Resolved
that the Annual Governance Statement for 2011/12, which accompanies the Council’s Accounts, be agreed.
Performance and Governance agreed this item on Tuesday 12 June 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
that the Annual Governance Statement for 2011/12, which accompanies the Council’s Accounts, be agreed.
2 Members may be aware that the Performance and Governance Committee is required to consider and approve the Annual Governance Statement (AGS) which is required to accompany the Council’s Annual Accounts, as part of the Performance and Governance Committee’s terms of reference.
3 The Annual Governance Statement explains how the Council has complied with the Local Code of Corporate Governance (which is consistent with the principles of the CIPFA Guidance, “Delivering Good Governance in Local Government”); as well as its internal control and risk management processes. It is a corporate document involving a variety of people including Officers, Members and external regulatory agencies charged with delivering or contributing towards the delivery of good governance within the Council.
Ownership of The Annual Governance Statement
4 The Annual Governance Statement is a corporate document which is owned by all senior Officers and Members of the Council. A shared approach was taken in preparing the AGS, as delegation to a single individual or section would lessen the statement's significance and may encourage people to distance themselves from their proper responsibilities.
5 The AGS is supported by the system of internal control which is reviewed continually throughout the year, as part of routine governance and managerial processes; prime examples being the authority's performance management and risk management frameworks.
6 Although corporately owned, the AGS requires individual self-assessments from heads of services regarding their internal control processes; and statement of assurance from Directors, the Monitoring Officer and the Section 151 Officer, all of which were obtained as part of the information gathering process which informed the AGS. Material matters identified within this process are set out on section 6 of the AGS
Outcome of the Process
7 The process identify that the Council has sound systems of internal control and governance in place. The only issue of significance identified during the process is set out on paragraph 6 of the appendix.
Approval Process
8 The AGS was considered by a committee of the Officers Risk management Group on 11th May 2012 and by Management Team on 23rd May 2012. The P&GC is therefore requested to consider and approved the AGS at this meeting. Following approval by the P&GC, the AGS is required to be signed by the Leader and the Chief Executive prior to publication with the Council’s statutory accounts.
Key Implications
Financial
9 This report has no financial implications.
Community Impact and outcomes
8 Not applicable
Legal, Human Rights etc.
9 This report has no additional legal implications
Resource (non-financial)
10 Not applicable
Value for Money and Asset Management
11 Not Applicable.
Equality
12 There are no additional equality implications for this report Sustainability Checklist
13 Not applicable
Conclusions
14 The Annual Governance Statement has been prepared in compliance with relevant professional guidance. It demonstrates that the Council had sound governance arrangements in place during the year and in the period leading up to the preparation of the Council’s Annual Accounts. Members are therefore requested to agree the attached AGS.
Risk Assessment Statement
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Annual Governance Statement 2011/12.Report | 39 KB | DownloadRead as text |
PDF |
Item 10: Annual Governance Statement 2011-12: AppendixAppendix | 56 KB | Download |
Follow Performance and Governance at Sevenoaks and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Apr 2013 | MinutesThat the of the meeting of the Performance and Governance Committee held on 8 January 2013, be approved and signed by... | Approved | Open |
| 17 Apr 2013 | Performance ReportThat the report be noted. | Noted | Open |
| 17 Apr 2013 | Internal Audit Plan Q3 Progress ReportT hat the contents of the report and the progress made by the audit team in delivering the 2012/13 Annual Internal Au... | Noted | Open |
| 17 Apr 2013 | Annual Audit Plan 2013/14That the the draft Internal Audit Plan for 2013/14, be approved. | Approved | Open |
| 17 Apr 2013 | Budget Monitoring - January 2013 Figures and February 2013That the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.