Sevenoaks District Council
Cabinet, Thursday 8 May 2014 at 7.00pm

Flood Support Schemes

Agreed Key decision Executive 5 papers

Cabinet agreed this item on Thursday 8 May 2014. Below is the council's own wording, with the papers it was decided on.

Item113

Resolved

That i) the guidelines for the Council’s Repair and Renew Grant, as set out at Appendix B to the report, be agreed; and ii) authority delegated to the Portfolio Holder for Economic and Community Development to approve grants.
Word for word from the decision Sevenoaks published for this meeting. Source: cds.sevenoaks.gov.uk

Follow this further

Built from Sevenoaks's papers

What the report saysPro

Report to Cabinet

FLOOD SUPPORT SCHEMES

Cabinet – 8 May 2014

Report of Chief Officer Communities & Business

Status: For Urgent Decision

Key Decision: Yes

Executive Summary: This report sets out information about the Repair and Renew Grant.

The Government is making funding available to this Council to fund the scheme, which will help properties and businesses in the District who have been affected by flooding put flood resilience measures in place to reduce the risk of future flooding.

Members are asked to agree Guidelines for this Council to administer the Repair and Renew Grant. This report supports the Key Aim of Supporting and developing the local economy and the Community Plan Vision for Safe & Caring Communities, a Green & Healthy Environment and a Dynamic & Sustainable Economy.

Portfolio Holder Cllr. Roddy Hogarth

Contact Officer(s) Simon Davies Ext. 7374

Recommendation to Cabinet: That the guidelines for the Council’s Repair and Renew Grant, as set out at Appendix B, are agreed and authority to approve grants be delegated to the Portfolio Holder responsible for economic development and emergency planning.

Reason for recommendation: Properties and businesses in the District suffered damage from flooding between December 2013 and March 2014. This Council has been allocated funding by DEFRA towards the Repair and Renew Grant. There is no ceiling to the funding, which is for a maximum of £5,000 per property. The Council will pay funding out and then claim back quarterly from DEFRA.

Introduction and Background

1 Members will be aware that the winter of 2013/14 has been the wettest winter on record for the UK since records began in 1910. Between 1 December 2013 and 31 March 2014, there was widespread flooding across the country and homeowners and businesses in the Sevenoaks District were impacted by flooding.

2 The Government set out guidance notes to provide information on schemes to help homeowners and businesses recover from adverse weather since 1 December 2013. The guidance notes are set out at Appendix A. The guidance notes set out four schemes to assist homeowners and businesses: a. The Repair and Renew Grant. b. Business Rates Flooding Relief. c. Council Tax Discounts. d. Business Support Scheme.

3 Guidance notes for the Business Flood Support Scheme were agreed by Cabinet 6 March 2014. Repair and Renew Grant - Appraisal Process

4 We are now able to proceed with the Repair and Renew Grant as we have enough information from DEFRA to do so. Officers have drafted some scheme guidelines and they are set out at Appendix B. The draft guidelines reflect the parameters set out in DEFRA’s guidance notes (Appendix C) and this Council’s Code of Practice for Grant- making (Appendix D). Members are asked to agree the guidelines.

5 The Council will be expected to forward fund applications and claim back from DEFRA on a quarterly basis. There is no upper ceiling for the amount that can be claimed, but all funds must be claimed from DEFRA by 31 March 2015. It is therefore proposed that applicants must have claimed their grants in full by 31 December 2014.

6 DEFRA requests that participating Councils maintain a spreadsheet of each grant application received, setting out those applications approved, those refused funding, the value of funds paid out and the value of overall commitments.

7 Applications will be appraised case-by-case on a first come, first served basis. Applications for grants will be appraised according to the following criteria: i. The extent to which the business has been affected by flooding between 1st December 2013 and 31 March 2014;

ii. Whether the proposed resilience measures are appropriate for the nature of flooding experienced;

iii. That the application represents value for money;

iv. Whether any other known flood defence schemes have been committed to in the same area;

v. Whether the applicant has received other public or insurance funds for the same measures;

vi. Whether applicant businesses comply with state aid legislation;

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
10: Appendix AAppendix 205 KB Download
PDF
10: Appendix BAppendix 43 KB Download
PDF
10: Appendix CAppendix 135 KB Download
PDF
10: Appendix DAppendix 38 KB Download
PDF
Flood Support SchemesReport 49 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Sevenoaks

Search all
  1. Flood Support SchemesThis decision
  2. Flood Support - Repair & Renew Grants - revised guidelinesAgreed
  3. Flood Support SchemesAgreed

More from Sevenoaks Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 MinutesThat the of the Cabinet meeting held on 7 July 2026 and the Special Cabinet meeting held on 14 July, be approved and ... Approved Open
22 Sep 2026 Appointments to Advisory Committees & BoardsThat the membership for the municipal year 2026/27, as set out in the supplementary agenda to the report, be approved. Approved Open
22 Sep 2026 Safeguarding Policy 2026 - 2030That it be recommended to Full Council that the contents of the report be noted and the safeguarding policy 2026-2030... Noted Open
22 Sep 2026 Financial Monitoring to end of July 2026That the report be noted. Noted Open
22 Sep 2026 Treasury Management 2025/26 Annual ReportThat the Treasury Management report for 2025/26, be approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies