Resolved
That the Head of Highways and Public Protection be authorised to implement the replacement of the existing signal-controlled toucan crossing on the A59 southbound with another facility approximately 20m south of the existing one.
Licensing and Regulatory Committee decided this item on Monday 1 November 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Head of Highways and Public Protection be authorised to implement the replacement of the existing signal-controlled toucan crossing on the A59 southbound with another facility approximately 20m south of the existing one.
To seek Members’ approval for the implementation of the relocation of the signal controlled toucan crossing on the A59 in Aintree.
Recommendation(s):
It is recommended that the Head of Highways and Public Protection be authorised to implement the following modifications to the highway:
(a) Replacement of the existing signal controlled toucan crossing on the A59 southbound with another facility approximately 20m south of the existing one.
Reasons for the Recommendation(s):
The Council has funding identified within the Transport Capital Programme for 2021-22 to fund Local Safety Schemes. These proposals should both improve safety by minimising the risk of collisions and also reducing maintenance cost.
Licensing and Regulatory Committee have powers to consider the details of improvements to highways and can approve the scheme as proposed or with minor amendments but otherwise must refer the scheme to the Cabinet Member.
Alternative Options Considered and Rejected: (including any Risk Implications)
The existing facility could be retained, but there are no obvious solutions such as new signage or carriageway marking amendments which are likely to slow vehicles sufficiently to mitigate the risk of a collision. What will it cost and how will it be financed?
(A) Revenue Costs
None.
(B) Capital Costs
The cost of the proposals will be met from the Local Safety Scheme allocation within the Transportation Capital programme for 2021-22 as approved by Cabinet Member in October 2021.
Implications of the Proposals:
Resource Implications (Financial, IT, Staffing and Assets): None
Legal Implications: None
Equality Implications: There are no equality implications
Climate Emergency Implications:
The recommendations within this report will Have a positive impact Y/N Have a neutral impact Y/N Have a negative impact Y/N The Author has undertaken the Climate Emergency training for Y/N report authors
Contribution to the Council’s Core Purpose:
Protect the most vulnerable: Not applicable
Facilitate confident and resilient communities: Improve conditions for pedestrians crossing the A59 in Aintree
Commission, broker and provide core services: Not applicable
Place – leadership and influencer: Enhances the local environment by promoting alternative modes of travel.
Drivers of change and reform: Not applicable
Facilitate sustainable economic prosperity: The route improves the pedestrian link between the residential properties of Netherton and Aintree and the local supermarket.
Greater income for social investment: Not applicable
Cleaner Greener: Supports sustainable travel, particularly walking.
What consultations have taken place on the proposals and when?
(A) Internal Consultations
The Executive Director of Corporate Resources and Customer Services (FD.6587/21) and the Chief Legal and Democratic Officer (LD4788/21) have been consulted and any comments have been incorporated into the report.
(B) External Consultations
As the new toucan crossing is intended to replace an existing one, albeit 20m further along the carriageway, and no residential properties were directly affected, it was agreed that no external consultation would be required.
Implementation Date for the Decision
Immediately following the Committee meeting
Contact Officer: Andrew Dunsmore Telephone Number: Tel: 0151 934 2766 Email Address: [email protected]
There are no appendices to this report
There are no background papers available for inspection. 1.0 Introduction/ Background
1.1The controlled toucan crossing on the southbound carriageway of the A59 is located on the straight section of carriageway approximately 20m from the end of the circulatory section.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Modified signal-controlled toucan crossing, A59, Ormskirk Road, AintreeReport | 5 pages | DownloadRead as text |
Follow Licensing and Regulatory Committee at Sefton and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Sep 2026 | MinutesThat the of the meeting held on 3 June 2026 be confirmed as a correct record. | Decided | Open |
| 7 Sep 2026 | Exclusion of Press and PublicThat under Section 100A(4) of the Local Government Act, 1972, the press and public be excluded from the meeting for t... | Decided | Open |
| 8 Jun 2026 | Appointment of Vice-Chair of the Committee 2026/27That Councillor Carragher be appointed Vice Chair of the Committee for the Municipal Year 2026-2027. | Decided | Open |
| 8 Jun 2026 | MinutesThat the of the meeting held on 9 March be confirmed as a correct record. | Decided | Open |
| 8 Jun 2026 | Local Licensing Annual Report 2025/26That (1) the report be noted; and (2) the licensing team be requested to submit similar reports to the Licensing and ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.