That a) the proposal for performance monitoring reports to be by exception only as set out in paragraphs 3 and 4 of the report be agreed; and b) where appropriate, areas of underperformance be referred to the appropriate Select Committee or relevant Officers for further action.
Word for word from the decision Sevenoaks published for this meeting.Source: cds.sevenoaks.gov.uk
1 The Council’s performance management arrangements are supported by a software system which allows performance to be monitored using a simple traffic light system i.e. Green for good, Amber if caution is required and Red if the indicator requires attention. This allows the Council to both celebrate good practice and take early steps to rectify actual and potential problem areas. The system allows for the review of historical performance as well as tracking progress against performance targets.
2 The Council’s performance management system, Covalent, is available to all Members via the Members Portal. All of the current performance indicators agreed by Members are available on the system and Members are encouraged to use this to access performance information across all service areas.
Performance Reporting
3 With the agreement of Members it is recommended that the performance reports presented to this Committee support the Performance and Governance Committee’s aim of identifying under performance from across the Council’s services and asking for actions to be put in place to rectify it. Performance and Governance Committee – 28 June 2011 4 To this end the performance report has been redesigned for Members consideration. Taking on board the recommendation of the Committee at its meeting of 19 April 2011 the report, as provided as an Appendix, is exceptions based. The layout of the report is designed to assist Members in referring matters of concern to the appropriate Select Committee for action. All future Agendas of the Performance & Governance Committee will allow for formal feedback from the Select Committees on any performance matters referred to them.
5 An initial introduction to Covalent was provided to Members at the IT Briefing held on 14 June 2011. It is proposed that further training will be provided to Members in September this year which will support Members in using and understanding the Covalent system. A number of improvements are currently being implemented to the system and should will be completed in the coming months. These improvements will further improve access to information and ease of use for Members.
Performance Overview – End of Quarter 4 2010/11
6 The following table summarises the performance levels for the end of 2010/11.
Red Amber Green
10% or more below Less than 10% below At or above target target target
14 12 54
17.5% 15.0% 67.5%
7 Set out in the Appendix are details of each of the 14 ‘Red’ performance indicators categorised by the Select Committee which holds responsibility for scrutinising that service’s performance. Alongside the performance data is a commentary provided by the managers of the service explaining the reason behind the performance and any actions that are planned or are currently being taken to improve performance.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Internal Audit Plan Q3 Progress ReportT hat the contents of the report and the progress made by the audit team in delivering the 2012/13 Annual Internal Au...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.