CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Sevenoaks District Council
Performance and Governance, Tuesday 8 January 2013 at 7.00pm

Risk Management Update

Noted Committee 3 papers

Performance and Governance noted this item on Tuesday 8 January 2013. Below is the council's own wording, with the papers it was decided on.

Item113

Resolved

That the contents of the report be noted.
Word for word from the decision Sevenoaks published for this meeting. Source: cds.sevenoaks.gov.uk

Follow this further

Built from Sevenoaks's papers

What the report saysPro

Report to Performance and Governance

PERFORMANCE AND GOVERNANCE COMMITTEE – 8 JANUARY 2013

Risk Management Update

Report of the: Deputy Chief Executive and Director of Corporate Resources

Status: For Consideration

Executive Summary: This report provides Members with an update on the progress of implementing the Council’s revised risk management framework, following the meeting of this Committee in June, at which Members were informed of plans to refresh and revise the framework.

This report supports the Key Aim of Corporate Performance Plan “Effective Management of Council Resources”

Portfolio Holder Cllr. Ramsay

Head of Service Adrian Rowbotham, Group Manager – Finance

Recommendation: It be RESOLVED that Members note the contents of this report.

Introduction

1 As part of its terms of reference the Performance and Governance Committee considers reports on the Council’s risk management strategy and framework. Members were informed of proposals to simplify and strengthen the Council’s risk management framework at their meeting on 12 June 2012. This report updates Members on the progress being made in implementation of the revised framework and further proposals to improve and embed the process across the Council going forward.

2 The Council’s risk management strategy sets out that risk will be identified, assessed and managed both strategically and operationally. Strategic risks are those that may prevent the Council achieving its objectives as set out in the Corporate Plan 2009-12. Strategic risks are managed by Directors and Heads of Service with oversight and scrutiny being delivered by Performance and Governance Committee.

3 Operational risks are those that may prevent individual services meeting the objectives set out in their service plans. Operational risks are managed by Service Managers, supported by Heads of Service.

4 The Council also has processes in place to manage financial risks, project risks and health and safety risks that operate alongside the risk management framework. Financial risks are monitored by the Finance team and assessed and scrutinised by the Finance Advisory Group. Project risks are managed by the relevant Head of Service working closely with the project manager and are subjected to DMT and MT monitoring, based on the type of project. Health and Safety risk assessments are overseen and coordinated by the Council’s Environmental Health team, with Service Managers responsible for undertaking regular risks assessments and taking actions to mitigate those risks.

Risk Management Framework

5 Since June 2012 through its officers Risk Management Group the Council has developed a revised risk management framework for the Council. The revised framework takes account of best practice guidance as developed by ALARM (The Public Risk Management Association) and the views of senior management that helped to shape the framework to ensure it fits with the organisations culture and practices.

6 The revised risk management framework is attached at Appendix A to this report and is entitled ‘Risk on a page’. The framework has been simplified to ensure the Council is able to focus on its key risks and provides the tools that are needed to demonstrate that the Council has a thorough understanding and strong basis to evaluate the risks it faces.

Risk Management Training

7 The facilitate the introduction and adoption of the revised risk management framework across the council risk management training workshops were designed and delivered to Members, Directors , Heads of Service and Service Managers.

8 The delivery of training to both Officers and Members was a key objective for improving the risk management framework for 2012/13. The Council’s insurance provider, Zurich Municipal, assisted in providing the training required and the Council was able to access the training as part of its insurance contract at no additional cost.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Item 08: Risk Management Update: Appendix AAppendix 51 KB Download
PDF
Item 08: Risk Management Update: Appendix BAppendix 90 KB Download
PDF
Risk Management UpdateReport 72 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Sevenoaks

Search all
  1. Risk Management UpdateThis decision
  2. Risk Management PolicyApproved
  3. Audit Committee Member Development - Risk ManagementNoted
  4. Member Development - Risk ManagementNoted
  5. Risk Management StrategyApproved
  6. Member Development - Risk ManagementNoted

More from Sevenoaks Performance and Governance

All decisions
MeetingDecisionOutcome
17 Apr 2013 MinutesThat the of the meeting of the Performance and Governance Committee held on 8 January 2013, be approved and signed by... Approved Open
17 Apr 2013 Performance ReportThat the report be noted. Noted Open
17 Apr 2013 Internal Audit Plan Q3 Progress ReportT hat the contents of the report and the progress made by the audit team in delivering the 2012/13 Annual Internal Au... Noted Open
17 Apr 2013 Annual Audit Plan 2013/14That the the draft Internal Audit Plan for 2013/14, be approved. Approved Open
17 Apr 2013 Budget Monitoring - January 2013 Figures and February 2013That the report be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies