Roofing Repairs to Council Properties

Agreed Executive 1 paper

Cabinet agreed this item on Wednesday 29 September 2021. Below is the council's own wording, with the papers it was decided on.

Item11/21

Resolved

Agreed:- (1) that approval be given to authorise the Director – Housing to award contracts for the delivery of Roofing Repairs to: - (a) Hardyman Group Limited and Roy Hankinson Limited – Lot 1 Pitched Roofing Repairs, for the sum of approximately £796,500 (£265,500 per annum) to Hardyman Group / £265,500 (£88,500 per annum) to Roy Hankinson Limited and for a period of 3 years, from 1 October 2021 to 30 September 2024; (b) IJS Roofing and Building Limited and Hardyman Group Limited – Lot 2 Built Up Felt and Sheet Roofing Repairs, for the sum of approximately £888,750 (£296,250 per annum) to IJS Roofing and Building Limited / £296,250 (£98,750 per annum to Hardyman Group Limited and for a period of 3 years, from 1 October 2021 to 30 September 2024; (c) Roy Hankinson – Lot 3 Asphalt Roofing Repairs, for the sum of approximately £453,000 (£151,000 per annum) and for a period of 3 years, from 1 October 2021 to 30 September 2024; (2) that the Director – Law and Governance and Monitoring Officer be authorised to enter into appropriate contracts for Roofing Repairs with Hardyman Group Limited, Roy Hankinson Limited and IJS Roofing and Building Limited.
Word for word from the decision Sandwell published for this meeting. Source: sandwell.moderngov.co.uk

Follow this further

Built from Sandwell's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Roofing Repairs to Council PropertiesReport 133 KB Copy on its way

More from Sandwell Cabinet

All decisions
MeetingDecisionOutcome
12 Mar 2025 Levelling up Partnership Update- (1) the progress update on the delivery of the Levelling Up Partnership is received; (2) a further progress report ... Decided Open
12 Mar 2025 Quarter 3 Budget Monitoring 2024/25Resolved that the financial monitoring position as at 31 December 2024 (Quarter 3) is received and referred to the Bu... Decided Open
12 Mar 2025 Cradley Heath Community Centre - Future OptionsResolved :- (1) that Cradley Heath Community Centre, Cradley Heath, B64 5JG is declared as being surplus to all Counc... Approved Open
12 Mar 2025 Housing Repairs and Maintenance Contracts 2025/26Resolved :- (1) that the Executive Director of Place is authorised in consultation with the Executive Director of Fin... Decided Open
12 Mar 2025 Council House New Build ProgrammeResolved :- (1) that the previous decision of Cabinet (Minute No. 140/22 (2) and (3) dated 22 June 2022) in relation ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies