Resolved
That the report be noted.
Performance and Governance noted this item on Tuesday 18 September 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be noted.
BUDGET MONITORING – JULY 2012
Performance & Governance Committee – 18 September 2012
Report of the: Deputy Chief Executive and Director of Corporate Resources
Status: For Information
Key Decision: No
This report supports all the Council’s key themes and objectives
Portfolio Holder Cllr. Ramsey
Head of Service Group Manager Financial Services – Adrian Rowbotham
Recommendation to Performance and Governance Committee: That the report be noted.
Introduction
Overall Financial Position
1 Four months into the year the results to date show an overall favourable variance of £150,000.
2 The year-end position is forecast to be £120,000 better than budget.
Key Issues for the year to date
3 Income – investment income is performing above target and is forecast to be better than budgeted at the year-end. This is due to higher than estimated balances and slightly higher rates being achieved, and a favourable forecast is shown to reflect this position.
4 Looking at the other main income sources, the position remains difficult. Building Control, Land Charges and Planning Pre-application fees currently show adverse variances for the year to date.
5 Pay costs – the actual expenditure is less than budget due to some vacancies during the year and staffing restructures following the departure of senior managers.
6 Other –Direct Services’ results show a negative variance of £6,000 compared to budget. Year End Forecast
7 Four months into the year, the year-end position is forecast to be £120,000 better than budget with extra investment income being the largest factor explaining the variance. Additional income is also expected from office rentals and council tax court costs. Further favourable variance is forecast for audit fees.
Risk areas
8 The current economic situation continues to have a real and potential impact on the Council’s finances:
• The investment strategy is constantly under review in light if the changing long term credit ratings which affects the number of organisations the Council can invest in;
• property related income such as Development Control (particularly pre- application fees and s106 monitoring), Building Control, Land Charges and Capital Receipts remain vulnerable;
• the Benefits workload is continuing at a higher level than before the recession, which is having an impact on processing times (though an action plan is in place to improve performance);
• Council Tax collection rates, though currently in line with the previous year, could be affected by increased unemployment and squeezed household incomes; and
• Planned savings through the generation of income, particularly from new partnership working, remain risk areas for the current and for future years.
Key Implications
Financial
The financial implications are included elsewhere in the report.
Community Impact and Outcomes
None.
Legal, Human Rights etc.
None.
Risk Assessment Statement
Detailed budget monitoring is complete on a monthly basis where all variances over £10,000 are explained. Future risk items are also identified. Appendices Appendix A – Budget Monitoring Sheets for July 2012
Background Papers: Budget 2012/13
Budget Monitoring Reports for 11/12
Financial System
Contact Officer(s): Helen Martin x7483
[name removed] Chief Executive and Director of Corporate Resources
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Budget Monitoring July 2012Report | 31 KB | DownloadRead as text |
PDF |
Item 14: Budget Monitoring: July 2012(1) AMALGAMATEDReport | 1.2 MB | Download |
Follow Performance and Governance at Sevenoaks and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Apr 2013 | MinutesThat the of the meeting of the Performance and Governance Committee held on 8 January 2013, be approved and signed by... | Approved | Open |
| 17 Apr 2013 | Performance ReportThat the report be noted. | Noted | Open |
| 17 Apr 2013 | Internal Audit Plan Q3 Progress ReportT hat the contents of the report and the progress made by the audit team in delivering the 2012/13 Annual Internal Au... | Noted | Open |
| 17 Apr 2013 | Annual Audit Plan 2013/14That the the draft Internal Audit Plan for 2013/14, be approved. | Approved | Open |
| 17 Apr 2013 | Budget Monitoring - January 2013 Figures and February 2013That the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.