Renewal of over 100kW electricity contract for Salford City Council (Majid Maqbool)

Approved Committee 1 paper

AI summarySalford City Council's City Mayor approved a 24 month, £7,876,912 electricity supply contract with Drax Energy Solutions Ltd, costing £3,938,456 a year, a 13% rise on current costs, after rejecting a costlier 12 month option.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApproved24 month over 100kW electricity supply via direct award
Money£3,938,456 per annum, £7,876,912 total13% increase on current annual cost of £3,486,375
What happens nextContract starts 01/10/2026, ends 30/09/2028Decision comes into force 2 October 2026 unless called in
Who it affectsAll council buildings and schoolsCorporate, PFI schools, schools, Pendleton Together sites

What was decided

The City Mayor approved a 24 month direct award contract for over 100kW electricity supply to Drax Energy Solutions Ltd under Manchester Framework TC970. Report P1, P16, P17

The contract is for 100% renewable source electricity, with prices obtained for both 12 and 24 month durations and the longer option chosen for budget certainty. Report P17, P28, P34

Why

Wholesale electricity prices rose over the last year due to geopolitical events including the US, Israel and Iran conflict and disruption risks to the Strait of Hormuz, and new non-commodity charges such as the Nuclear Asset Base levy and higher Climate Change Levy from April 2027. Report P12, P13

The 24 month option was preferred over 12 months because it delivers a lower annual cost (£3,938,456 versus £3,994,970) and provides two years of budget certainty against current market volatility. Report P21, P26, P27, P28, P29

What happens next

Drax Energy Solutions Ltd begins supplying electricity from 01/10/2026, funded from the general fund revenue budget and schools' devolved revenue budgets. Report P1, P48

The decision is open to call-in by the Growth and Prosperity Panel and Overview Scrutiny Panel, with the call-in period ending at 4.00 p.m. on 2 October 2026.

The money

  • £3,938,456 per annum Recommended 24 month contract annual value with Drax Energy Solutions Ltd Report P1, P26
  • £7,876,912 Total contract value over 24 months Report P1
  • £452,081 Annual cost increase under 24 month option, 13% on current costs Report P26, P29
  • £3,994,970 Annual cost of rejected 12 month option, 14.6% increase Report P21, P22
  • £508,594 Annual cost increase under rejected 12 month option Report P21, P22
  • £3,486,375 Current annual electricity cost Report P20, P21, P26, P57

Options considered

  • Chosen: 24 month contract with Drax Energy Solutions Ltd. Lower annual cost than the 12 month option and provides two years of budget certainty amid current market volatility and Middle East conflict risk Report P27, P28, P29, P57, P59
  • Rejected: 12 month contract with Drax Energy Solutions Ltd. Would cost £3,994,970 a year, a 14.6% increase, £56,514 more per year than the 24 month option Report P19, P21, P22, P57

Implications

  • Financial: Annual electricity spend rises by £452,081 (13%) to £3,938,456, funded from the general fund revenue budget and schools' devolved revenue budgets. A 24 month fixed rate provides certainty and is £56,514 per year cheaper than the 12 month alternative. Report P26, P29, P48, P57
  • Risk: Assessment of risk is low. Failure to renew by October 2026 would trigger default deemed contract rates that are considerably higher, and further non-commodity cost increases include a new Nuclear Asset Base levy and a Climate Change Levy rise from 1 April 2027. Report P11, P13, P46, P56
  • Legal: Legal advice confirms the award follows a compliant call-off under the Manchester City Council framework and meets Contractual Standing Orders; value above £1,000,000 requires City Mayor approval on Procurement Board recommendation. Report P51, P52, P53, P54
  • Climate: The contract is 100% renewable source electricity at no extra premium, supporting the council's climate change commitments. Report P34, P62
  • Equalities: Procurement is for energy supply to the council's buildings and schools; no specific equality impact assessment is identified in the report. Report P44, P45

Who and where

  • Salford City Council corporate buildings Report P20, P25
  • PFI schools in Salford Report P20, P25
  • Salford schools (devolved budgets) Report P20, P25, P48
  • Pendleton Together sites Report P20, P25
  • All wards across the city Report P65

Timeline

  • October 2024: Current NHH electricity contract agreed for 24 months Report P4
  • 03/09/2026: Financial advice provided by Rafeeah Khan, Senior Accountant Report P55
  • 5th September 2026: Legal advice provided by Richard Purcell Report P50
  • 21 September 2026: Decision signed by the City Mayor
  • 25 September 2026: Decision published
  • 01/10/2026: New contract start date with Drax Energy Solutions Ltd Report P1
  • 2 October 2026 at 4.00 p.m.: Decision comes into force unless called in
  • 1 April 2027: Climate Change Levy increase expected Report P13
  • 30/09/2028: Contract end date Report P1

