CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Salford City Council
Cabinet, Tuesday 25 August 2026 at 10.00am

Nature, Towns and Cities Programme - Nature City Accreditation and Refresh of the Greenspace Strategy

Approved Executive 1 paper

AI summarySalford Cabinet approves bid for Nature City accreditation and a refresh of the 2019 Greenspace Strategy, drawing on almost £1 million of National Lottery Heritage Fund grant secured with Manchester City Council.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedDecision by City Mayor under Cabinet powers
MoneyAlmost £1 million external grantAbout £700,000 funds staff capacity across both councils
What happens nextSelf-assessment to start summer 2026Accreditation application due spring 2027
Who it affectsAll wards in SalfordKey Decision, affects whole city

What was decided

The Cabinet approved preparing and submitting an application for Nature Towns and Cities Foundation Accreditation, also known as Nature City status. Report P25, P26

The Cabinet approved reviewing and refreshing the council's Greenspace Strategy to reflect current evidence, corporate priorities and the accreditation framework. Report P25, P26

The Cabinet approved the programme of stakeholder and public consultation required for the refreshed strategy and accreditation submission. Report P25, P26

Why

Achieving Nature City accreditation is a required output of the NTC grant agreement with the National Lottery Heritage Fund, and failing to deliver it could lead to grant recovery or reputational risk. Report P1, P21, P53

The 2019 Greenspace Strategy needs updating to reflect new national policy on climate adaptation, biodiversity recovery, Biodiversity Net Gain and Local Nature Recovery Strategies. Report P21, P22, P23

An initial equality screening found an overall positive impact and no disproportionate adverse effects on protected groups, so a full Equality Impact Assessment was not required at this stage. Report P127, P129, P131

What happens next

Complete the NTC Self-Assessment in summer 2026, develop the refreshed vision through summer and autumn 2026, draft the strategy in autumn 2026 and run public consultation in winter 2026. Report P75

Finalise the Greenspace Strategy in early 2027 following consultation, then submit the Foundation Accreditation application in spring 2027. Report P75

Present the refreshed Greenspace Strategy for formal approval through the council's governance process, with progress reported through existing programme governance. Report P75, P76, P50

The money

  • almost £1 million External funding secured through the Nature Towns and Cities Capacity Building Fund Report P20
  • Approximately £700,000 Supports additional programme capacity across Salford and Manchester over three years Report P20, P110

Options considered

  • Chosen: Proceed with NTC Accreditation and refresh the Greenspace Strategy. Delivers grant outputs, updates strategy, strengthens partnerships and investment readiness, with risks judged manageable Report P61, P62, P69, P70
  • Rejected: Refresh the Greenspace Strategy without seeking accreditation. Would miss an approved grant output, lose national recognition and risk challenge from the funder Report P63, P64, P65
  • Rejected: Maintain the existing Greenspace Strategy and do not proceed with accreditation. Fails to deliver a grant output, leaves strategy outdated, reduces future investment prospects and increases financial and reputational risk Report P66, P67

Implications

  • Legal: Gaining accreditation is a requirement of the NTC grant terms; non-compliance could lead to grant recovery, reduction, suspension or withholding. Report P1, P53
  • Financial: Programme activities are funded from the existing NTC grant; no additional council revenue is required at this stage. Report P2, P54
  • Equalities: Initial screening found an overall positive impact with no disproportionate adverse effects; equality impacts will be monitored through the consultation. Report P127, P129, P131
  • Climate: The accreditation and refreshed strategy will support the council's Climate Change and Biodiversity Strategies through nature-based solutions and habitat enhancement. Report P57, P58, P84
  • Risk: Residual risks after mitigation are judged low and proportionate to the benefits, covering delivery, timing, engagement, governance and future funding. Report P82, P83
  • Staffing: All posts needed for the programme are already funded through the NTC grant and have been recruited; no additional HR implications arise. Report P2, P56

Who and where

  • All wards across the city of Salford Report P89
  • Residents in communities currently under-represented in environmental decision making Report P34, P129
  • Community organisations, voluntary groups, environmental organisations, educational institutions and public sector partners Report P34
  • Manchester City Council as joint delivery partner Report P20, P95

