Item10/24
Resolved
- (1) that the Interim Director of Housing be authorised to continue procurement for the HIP Programme based on previous Cabinet Approval with increased funding to a total value of £ 100million; (2) that the Interim Director of Housing be authorised to commence the procurement process for the Domestic Gas Appliance contract; (3) that approval be given to the alterations to the delivery model for Social Housing Decarbonisation Fund (SHDF) Wave 2.1, for Sandwell MBC to act as Principal Contractor and procure a range of providers for energy efficiency works; (4) that the Interim Director of Housing be authorised to award contracts as set out in Resolutions (1) to (3) above to the successful bidders, following a compliant procurement process that meets Public Contract Regulations 2015 and Sandwell Corporate Procurement Procedures.
Word for word from the decision Sandwell published for this meeting.
Source: sandwell.moderngov.co.uk