Item7
Resolved
- (1) that Cabinet endorse the new design for the rebuild of Haden Hill Leisure Centre within the financial envelope available; (2) that delegate authority is given to the Executive Director for Place in consultation with the Executive Director for Finance and Transformation to enter into the construction contract, subject to an affordable cost plan at RIBA Stage 4; (3) that delegate authority is given to the Executive Director for Place, in consultation with the Assistant Director of Legal and Assurance to sign legal agreements and contracts associated with the delivery of the replacement of Haden Hill Leisure Centre.