Timeline

  • Summer 2026: Complete Nature Towns and Cities Self-Assessment Report P75
  • Summer to Autumn 2026: Develop refreshed vision for green and blue infrastructure through stakeholder engagement Report P75
  • Autumn 2026: Prepare the draft Greenspace Strategy Report P75
  • Winter 2026: Undertake public and stakeholder consultation Report P75
  • Early 2027: Finalise the Greenspace Strategy following consultation Report P75
  • Spring 2027: Submit the Nature Towns and Cities Foundation Accreditation application Report P75

Plain English for the jargon

  • Nature Towns and Cities (NTC): A national programme led by the National Lottery Heritage Fund, Natural England and the National Trust supporting towns and cities to put nature at the heart of local decision making.
  • Nature City Foundation Accreditation: Independent recognition that a council has the leadership, governance, partnerships and strategic framework to deliver long-term environmental improvements and attract investment.
  • Greenspace Strategy: Salford's strategic framework for green and blue infrastructure, first adopted in 2019 as a Supplementary Planning Document and now being refreshed.
  • Green and blue infrastructure: Networks of natural and semi-natural spaces, such as parks, rivers and wetlands, that provide environmental, health and community benefits.
  • Biodiversity Net Gain: A national policy requirement that development delivers measurable improvements for biodiversity compared with the pre-development baseline.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5

Resolved

Salford City Council - Record of Decision (Cabinet) I Paul Dennett, City Mayor, in exercise of the powers contained within the City Council Constitution do hereby approve: The development and submission of an application for Nature Towns and Cities Foundation Accreditation to enable Salford to achieve recognised Nature City status. The review and refresh of the council's Greenspace Strategy to ensure it reflects current evidence, corporate priorities and the requirements of the Nature Towns and Cities accreditation framework. The programme of stakeholder and public consultation required to inform the refreshed Greenspace Strategy and accreditation submission. The Reasons are : The council has secured almost £1 million of external funding through the Nature Towns and Cities (NTC) programme, delivered in partnership with Manchester City Council, to strengthen strategic planning for green and blue infrastructure, improve access to nature, increase community involvement and develop a pipeline of investable projects. Achieving Nature City accreditation is one of the agreed outputs of the funded programme and demonstrates the council's commitment to delivering healthier, greener and more climate-resilient neighbourhoods. The revised strategy will provide an updated evidence base, strengthen cross-directorate working, support future investment opportunities and ensure the council continues to meet its ambitions for biodiversity, climate resilience and reducing health inequalities. Failure to deliver the accreditation could affect delivery of the approved grant outputs and may expose the council to financial and reputational risk Options considered and rejected were: The council has considered the following options. Option 1 – Proceed with Nature Towns and Cities Accreditation and refresh the Greenspace Strategy (Preferred) This option delivers the approved outputs of the Nature Towns and Cities grant, updates the council's strategic approach to green and blue infrastructure and provides an opportunity to strengthen partnership working, community engagement and future investment readiness. Benefits include: delivery of grant commitments; improved strategic planning; stronger evidence base; enhanced investment readiness; improved partnership working; updated corporate policy; greater alignment with climate, biodiversity and health priorities. Risks are considered manageable through the governance arrangements established for the programme. Option 2 – Refresh the Greenspace Strategy without seeking accreditation This option would update the council's strategic framework but would fail to deliver one of the approved outputs within the Nature Towns and Cities funding agreement. While some strategic benefits would still be achieved, opportunities associated with independent accreditation, national recognition and investment confidence would be reduced. This option also increases the risk of challenge from the funding body regarding delivery of approved programme outputs. Option 3 – Maintain the existing Greenspace Strategy and do not proceed with accreditation This option would require no additional programme activity beyond existing commitments. However, it would: fail to deliver one of the agreed grant outputs; leave the council operating under an increasingly outdated strategy; reduce opportunities to secure future external investment; weaken strategic alignment with current environmental policy; increase financial and reputational risk. This option is not recommended. a) Preferred option and rationale Option 1 is the preferred option. It delivers the commitments contained within the approved ...
Word for word from the decision Salford published for this meeting. Source: sccdemocracy.salford.gov.uk