Plain English for the jargon

  • NHH electricity: Non-Half-Hourly electricity, metered supplies that are not read every half hour, typically smaller commercial and public sector sites
  • Over 100kW electricity: Larger electricity supply connections exceeding 100 kilowatts, used by the council's bigger buildings and schools
  • Direct award / call-off: A procurement method where the buyer purchases directly from a supplier on an existing framework agreement without running a fresh competition
  • Manchester Framework TC970: A multi-supplier framework for electricity and electricity related services, set up by Manchester City Council, running from September 2023 with extension options
  • Non-commodity elements: The non-energy parts of an electricity bill, such as network charges, levies, taxes and policy costs
  • Nuclear Asset Base (RAB): A mandatory government charge to fund upfront construction costs of new nuclear power stations
  • Climate Change Levy (CCL): A government tax on energy supplied to non-domestic users, expected to rise from 1 April 2027
  • PFI schools: Schools whose buildings are managed under a Private Finance Initiative arrangement
  • Pendleton Together: The organisation responsible for housing and related services in the Pendleton area of Salford
  • Proclass Classification: A procurement coding system used to categorise the type of goods, services or works being bought
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5b

Resolved

Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Board and in exercise of the powers contained within the Council Constitution do hereby: approve to Award energy supply contract for over 100KW electricity supply, as detailed in the table below: Detail required Answers Title/ Description of Contracted Service/Supply/Project Over 100KW electricity supply contract Procurement Reference numbers (DN and CR number supplied by Procurement) S1051 Name of Successful Contractor Drax Energy Solutions Ltd Supplier Registration Number (to be supplied by Procurement 05893966 Proclass Classification No. (to be completed by procurement) 371000 Type of organisation (to be supplied by Procurement) Public Limited Company Status of Organisation (to be supplied by Procurement) Non-SME Contract Value (£) £3,938,456 per annum Total contract value £ (including extensions) £7,876,912 total project value Contract Duration 24 months Contract Start Date 01/10/2026 Contract End Date 30/09/2028 Optional Extension Period 1 0 months Optional Extension Period 2 0 months Who will approve each Extension Period? Procurement Board (extension > £150k) Contact Officer (Name & number) Lead Service Group Place How the contract was procured? (to be supplied by procurement) Direct Award/ Call off Framework Details (where applicable) (procurement body, framework reference & title, start/ end date TC970 – Supply of electricity and electricity related services Funding Source Revenue Budget Ethical Contractor (EC): Mayor’s Employment Charter Choose an item. EC: Committed to sign The Mayor’s Employment Charter N/A EC: Committed to the principles outlined in the Mayor’s Employment charter Yes EC: Accredited Living Wage Employer No EC: Committed to becoming Accredited Living wage Employer Yes ? The Reasons are: following the procurement of over 100KW contract for the supply of electricity via a fully compliant Manchester Framework, prices were obtained from the direct award supplier, Drax Energy Solutions for 12 and 24 month contract durations. The 24 month contract will result in a cost of £3,938,456 per annum. This amounts to a an increase in annual costs of £452,081 per annum (13%). Options considered and rejected were a 12 month fixed contract duration that would result in a bigger increase of £3,994,970 (14.6%). A 24 month contract provides budget certainty for the next 2 years and thereby offering protection from the present short term geopolitical risks and help in easing budget pressures. Assessment of Risk : Low. The source of funding is : General revenue budget and schools devolved budgets. Legal Advice obtained from: Richard Purcell, Legal Services. Financial Advice obtained from: Rafeeah Khan, Senior Accountant. Procurement Advice obtained from: Heather Stanton, Category Manager. HR Advice obtained: N/A. Climate Change Implications obtained from: Majid Maqbool, Energy Manager. Contact Officer: Majid Maqbool Telephone number: 0161 607 6987 The appropriate Scrutiny Committee to call-in the decision is the Growth and Prosperity Panel and Overview Scrutiny Panel. Signed: Dated 21 st September 2026 City Mayor FOR DEMOCRATIC SERVICES USE ONLY: * This decision was published on 25 September 2026. * This decision will come in force at 4.00 p.m. on 2 October 2026 unless it is called-in in ...
Word for word from the decision Salford published for this meeting. Source: sccdemocracy.salford.gov.uk

