Resolved
That the report be noted.
Finance and Resources Advisory Committee noted this item on Tuesday 12 November 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be noted.
FINANCIAL RESULTS 2013/14 – to the end of September 2013
Finance and Resources Advisory Committee – 12 November 2013
Report of Group Manager Financial Services
Status: For consideration
Key Decision: No
This report supports the Key Aim of Effective Management of Council Resources
Portfolio Holder Cllr. Ramsey
Contact Officer(s) Helen Martin Ext. 7483
Recommendation to Finance and Resources Advisory Committee: That the report be noted.
Introduction and Background
Overall Financial Position
1. Six months into the year the results to date show an overall favourable variance of £444,000. Reasons for this current favourable variance are explained in the individual commentaries from Chief Officers
2. The year-end position is forecast to be £30,000 better than budget.
Key Issues for the year to date
3. Income – investment income is performing above target and is forecast to be better than budgeted at the year-end. This is due to higher than estimated balances and slightly higher rates being achieved during the year so far, and a favourable forecast is shown to reflect this position.
4. Income from on-street parking, land charges and development management are achieving or exceeding budget targets at the end of September.
5. Pay costs – the actual expenditure to date on SDC funded salaried staff is £127,000 below budget. An underspending of £167,000 relates to Direct Services and will be offset by agency staff costs held within the trading account. Additional resources are being used to address the Benefits workload and costs will be met by additional funding from both partners. The 1% pay award will be paid in October.
6. Other – Direct Services’ results show a positive variance of £98,000 compared to budget. 7. Costs amounting to £30,000 were incurred in facilitating the sale of 66 London Road.
Year End Forecast
8. The year-end position is forecast to be £30,000 better than budget.
9. Extra investment income is still a favourable variance, however interest rates are expected to remain low into the future. Income from council tax court costs is expected to be above budget for the year.
10. Following the sale of 66 London Road, there will be a saving on rent and rates at that site. Expenditure is forecast to be £76,000 below budget.
11. The contracts for markets at Sevenoaks and Swanley were re-tendered in 12/13 following the voluntary liquidation of the previous operators. Income from these new contracts is forecast to be £62,000 worse than budget.
12. Car Parking income, mainly pay and display, is now expected to be £70,000 worse than budget.
13. Direct Services are forecasting a favourable variance of £25,000 for the year.
14. Planning Services are now predicting that Planning fee income will be £95,000 better than budget.
15. The review of the senior management structure did not take effect until 1 September and as a result the full salary saving will not be met in 2013/14 although this shortfall of £48,000 will be met from other Corporate savings. The full saving will be delivered in future years.
Risk areas
16. The current economic situation continues to have a real and potential impact on the Council’s finances:
• the investment strategy is constantly under review in light of the changing long term credit ratings which affects the number of organisations the Council can invest in. The annual budget for investment income is £229,000 and a reduction of 0.1% in the rate of interest we are able to achieve could reduce our income by £28,000;
• property related income such as Development Control (particularly pre- application fees and S106 monitoring), Building Control, Land Charges remain vulnerable. The income budget for these major items is £1.294m and the current predicted favourable variance of £65k represents 5% of the budget;
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Financial Results 2013/14: to the end of September 2013Report | 37 KB | DownloadRead as text |
PDF |
Item 12 Financial Results 2013-14: To the end of September AppendixAppendix | 1.6 MB | Download |
PDF |
Tabled: Financial Results 2013-14: to the end of September 2013 (Commentaries)Report | 57 KB | Download |
Follow Finance and Resources Advisory Committee at Sevenoaks and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Apr 2015 | MinutesThat the minutes of the meeting of the Finance and Resources Advisory Committee held on 20 January 2015 be agreed and... | Agreed | Open |
| 14 Apr 2015 | Financial Performance Indicators 2014/15 to end of February 2015that the report be noted. | Noted | Open |
| 14 Apr 2015 | Financial Results 2014/15 to end of February 2015That it be recommended to Cabinet that the comments made by the Committee be considered and the report be noted. | Noted | Open |
| 20 Jan 2015 | MinutesThat the minutes of the meetings of the Finance and Resources Advisory Committee held on 11 November 2014, as amended... | Agreed | Open |
| 20 Jan 2015 | Risks and Assumptions for Budget 2015/16That the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.