with public procurement legislation, Contractual Standing Orders and Best Value duties. Report P36, P37, P38, P41, P42
  • Equalities: Proposals support safe movement of the public and are not discriminatory; works will be programmed sensitively where they may affect specific communities or religious events. Report P33
  • Risk: Risk assessed as Low; targeted use of available funding will ensure statutory maintenance obligations are met while facilitating continuous improvement of highway infrastructure. Report P34
  • Climate: Hot-applied repairs reduce waste by avoiding full excavation and minimise carbon output through shorter repair times and fewer vehicle movements. Report P24, P25
  • Staffing: The Council will train and equip a dedicated team of operatives to deliver hot-applied repairs in-house, building on the expansion of the Highways Construction team over the past 18 months. Report P21, P22

Who and where

  • All wards in Salford Report P53
  • Highway users and the public Report P33
  • Salford City Council highways operatives (training and upskilling) Report P21, P22
  • External surfacing contractors (used for specialist techniques such as Hot Rolled Asphalt) Report P15

Timeline

  • February 2026: Current SCC Technical and Highways Works Framework ends Report P48
  • 03/02/2026: Financial implications provided by Senior Accountant Report P46
  • 2026/27: Programme delivery period for carriageway patching and surface repairs Report P2, P3
  • Summer period (2026/27): Hot-applied patch repair works prioritised due to dry, warmer conditions Report P17, 1.3
  • Winter period (2026/27): Medium to large conventional patching works delivered in-house when hot-applied materials cannot be applied Report P19, 1.3
  • August 2026: Expected end of proposed framework extension before new framework goes to market Report P48

Plain English for the jargon

  • CRSTS: City Region Sustainable Transport Settlement, a DfT fund distributed via GMCA
  • DfT: Department for Transport
  • GMCA: Greater Manchester Combined Authority
  • CSO: Contractual Standing Orders, the Council's procurement rules
  • PCR 2015: Public Contracts Regulations 2015
  • PA 2023: Procurement Act 2023
  • Hot Applied Patch Repair System: A surface treatment that heats and applies material to seal and strengthen areas around previous repairs, improving skid resistance and reducing water penetration
  • Section 41 / Section 58 Highways Act 1980: Section 41 sets the duty to maintain the highway; Section 58 provides a statutory defence where the authority took reasonable care
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4c

Resolved

Salford City Council - Record of Decision I Councillor Jack Youd, Deputy City Mayor, City Mayor and Lead Member for Finance, Support Services And Regeneration, in exercise of the powers contained within the City Council Constitution and in consultation with Cabinet, do hereby approve: The proposed programme of carriageway patching and surface repairs for 2026/27, funded through the Pothole Action Fund and associated allocations, including the introduction of a Hot Applied Patch Repair System and the seasonal delivery model set out in the accompanying report. The Reasons are : The programme enables targeted repairs to address localised carriageway deterioration, improves durability and network resilience, and supports compliance with the Council’s statutory duty to maintain the highway under the Highways Act 1980. The introduction of a Hot Applied Patch Repair System strengthens surface condition, reduces water ingress and enhances the long?term performance of previous repairs. Options considered and rejected were: No alternative options were considered. The combined funding allocations and the nature of the required works make the proposed programme the most appropriate asset-led approach. Final Approval is granted for the 2026/27 Pothole Action Fund programme with a total budget of £855,000, comprising CRSTS Pothole Action Fund allocation, DfT transparency?return funding and Council Revenue Reserves. The programme will proceed as a unified patching and preventative repair programme as described in the briefing. Assessment of Risk: Low. The targeted use of the available funding will ensure that statutory maintenance obligations are met and that the service continues to apply an asset?management approach to prevent further deterioration and reduce longer?term liabilities. Source of Funding: The programme is funded from: CRSTS Pothole Action Fund allocation (£250,000), DfT conditional maintenance uplift released following the transparency return (£333,000), and Highways off?programme Revenue Reserve allocation (£272,000). These sources combine to create an overall budget of £855,000. Legal Advice Obtained: Helen Chapman and Tony Hatton In relation to the Highways Act 1980 the requirement to maintain pot holes will fall under the Council’s general duty as Highway Authority to maintain highways maintainable at public expense. Section 58 of the Highways Act 1980 provides a statutory defence to the Section 41 duty in an action against the Highway Authority for having failed in its duty to maintain a highway within its control. Section 58 states that it is a defence (without prejudice to any other defence or the application of the law relating to contributory negligence) to such action if the authority had taken such care as in all the circumstances was reasonably required to secure that the part of the highway to which the action relates was not dangerous for traffic. Section 58 lists the matters a Court will have regard to in relation to the defence. This includes such matters as the character of the highway, appropriate standard of maintenance, expected state of repair and traffic expected to use it. It also includes 1. whether the highway authority knew, or could reasonably have been expected to know, that the condition of ...
Word for word from the decision Salford published for this meeting. Source: sccdemocracy.salford.gov.uk

Follow this further

Built from Salford's papers

What the report saysPro

Report to Property / Regeneration Briefing

Recommendations

That the Deputy City Mayor and Lead Member for Finance, Support Services and Regeneration approves: Approves the proposed carriageway patching activity for 2026/27, including the adoption of a Hot Applied Patch Repair System as part of our maintenance strategy.

