Resolved
That the Draft Strategic Risk Register be agreed with no further recommendations, amendments or additions.
Audit Committee agreed this item on Tuesday 10 June 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Draft Strategic Risk Register be agreed with no further recommendations, amendments or additions.
DRAFT STRATEGIC RISK REGISTER
Audit Committee – 10 June 2014
Report of Chief Finance Officer
Status: For Decision
Key Decision: No
This report supports the Key Aim of effective deliver of the Council’s Vision and Promises
Portfolio Holder Cllr. Ramsay
Contact Officer(s) Bami Cole Ext. 7236
Recommendation to Audit Committee:
Review the Draft Strategic Risk Register and make recommendations for any further amendments or additions to the register.
Reason for recommendation: Review of the Council’s Draft Strategic Risk Register by the Audit Committee helps to ensure that a wide range of view points are taken in to account in assessing the risk’s the Council faces in delivering the Vision and Promises set out in the Corporate Plan.
Introduction and Background
1 It is a requirement of the Audit Committee’s Terms of Reference to maintain an overview of the effective development and operation of risk management in the Council.
2 At the Committee’s meeting in January 2014 it considered and approved the revised Risk Management Policy Statement and in March 2014 recommended that the Risk Management Strategy be adopted by the Cabinet, which it do so in April 2014.
3 This report provides Members with the opportunity to review and comment on the Council’s Draft Strategic Risk Register. The Draft Register has been developed by Officers, taking in the views of the Officers Risk Management Group, Service Managers and Chief Officers. It sets out those risks that Officers consider could prevent the Council delivering the Vision and Promises set out in the Council’s Corporate Plan.
4 The consideration of the Draft Register by the Audit Committee provides an opportunity for Members to input their views and provides for a more robust assessment of the risks faced by the Council. The views of the Audit Committee will be taken in to account before Cabinet is asked to review and adopt the Draft Risk Register at a future meeting.
Draft Strategic Risk Register
5 Provided as Appendix A to this report is the Council’s Draft Strategic Risk Register. The Draft Register has been updated to reflect the introduction of the Council’s new Corporate Plan and to ensure that strategic risk management activity is focussed on mitigating and managing the risks associated with the Council achieving the Vision and Promises it sets out.
6 The Draft Register sets out 13 strategic risks that Officers consider to have the potential to influence the achievement of the Vision and Promises within the Corporate Plan. For each risk Officers have set out those factors that could cause the risk to occur and the potential effect that these events could have. The Gross risk scores reflect Officers opinion of the likelihood and impact of the risk occurring without any internal controls in place. The Net risk scores take in to account the internal controls that are currently in place and it is therefore the net risk score that gives the current status for each risk. The draft risk scores are summarised in the chart below.
7 Members are asked to consider the Draft Register and provide any suggestions for improvements or changes that can be incorporated in to it. Officers will review the comments of the Audit Committee and include them within a revised and updated register as appropriate. Any additional actions that are required to be taken to better mitigate or manage each risk faced will also be documented once the feedback from the Audit Committee has been taken in to account.
8 As set out in the Council’s Risk Management Strategy Cabinet will be asked to adopt the Strategic Risk Register at a future meeting and a review of the Strategic Risk Register will be bought back to the Audit Committee in six months time, or more immediately if there are new risks arising or there is a significant shift in risk scores.
Other Options Considered and/or Rejected
None. Key Implications
Financial
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
14 Draft Strategic Risk Register: Appendix AAppendix | 129 KB | Download |
PDF |
Draft Strategic Risk RegisterReport | 59 KB | DownloadRead as text |
Follow Audit Committee at Sevenoaks and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Jul 2026 | MinutesThat the of the Audit Committee held on 14 April 2026, be signed and approved by the Chairman as a correct record. | Approved | Open |
| 8 Jul 2026 | Member Allowance Scheme MonitoringThat the report be noted. | Noted | Open |
| 8 Jul 2026 | Statement of Accounts 2025/26 - progress update and Establishment of Member Working GroupThat a) the update on progress on the 2025/26 draft Statement of Accounts be noted; b) a member working group be set ... | Noted | Open |
| 8 Jul 2026 | Internal Audit Annual Report and OpinionThat the report be noted. | Noted | Open |
| 8 Jul 2026 | Review of Effectiveness of the Audit CommitteeThat the Self-Assessment Review of the Effectiveness of the Audit Committee (Appendix A) for 2025/26 be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.