Resolved
That the content and progress made by the Audit Team be noted.
Audit Committee noted this item on Tuesday 14 January 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
That the content and progress made by the Audit Team be noted.
INTERNAL AUDIT PROGRESS REPORT
Audit Committee – 14 January 2014 Report of Chief Finance Officer
Status: For Consideration
Key Decision: No
This report supports the Key Aim of Effective Delivery of the Corporate Plan
Portfolio Holder Cllr. Ramsay
Contact Officer(s) Bami Cole, ext.7236
Recommendation to Audit Committee: That Members:
Note the contents of the report and the progress made by the audit team in delivering the 2013/14 Annual Internal Audit Plan
Reason for recommendation: The Audit Committee is required to review the progress of the Internal Audit Plan in compliance with its terms of reference.
Introduction
1 This report provides details of the progress of the Internal Audit Team in delivering the Annual Internal Audit Plan 2013/14 and outcomes of final internal audit reports issued since the meeting of the committee in September 2013.This is the second progress report sent to the Audit Committee since its formation in May 2013.
2 The internal audit function is a key process of the Council’s overall governance arrangements. Its key purpose is to conduct independent reviews of the Council’s system of internal controls and to provide an assurance to both senior Management and Members regarding the effectiveness of such systems. In fulfilling his duty and responsibilities, the Audit Manager, is required to report to the Audit Committee on the progress made in delivering the internal audit plan in meeting the Council’s assurance requirements, in accordance with relevant professional standards.
Summary of Issues Raised Within the Report:
3 A summary of progress made towards delivering the assurance requirements for 2013/14 is attached as Appendix A to this report, which sets out details of the reviews agreed initially by the Performance and Governance Committee, in April 2013; and subsequently endorsed by the Audit Committee in June 2013. Members may note that nine planned reviews have been completed, two of which are at draft stage. Eight reviews are work in progress and a further four planned to commence in quarter four. Thus to date, a total of seventeen reviews have either been completed, or have commenced from this year’s annual plan. This is equivalent to 77% of the annual internal audit plan for 2013/14.
4 Members are advised that one review, item 22 on Appendix A is proposed to be taken forward to 2014//15 for operational reasons, In particular, the management information system and data management processes are currently being overhauled and upgraded within the relevant service, the faculties section. Hence it would be difficult to carry out a meaningful review at whilst the process is in transition and would be disruptive. It is therefore propose to undertake the review in the first quarter of 2014/15.
5 Appendix B sets out details of the reports which were issued since the last meeting of this committee and provides a brief summary of the findings and recommendations agreed with service management, to address any areas for further improvements, required to strengthen internal control. Further details on any of the issues raised on the report summaries would be provided to members of this committee on request.
Internal Audit Resources
6 Internal audit resources have been under capacity during the quarter due to sickness levels. This has consequently put some strain on delivery of the plan. Thus management is reviewing the plan and available resources to year end, to determine whether it would be appropriate to obtain agency staffing resources, or to carry forward some reviews. Senior management will be consulted on this and the Audit Committee will be advised at the next meeting of the Board on the outcome of this process.
Key Implications
Financial
7. Not Applicable.
Legal Implications and Risk Assessment Statement.
8. No additional legal implication beyond the Council’s duty to comply with the Accounts and Audit Regulations 2011.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
06 Internal Audit Progress Report: Appendix B: Summary of Final ReportsAppendix | 53 KB | Download |
PDF |
06 Internal Audit Progress Report 2013-14Appendix C: Audit Opinions: DefinitionsAppendix | 19 KB | Download |
PDF |
Progress of Internal Audit Plan 2013-14Appendix A | 24 KB | Download |
PDF |
Internal Audit 2013/14: 2nd Progress ReportReport | 36 KB | DownloadRead as text |
Follow Audit Committee at Sevenoaks and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Jul 2026 | MinutesThat the of the Audit Committee held on 14 April 2026, be signed and approved by the Chairman as a correct record. | Approved | Open |
| 8 Jul 2026 | Member Allowance Scheme MonitoringThat the report be noted. | Noted | Open |
| 8 Jul 2026 | Statement of Accounts 2025/26 - progress update and Establishment of Member Working GroupThat a) the update on progress on the 2025/26 draft Statement of Accounts be noted; b) a member working group be set ... | Noted | Open |
| 8 Jul 2026 | Internal Audit Annual Report and OpinionThat the report be noted. | Noted | Open |
| 8 Jul 2026 | Review of Effectiveness of the Audit CommitteeThat the Self-Assessment Review of the Effectiveness of the Audit Committee (Appendix A) for 2025/26 be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.