Executive summary

For 2026/27, a total budget of £855,000 is available to support carriageway patching and surface repairs across the highway network. This consists of £250,000 from the City Region Sustainable Transport Settlement Pothole Action Fund, £333,000 released by the Department for Transport following the Council’s submission of its transparency return, and £272,000 from the Council’s Highways off-programme funding held in Reserves. The £272,000 forms the second year of a three-year £800,000 allocation approved to relieve pressure on the highways maintenance revenue budget.

The funding will be applied collectively to deliver a single programme focused on preventative surface repairs, hot-applied patch treatment and medium to large conventional patching where required. The introduction of a Hot Applied Patch Repair System will improve durability, reduce water ingress, prolong the life of previous safety repairs and support a more sustainable approach through reduced waste and fewer vehicle movements. The programme continues the strategic shift towards in-house delivery by training and

1 equipping Salford operatives to undertake hot-applied patching during the optimal summer period and conventional patching during the winter period.

BACKGROUND DOCUMENTS:

N/A

KEY DECISION: Yes-

DETAILS:

1.0The Pothole Action Fund and Associated Allocations

For 2026/27, three separate funding sources support the citywide programme of carriageway patching and surface repairs. The City Region Sustainable Transport Settlement provides £250,000 for pothole and patching activity. The Department for Transport has released £333,000 as the final 25% of its conditional maintenance uplift following timely submission of the Council’s transparency return. A further £272,000 has been allocated from the Council’s Revenue Fund as part of a three year £800,000 programme to support the highways maintenance revenue service, which continues to face increasing financial pressure as a result of inflation and the managed decline of the network.

These funds create a combined programme budget of £855,000. They will be used flexibly to deliver preventative treatments and structural patching in line with asset management principles and statutory duties.

1.1Scope of Works

An individual list of locations is not included within this report. The volume of potential sites makes a prescriptive schedule impractical and inconsistent with the asset led approach. Hot applied patch repairs will be targeted at locations where surface deterioration has developed around previous permanent repairs and where water ingress threatens further deterioration. Medium to large structural patches will continue to be programmed at sites where engineering assessment identifies significant localised failure that cannot be resolved through surface sealing alone.

Location selection will follow established asset management procedures using condition data, inspection history and engineering judgement. It is not envisaged that conventional patching works will be outsourced, as these

2 activities will be undertaken by the in-house team wherever possible. There may, however, be occasions where specialist techniques such as Hot Rolled Asphalt repairs require support from an external surfacing contractor to ensure the correct materials and workmanship standards are achieved.

1.2Hot Applied Patch Repair system

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Pothole Action Fund 2026/27Report 93 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 12 attended
BB
Barbara BenthamCommittee Member, present
JC
Jim CammellCommittee Member, present
PD
Paul DennettCommittee Member, absent
TK
Tracy KellyCommittee Member, absent
MM
Mike McCuskerCommittee Member, present
JM
John Merry CBECommittee Member, absent
WN
Wilson NkurunzizaInvitee, in attendance
TP
Teresa PepperCommittee Member, present
MR
Mike RelphSecretary, expected
GR
Gina ReynoldsInvitee, in attendance
HR
Hannah Robinson-SmithCommittee Member, absent
JY
Jack YoudCommittee Member, present

On this subject at Salford

Search all
  1. Pothole Action Fund 2026/27This decision
  2. Pothole Action Fund 2022/23 and 2023/24Approved

More from Salford Property / Regeneration Briefing

All decisions
MeetingDecisionOutcome
14 Sep 2026 Retail Unit1 1 New BaileySalford City Council - Record of Decision I, Councillor Mike McCusker, Deputy City Mayor and Lead Member for Planning... Approved Open
14 Sep 2026 Housing Development at Robert Hall Street, Ordsall - Appointment of ContractorsSalford City Council - Record of Decision Affordable Housing Development - A2 Robert Hall Street, Ordsall I Councillo... Approved Open
24 Aug 2026 One New Bailey, ProposalSalford City Council - Record of Decision I Councillor Mike McCusker, Deputy City Mayor and Lead Member for Planning,... Approved Open
24 Aug 2026 One New Bailey, 2023 Rent ReviewSalford City Council - Record of Decision I Councillor Mike McCusker, Deputy City Mayor and Lead Member for Planning,... Agreed Open