Follow this further

Built from Salford's papers

What the report saysPro

Report to Cabinet

Supplied by: Richard Purcell, Legal Services [email protected] Date: 1st June 2026 Gaining Nature Towns and Cities accreditation is an element and requirement of the approved grant purposes of the NTC grant funding terms and conditions the Council is subject to. Failure by the Council to comply with the approved grant purpose and NTC grant terms could result in recovery/repayment, reduction, suspension and/or withholding of the grant. ________________________________________ FINANCIAL IMPLICATIONS:

Supplied by: Ethan Bestwick, Accountant [email protected] Date: 28th May 2026 Funding source: Nature town and cities – National Lottery Heritage Fund All time required to complete the accreditation will be covered by the staff employed through the NTC grant. There are no additional costs if we achieve nature city status. ________________________________________ PROCUREMENT IMPLICATIONS:

Supplied by: Heather Stanton, Procurement [email protected] Date: 8th June 2026 No procurement is required ________________________________________ HR IMPLICATIONS: N/A ________________________________________ INNOVATE / BEST VALUE:

A. Continuous improvement

The NTC Accreditation demonstrates a vision for green and blue spaces that is co- designed and ambition, that is striving for continuous improvements

B. Leadership

The NTC accreditation demonstrates the commitment and leadership for improvements to green and blue spaces that benefit everyone and everything that the Council does.

C. Governance

The NTC accreditation sets out clear governance and decision making alongside a clear plan for improvements.

D. Culture

The NTC accreditation supports co-design and raising awareness of why green and blue spaces are so important, and embraces a culture of working in partnership.

E. Use of resources

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Nature, Towns and Cities Programme: Nature City Accreditation and Refresh of the Greenspace StrategyReport 200 KB DownloadRead as text

At this meeting

Whole meeting
3Minutes of the Previous MeetingOn the agenda 42026/27 Revenue Budget Monitoring and Capital Budget Monitoring - Quarter 1Approved
5Nature, Towns and Cities Programme - Nature City Accreditation and Refresh of the Greenspace StrategyThis decision

Who was there

13 of 27 attended
PD
Paul DennettChair, present
TK
Tracy KellyDeputy Chair, present
MB
Michele BarnesCommittee Member, present
BB
Barbara BenthamCommittee Member, present
JC
Jim CammellCommittee Member, present
PC
Philip CusackCommittee Member, present
MM
Mike McCuskerCommittee Member, present
HR
Hannah Robinson-SmithCommittee Member, present
JM
Joshua Mark BrooksInvitee, present
JH
Jane HamiltonInvitee, present
WN
Wilson NkurunzizaInvitee, present
JP
James PradyInvitee, present

All 27 on the meeting page

More from Salford Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 Crisis Resilience Fund 2026/27Salford City Council - Record of Decision I Paul Dennett, City Mayor, in exercise of the powers contained within the ... Noted Open
25 Aug 2026 2026/27 Revenue Budget Monitoring and Capital Budget Monitoring - Quarter 1Salford City Council - Record of Decision (Cabinet) 2026/27 – Revenue Budget Monitoring – Quarter 1 I Paul Dennett, C... Approved Open
11 Aug 2026 Proposal to designate a citywide Additional HMO Licensing Scheme for properties that fall within the Definition of Section 257 Houses in Multiple Occupation of the Housing Act 2004Salford City Council - Record of Decision (Cabinet) I, Tracey Kelly, Statutory Deputy City Mayor, in exercise of the ... Approved Open
11 Aug 2026 Planned Carriageway Patching Programme - Local Highway Maintenance Fund 2026/27Salford City Council - Record of Decision (Cabinet) I, Tracey Kelly, Statutory Deputy City Mayor, in exercise of the ... Approved Open
28 Jul 2026 Library Strategy - Vision and Strategy WorkSalford City Council - Record of Decision I Paul Dennett, City Mayor , in exercise of the powers contained within the... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies