Sevenoaks Highway Works Programme - September 2015

Noted Committee 1 paper

Sevenoaks Joint Transportation Board noted this item on Thursday 3 September 2015. Below is the council's own wording, with the papers it was decided on.

Item20

Resolved

The report was noted.
Word for word from the decision Sevenoaks published for this meeting. Source: cds.sevenoaks.gov.uk

Follow this further

Built from Sevenoaks's papers

What the report saysPro

Report to Sevenoaks Joint Transportation Board

To: Sevenoaks Joint Transportation Board

By: KCC Highways and Transportation

Date: 3 September 2015

Subject: Highway Works Programme 2015/16

Classification: Information Only

Summary: This report updates Members on the identified schemes approved for construction in 2015/16

1. Introduction

This report provides an update and summarises schemes that have been programmed for delivery in 2015/16

Footway and Carriageway Improvement Schemes – see Appendix A

Drainage Repairs & Improvements – see Appendix B

Street Lighting – see Appendix C

Transportation and Safety Schemes – see Appendix D

• Casualty Reduction Measures – see Appendix D1 • Integrated Transport Schemes – see Appendix D2 • Local Growth Fund – see Appendix D3

Developer Funded Works – see Appendix E

Bridge Works – see Appendix F

Traffic Systems – see Appendix G

Combined Member Fund – see Appendix H

Conclusion

1. This report is for Members information.

Contact Officers:

The following contact officers can be contacted on 03000 418181

Carol Valentine Highway Manager (West) Julian Cook Sevenoaks District Manager Sue Kinsella Street Lighting Manager Katie Lewis Drainage Manager Alan Casson Resurfacing Manager Tony Ambrose Structures Manager Toby Butler Traffic Systems Appendix A – Footway and Carriageway Improvement Schemes

The delivery of these schemes is weather dependent; should it prove not possible to carry out these works on the planned dates, new dates will be arranged and the residents will be informed by a letter drop to their homes.

Machine Resurfacing – Contact Officer [name removed] Name Parish Extent of Works Current Status

From previous surfacing Programmed 21st A225 Eynsford Road Eynsford/Farningham at Mill Lane to Beesfield October (3 nights) Lane

Adjacent Subway and Programmed 18th A224 Pohill Dunton Green adjacent Helipad on August (2 nights) Crow Drive

B2211 Sundridge South of Turvins Farm Programmed 17th Chevening Road and Pond August (1 night)

Outside Westerham Programmed 14th A233 Westerham Hill Westerham Heights Farm August (1 night)

Footway Improvement - Contact Officer [name removed] and Description Road Name Parish Current Status of Works From its junction with Works to be Garth Road to its programmed, junction with Beechmont currently liaising Road – completion of Brattlewood Sevenoaks with legal and postponed replacement local resident in of existing asphalt regard to allergy surface and renewal of issues kerbs where required

From its junction with Works to be The Rise to its junction programmed, with Weald Road - currently liaising completion of postponed Garth Road Sevenoaks with legal and replacement of existing local resident in asphalt surface and regard to allergy renewal of kerbs where issues required

Entire Length Programmed to (replacement of existing commence on 10th Donnington Road Dunton Green asphalt surface and August 2015 for 2 renewal of kerbs where weeks required) From its junction with Programmed to London Road to the commence on Argyle Road Sevenoaks junction with South Park 18th August 2015 (Footway protection for 2 days treatment)

Surface Treatments – Contact Officer [name removed] Dressing Schemes

Road Name Parish Extent of Works Current Status

From its junction with Botsom Lane to its Knatts Valley Road West Kingsdown Completed junction with Tinker Pot Lane

St Clere Hill Road Whole length including West Kingsdown Completed St Clere Hill

Hartley Bottom Road From its junction with Ash-Cum-Ridley Pease Hill to its junction Completed with Redhill Road

Valley Road / From its junction with Fawkham Road Fawkham/Longfield and Scudders Hill to its Completed New Barn junction with railway bridge

Church Road From its junction with Ash Cum Ridley/Hartley Ash Road to 30mph Completed speed limit plates

From its junction with Bullfinch Lane London Road to its Riverhead/Chevening Completed junction with Chipstead Lane

From its junction with Sevenoaks/Sevenoaks Gracious Lane A225 to its junction with Completed Weald Oak Lane

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Sevenoaks Highway Works Programme: September 2015Report 86 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Sevenoaks

Search all
  1. Sevenoaks Highway Works Programme - September 2015This decision
  2. Sevenoaks Highways Works Programme 2017/18Noted
  3. Sevenoaks Highway Works Programme - December 2017Noted
  4. Sevenoaks Highway Works ProgrammeNoted
  5. Sevenoaks Highway Works ProgrammeNoted
  6. Sevenoaks Highway Works Programme 2016/17Noted

More from Sevenoaks Sevenoaks Joint Transportation Board

All decisions
MeetingDecisionOutcome
17 Mar 2026 MinutesThat the minutes of the meeting held 14 October 2025 be approved and signed by the Chairman as a correct record. Approved Open
17 Mar 2026 Petition - Crossing at Bessels GreenThat the concerns raised by the petition be evaluated by Officers and a report brought back to a future meeting of th... Decided Open
17 Mar 2026 Petition - Commuter Parking, Cherry AvenueThat the concerns raised by the petition be evaluated by Officers and a report brought back to a future meeting of th... Decided Open
17 Mar 2026 Sevenoaks 20mph Zone - 1 Year UpdateThat the report be noted. Noted Open
17 Mar 2026 Active Travel UpdateThat the report be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies