Resolved
The report be noted
Sevenoaks Joint Transportation Board noted this item on Tuesday 8 December 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
The report be noted
To: Sevenoaks Joint Transportation Board
By: KCC Highways and Transportation
Date: 8th December 2015
Subject: Highway Works Programme 2015/16
Classification: Information Only
Summary: This report updates Members on the identified schemes approved for construction in 2015/16
1. Introduction
1(1)This report provides an update and summarises schemes that have been programmed for delivery in 2015/16
2. Footway and Carriageway Improvement Schemes – see Appendix A
3. Drainage Repairs & Improvements – see Appendix B
4. Street Lighting – see Appendix C
5. Transportation and Safety Schemes – see Appendix D
• Casualty Reduction Measures – see Appendix D1 • Integrated Transport Schemes – see Appendix D2 • Local Growth Fund – see Appendix D3
6. Developer Funded Works – see Appendix E
7. Bridge Works – see Appendix F
8. Traffic Systems – see Appendix G
9. Combined Member Fund – see Appendix H
10. Conclusion
10(1) This report is for Members information.
Contacts: Carol Valentine / Julian Cook 03000 418181
Contact Officers:
The following contact officers can be contacted on 03000 418181
Carol Valentine Highway Manager (West) Julian Cook Sevenoaks District Manager Sue Kinsella Street Lighting Manager Katie Moreton Drainage Manager/ Structures Manager Alan Casson Resurfacing Manager Toby Butler Traffic Systems Appendix A – Footway and Carriageway Improvement Schemes
The delivery of these schemes is weather dependent; should it prove not possible to carry out these works on the planned dates, new dates will be arranged and the residents will be informed by a letter drop to their homes.
Machine Resurfacing – Contact Officer [name removed] Name Parish Extent of Works Current Status
st From previous surfacing at Programmed 21 A225 Eynsford Road Eynsford/Farningham Mill Lane to Beesfield Lane October (3 nights)
Adjacent Subway and Completed A224 Pohill Dunton Green adjacent Helipad on Crow Drive
South of Turvins Farm and Completed B2211 Sundridge Road Chevening Pond
Outside Westerham Completed A233 Westerham Hill Westerham Heights Farm
Footway Improvement - Contact Officer [name removed] Name Parish Extent and Description Current Status of Works From its junction with Garth Road to its junction with Works to be Beechmont Road – programmed, Completion of postponed currently liaising Brattlewood Sevenoaks replacement of existing with legal and local asphalt surface and resident in regard to renewal of kerbs where allergy issues. required From its junction with The Works to be Rise to its junction with programmed, Weald Road - Completion currently liaising Garth Road Sevenoaks of postponed replacement with legal and local of existing asphalt surface resident in regard to and renewal of kerbs allergy issues. where required Entire Length (replacement of existing asphalt surface Completed Donnington Road Dunton Green and renewal of kerbs where required) From its junction with London Road to the Argyle Road Sevenoaks junction with South Park. Completed (Footway protection treatment)
Surface Treatments – Contact Officer [name removed] Surfacing Schemes
From its junction with Completed Hildenborough Road to Powder Mill Lane Leigh de-restriction/30mph speed limit plates
From its junction with Completed Lower Green to its High Street Leigh junction with Powder Mill Lane
From the High Friction Completed Surfacing at railway Tonbridge Road Chiddingstone bridge double bends to approx 300m east of Bore Place Road
From its junction with Completed Hever Lane Hever/Edenbridge/Cowden B2026 to its junction with Station Road
From its junction with Completed Blackhall Lane to its Park Lane Seal junction with Bitchet Green Road
From its junction with Completed Holmsdale Road to its East Hill South Darenth junction with Rabbits Road
Appendix B – Drainage
Drainage Works – Contact Officer Kathryn Lewis
Road Name Parish Description of Works Current Status
No Drainage works planned over £5000 Appendix C – Street Lighting
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Sevenoaks Highway Works ProgrammeReport | 98 KB | DownloadRead as text |
Follow Sevenoaks Joint Transportation Board at Sevenoaks and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Mar 2026 | MinutesThat the minutes of the meeting held 14 October 2025 be approved and signed by the Chairman as a correct record. | Approved | Open |
| 17 Mar 2026 | Petition - Crossing at Bessels GreenThat the concerns raised by the petition be evaluated by Officers and a report brought back to a future meeting of th... | Decided | Open |
| 17 Mar 2026 | Petition - Commuter Parking, Cherry AvenueThat the concerns raised by the petition be evaluated by Officers and a report brought back to a future meeting of th... | Decided | Open |
| 17 Mar 2026 | Sevenoaks 20mph Zone - 1 Year UpdateThat the report be noted. | Noted | Open |
| 17 Mar 2026 | Active Travel UpdateThat the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.