Resolved
That (a) The Capital Programme 2013/16 and funding method set out in Appendix B be approved; and (b) The proposed Asset Maintenance budget of £427,000 be agreed for 2013/14.
Cabinet approved this item on Thursday 7 February 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
That (a) The Capital Programme 2013/16 and funding method set out in Appendix B be approved; and (b) The proposed Asset Maintenance budget of £427,000 be agreed for 2013/14.
This report sets out the proposed 2013/16 Capital Programme, with supporting documentation in a standard format for individual scheme bids. Projected capital receipts are included, indicating the proposed financing of the Programme. A proposed overall provisional limit for Asset Maintenance is also made.
This report supports the Key Aim of effective management of Council resources
Portfolio Holder Cllr. Ramsay
Head of Service Group Manager – Financial Services – Adrian Rowbotham
Recommendation to Cabinet: It be RESOLVED that:
(a) the Capital Programme 2013/16 and funding method set out in Appendix B be approved,
(b) and the proposed Asset Maintenance budget of £857,000 be agreed for 2013/14.
1 A copy of the existing 2012/15 three year programme is attached at Appendix A. The 2012/13 column includes budgets brought forward from 2011/12. Forecast outturn figures for the current year and estimated carry forward figures are shown.
2 The Council’s current policy in relation to capital expenditure is as follows: ”no new schemes to be added to the programme except mandatory improvement grants, information technology and vehicle replacements”
3 This policy has previously been revised and updated as part of the Best Value review of Asset Management and Capital Investment, including the development of a formal options appraisal process. Capital Bids
4 Scheme Bid Documents are attached at Appendix C for all on-going items referred to at paragraph 2 above which require additional capital resources. These documents identify any external funding available and indicate the internal funding source.
5 Appendix B summarises the position if all schemes are approved, and indicates the funding methods proposed.
6 Unspent schemes in the current year’s programme (2012/13) may be carried forward to 2013/14, subject to Cabinet approval, when the outturn is known.
7 Cabinet on 10 January 2013 discussed asset maintenance at White Oak Leisure Centre and it was resolved that Officers be asked to investigate and explore all possibilities surrounding Options Two (invest in the existing building) and Three (replace the existing building on the same or a different site), consulting with all stakeholders and report back to Members as soon as practicable. The results of this investigation may lead to additional capital resources in future years.
Capital Receipts
8 Other than the Vehicle Renewal Fund, net capital scheme costs, after any approved funding from the Capital Reserve, are funded from Capital Receipt balances. New receipts expected over the programme period are as follows:
2012/13 2013/14 2014/15 2015/16 £000 £000 £000 £000
Shared Ownership 140 50 50 25 Staircasing
Mortgage repayments (net 2 1 1 1 of pooling)
Land Sales 1,317 2,131 1,050 0
1,459 2,182 1,101 26
The Land Sales receipts arise from the Property Review process which plans and monitors actions to dispose of surplus sites as part of the asset management plan.
9 It must be emphasised that the scale and timing of the land sales is very unpredictable and subject to market conditions and planning risks. For this reason, only 75% of the above figures have been included in Appendix B.
10 Up until 2008/09, the Council used its capital receipts to fund its capital programme. However, due to a combination of reducing assets and a period of recession impacting asset values, the level of reliance on capital receipts could not be sustained. Therefore, Members made the decision to fund the capital programme through the revenue budget at an annual cost of £330,000. This has now been reduced to £298,000 following a reduction in the gross capital scheme costs for Improvement Grants.
11 Appendix B takes these projections, together with the actual balance of such receipts at 1st April 2012.
Asset Maintenance
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Programme and Asset Maintenance: Appendix AAppendix | 19 KB | Download |
PDF |
Capital Programme and Asset Maintenance: Appendix BAppendix | 21 KB | Download |
PDF |
Capital Programme and Asset Maintenance: Appendix CAppendix | 34 KB | Download |
PDF |
Capital Programme and Asset Maintenance 2013-16Report | 52 KB | DownloadRead as text |
Follow Cabinet at Sevenoaks and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Sep 2026 | MinutesThat the of the Cabinet meeting held on 7 July 2026 and the Special Cabinet meeting held on 14 July, be approved and ... | Approved | Open |
| 22 Sep 2026 | Appointments to Advisory Committees & BoardsThat the membership for the municipal year 2026/27, as set out in the supplementary agenda to the report, be approved. | Approved | Open |
| 22 Sep 2026 | Safeguarding Policy 2026 - 2030That it be recommended to Full Council that the contents of the report be noted and the safeguarding policy 2026-2030... | Noted | Open |
| 22 Sep 2026 | Financial Monitoring to end of July 2026That the report be noted. | Noted | Open |
| 22 Sep 2026 | Treasury Management 2025/26 Annual ReportThat the Treasury Management report for 2025/26, be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.