Cabinet, Wednesday 22 June 2022 at 3.30pm

Council new build homes on land at West End Avenue, Smethwick

Approved Executive 4 papers

Cabinet approved this item on Wednesday 22 June 2022. Below is the council's own wording, with the papers it was decided on.

Item13

Resolved

- (1) That approval be given to develop approximately 3002.3 m 2 of land at West End Avenue Smethwick with new council housing for affordable rent, subject to planning permission, as shown for identification purposes only at Appendix 1. (2) That the Director of Finance be authorised to allocate adequate resources from the Council’s Housing Revenue Account to deliver the scheme and to utilise grant funding offered by Homes England, under the extended Homes England Strategic Partnership 1 Programme 2016 to 2021 to assist with the delivery of the project. 1.3 In connection with 1.1 and 1.2 above, approval be given to authorise the necessary steps for the delivery of the proposed project, including: a) the Director of Regeneration and Growth in consultation with the Director of Finance and the Director of Housing be authorised to prepare tendering documentation and subsequently procure, in accordance with any statutory regulations and the Council’s Procurement and Financial Regulations; b) execute any requirements in accordance with the Homes England Delivery Partner Dynamic Purchasing System (DPS) framework including appointing a contractor/contractors to develop, on behalf of the Council, the proposed housing scheme; to enter into or execute under seal any financial agreement in relation to the Homes England grant on terms and conditions to be agreed by the Director of Finance; c) that any necessary exemptions are made to the Council’s Procurement and Contract Procedure Rules to enable the course of action referred to b above to proceed; d) subject to a, b and c above, the Director – Monitoring Officer be authorised to enter into or execute under seal any documentation in relation to award of the contract and/or development/partnership agreement, Homes England developer status, licence, undertaking, framework joining agreement, any consents or applications required for Planning or Highways appertaining to the delivery of the scheme and any other agreements with the procured contractor(s) and with the Homes England, as may be deemed necessary to facilitate development of the site with a housing scheme as described in below on terms and conditions to be agreed by the Director of Regeneration and Growth; e) the Director of Regeneration and Growth in consultation with the Director of Housing and the Director of Finance be authorised to accept a tender of up to 10% above the approved estimated costs as a contingency to mitigate uncertain market conditions and inflationary cost uplifts. f) Subject to the practical completion of each property, the Director of Housing be authorised to manage and let the properties built in accordance with the Council’s housing allocation policy. g) That the following action points identified within the financial appraisal of the funding application by Strategic Finance, be implemented to reduce the risk to the Council: · That Cabinet consider the alternatives and are satisfied that the · proposal to construct the new build homes will meet the Council’s · objectives in the most appropriate manner. · That a process is developed to prioritise the development of sites · against pre-determined criteria and alternative options for · achieving the Council’s housing ...
Word for word from the decision Sandwell published for this meeting. Source: sandwell.moderngov.co.uk

Follow this further

Built from Sandwell's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
13a: Appendix 1: West End Avenue site boundary planAppendix 1 MB Copy on its way
PDF
13b: Appendix 2: West End Avenue-proposed layoutAppendix 694 KB Copy on its way
PDF
13c: Appendix 3: Public Appraisal Report West End Avenue SmethwickAppendix 276 KB Copy on its way
PDF
Council new build homes on land at West End Avenue, SmethwickReport 288 KB Copy on its way

At this meeting

Whole meeting
1Apologies for AbsenceDecided 3MinutesOn the agenda 5New Homelessness and Rough Sleeping StrategyApproved 6COVID Recovery FundApproved 7Towns Fund- Inclusion in Capital Programme and Assurance FrameworkApproved 8Draft Black Country Plan: Consultation on Additional Housing Sites and amendment to the Local Development SchemeApproved 9Award of Corporate Hybrid Print and Mail ContractAgreed 10Drug Strategy Grant: Supplemental Substance Misuse Treatment and Recovery GrantDecided 11Permission to consult on the Black Country Cycling and Walking Infrastructure PlanApproved 12Disposal of Grafton Lodge, Grafton Road, OldburyApproved
13Council new build homes on land at West End Avenue, SmethwickThis decision
14Council new build homes on land at Whitgreave Street, West BromwichApproved 15Proposed West Bromwich Definitive Map and Statement for Public Rights of WayDecided 16Council new build homes on land at Higham's Close, Rowley RegisApproved 17Planning, Building Consultancy, Land Charges & Associated Computer Systems Contract RenewalDecided 18Birmingham Commonwealth Games Act 2020Decided 19Council house new build programme - approval of sites and amendment to funding sourcesApproved 20Green Spaces Strategy - Implementation and Business Plan 2022/23 - 2025/26Approved 21Exclusion of the Public and PressOn the agenda 22Provision of new council homes on 3 sites to be delivered via LHC Framework Alliance ContractPrivate 23Approval of bids from Sandwell Metropolitan Borough Council to Round 2 of Levelling Up FundPrivate 24Management Options Appraisal - LeisurePrivate

On this subject at Sandwell

Search all
  1. Council new build homes on land at West End Avenue, SmethwickThis decision
  2. Council House New Build ProgrammeAgreed
  3. Council new build homes on land at Whitgreave Street, West BromwichApproved
  4. Council new build homes on land at Higham's Close, Rowley RegisApproved
  5. Planning, Building Consultancy, Land Charges & Associated Computer Systems Contract RenewalDecided
  6. Council house new build programme - approval of sites and amendment to funding sourcesApproved

More from Sandwell Cabinet

All decisions
MeetingDecisionOutcome
12 Mar 2025 Levelling up Partnership Update- (1) the progress update on the delivery of the Levelling Up Partnership is received; (2) a further progress report ... Decided Open
12 Mar 2025 Quarter 3 Budget Monitoring 2024/25Resolved that the financial monitoring position as at 31 December 2024 (Quarter 3) is received and referred to the Bu... Decided Open
12 Mar 2025 Cradley Heath Community Centre - Future OptionsResolved :- (1) that Cradley Heath Community Centre, Cradley Heath, B64 5JG is declared as being surplus to all Counc... Approved Open
12 Mar 2025 Housing Repairs and Maintenance Contracts 2025/26Resolved :- (1) that the Executive Director of Place is authorised in consultation with the Executive Director of Fin... Decided Open
12 Mar 2025 Council House New Build ProgrammeResolved :- (1) that the previous decision of Cabinet (Minute No. 140/22 (2) and (3) dated 22 June 2022) in relation ... Agreed Open