Follow this further

Built from Salford's papers

What the report saysPro

Report to Procurement Board

Recommendation

That Procurement Board recommends Paul Dennett, City Mayor, approve the award of a 24 month Contract for over 100KW electricity to Drax Energy Solutions, as detailed in the table below: Detail required Answers Title/Description of Contracted Over 100KW electricity supply contract Service/Supply/Project Procurement Reference numbers (DN and S1051 CR number supplied by Procurement) Name of Successful Contractor Drax Energy Solutions Ltd Supplier Registration Number 05893966 (to be supplied by Procurement Proclass Classification No. 371000 (to be completed by procurement) Type of organisation Public Limited Company (to be supplied by Procurement) Status of Organisation Non-SME (to be supplied by Procurement) Contract Value (£) £3,938,456 per annum Total contract value £ (including £7,876,912 total project value extensions) Contract Duration 24 months Contract Start Date 01/10/2026 Contract End Date 30/09/2028 Optional Extension Period 1 0 months Optional Extension Period 2 0 months Who will approve each Extension Period? Procurement Board (extension > £150k) Contact Officer (Name & number) Lead Service Group Place How the contract was procured? Direct Award/ Call off (to be supplied by procurement) Framework Details (where applicable) TC970 – Supply of electricity and electricity (procurement body, framework reference related services & title, start/ end date Funding Source Revenue Budget Ethical Contractor (EC): Mayor’s Choose an item. Employment Charter N/A EC: Committed to sign The Mayor’s Employment Charter

EC: Committed to the principles outlined Yes in the Mayor’s Employment charter EC: Accredited Living Wage Employer No EC: Committed to becoming Accredited Yes Living wage Employer ☒

Executive summary

The purpose of this report is to seek approval for the award of the above mentioned contract.

The current NHH electricity contract was agreed as of October 2024 for a period of 24 months and is therefore up for renewal as of 30 September 2026.

This report outlines the procurement strategy utilised to re-procure the contract and to seek approval to agree the new contract duration.

BACKGROUND DOCUMENTS:

Manchester Multi-supplier Framework TC970

KEY DECISION:

Yes - the total value over the life of the contract exceeds £350,000

DETAILS:

Background

Energy contracts must be agreed on an ongoing basis following a fixed period of contract duration, as failure to renew will result in the default deemed contract rates being applied which are considerably higher. The length of a contract is variable from 12 months and up to several years, subject to wholesale price movements and suppliers’ risk appetite.

Since the acceptance of present electricity contract in 2024, wholesale electricity price trend has been on a slightly upwards trajectory in the first 12 months following some price increases in the non-commodity elements that make up the unit rate, with the wholesale price increase reaching a peak around February 25 following the new American Administration and a change in policy shift, particularly with regards to trade tariffs and the rising US-Iran tensions. The major market volatility and price shock was seen at end of February 2026 following the escalation and outbreak of direct military conflict between the US, Israel and Iran. Whilst prices have eased off slightly over the last few months, they remain at a higher level over the last 12 months due to the continued uncertainty and in particular with regards to disruption of supply risks to the Strait of Hormuz.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Renewal of over 100kW electricity contract for Salford City Council (Majid Maqbool)Report 174 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

4 of 45 attended
PC
Philip CusackChair, present
PD
Paul DennettCommittee Member, apologies
TK
Tracy KellyCommittee Member, present
MM
Mike McCuskerCommittee Member, present
MB
Michele BarnesCommittee Member, expected
BB
Barbara BenthamCommittee Member, present
JC
Jim CammellCommittee Member, expected
HR
Hannah Robinson-SmithCommittee Member, expected
CH
Chris HowlSecretary, expected
TC
Thomas CurranCouncil Staff, expected
DB
Deborah BlackburnCouncil Staff, expected
SR
Samuel RussellCouncil Staff, expected

All 45 on the meeting page

On this subject at Salford

Search all
  1. Renewal of over 100kW electricity contract for Salford City Council (Majid Maqbool)This decision
  2. Over 100KW Electricity Contract Renewal (Majid Maqbool)Approved
  3. Request for Approval - Contract Award - Insurance Policy and Cover Renewals - Cliff PeacockApproved
  4. Request for Approval - Insurance Policy and Cover RenewalsApproved
  5. Request for approval - Contract renewal - Over 100kW Electricity and Unmetered Street LightingApproved
  6. Insurance Policy & Cover Renewals - Cliff PeacockApproved

More from Salford Procurement Board

All decisions
MeetingDecisionOutcome
21 Sep 2026 Approval to Procure All Age Carers Service (Paul Walsh/ Emma Higham/ Jessica Ta'ati)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Approval to Award the Contract for Adult Social Care Delivery Partner (Jon Manzoni/ Lee Thompson/ Matt Drogan)Salford City Council – Record of Decision I (Councillor Cusack, Lead Member for Corporate Services and Chairman of th... Approved Open
21 Sep 2026 Charles House, Eccles – Completion of Demolition Works (Sarah Malone)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open
21 Sep 2026 Bury Old Road/ Singleton Road Junction Improvement Scheme (Usman Zubair)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open
21 Sep 2026 Approval to Award the Contract for the continued use of the Line of Business System for Planning, Building Control and Local Land and Property Gazetteer (Anthony Stephenson)Salford City Council – Record of Decision I (Councillor Cusack, Lead Member for Corporate Services and Chairman of th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies