Internal Audit 2015/16 - 2nd Progress Report

Noted Finance 5 papers

Audit Committee noted this item on Tuesday 12 January 2016. Below is the council's own wording, with the papers it was decided on.

Item34

Resolved

That a) the contents of the report and the progress made by the Internal Audit Team in delivering the 2015/16 Annual Internal Audit Plan, be noted; and b) the amendments to the Internal Audit Plan 2015/16 as set out in Appendix A to the report, be approved.
Word for word from the decision Sevenoaks published for this meeting. Source: cds.sevenoaks.gov.uk

Follow this further

Built from Sevenoaks's papers

What the report saysPro

Report to Audit Committee

INTERNAL AUDIT 2015/16 – SECOND PROGRESS REPORT

Audit Committee – 12 January 2016

Report of Chief Finance Officer

Status: For Consideration

Key Decision: No

This report supports the Key Aim of Effective Delivery of the Corporate Plan

Portfolio Holder Cllr. Searles

Contact Officer(s) Bami Cole, ext.7236

Recommendation to Audit Committee: That Members

a) note the contents of the report and the progress made by the Internal Audit Team in delivering the 2015/16 Annual Internal Audit Plan; and

b) approve the amendments to the Internal Audit Plan 2015/16 as set out in Appendix A to the report.

Reason for recommendation: The Audit Committee is required to review the progress of the Internal Audit Plan and approve amendments to the Annual Plan in compliance with its terms of reference.

Introduction

1 This report provides details of the progress of the Internal Audit Team in delivering the Annual Internal Audit Plan 2015/16 and outcomes of final Internal Audit reports issued since the meeting of the committee in September 2015.

2 The Internal Audit function is a key process of the Council’s overall governance arrangements. Its key purpose is to conduct independent reviews of the Council’s system of internal controls and to provide an assurance to both Senior Management and Members regarding the effectiveness of such systems. In fulfilling his duty and responsibilities, the Audit, Risk and Anti-Fraud Manager, is required to report the progress made in delivering the assurance requirements to the Audit Committee, in accordance with regulatory requirements and relevant professional standards. Summary of Issues Raised Within the Report:

3 A summary of progress made towards delivering the assurance requirements for 2015/16 is attached as Appendix A to this report, which sets out details of the reviews agreed by the Audit Committee in March 2015. Members may note that thirteen reviews have commenced, four have been finalised, four at draft report stage and the remaining five are at various stages of completion. This is equivalent to 57% of the original plan. Comparatively, this is a significant improvement to last year’s out-turn, as could be seen on Appendix A.

Amendments to the Audit Plan

4 Members are advised that the Internal Audit plan 2015/16 has been amended to take account of existing capacity and to reflect the assurance priorities for the rest of the municipal year. Some productive capacities have been lost, partly due to carrying vacancies and the need to train and develop new staff into their roles. To this effect, it is necessary to carry forward five reviews. Senior management have approved the proposed amendments to the plan as set out below.

5 Details of the amendments are set out on Appendix A. In particular, the following items are proposed to be deferred to next year’s assurance plan; Items 3, 7, 8, 9 and 18. However, prior to inclusion, they would be subjected to the annual risk assessment and a review of assurance needs and priorities, as part of the annual planning process.

6 Members are advised that the proposed changes to the plan will not have a material impact on the level of assurance that could be provided in 2015/16; as the proposals take account of assessed risks and assurance needs.

7 A revised resource plan is attached as Appendix B and shows how Internal Audit resources will be used for the rest of the period.

8 Appendix C sets out details of the final reports which have been issued since the last meeting of this committee It also provides a brief summary of the findings and recommendations agreed with service management, to address any areas for further improvements required to strengthen internal controls. Further details on any of the issues raised on the report summaries would be provided to Members of this Committee on request.

Internal Audit Resources

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
08 Internal Audit 2015-16: 2nd Progress Report Appendix A: Progress Against 2014-15 PlanAppendix 36 KB Download
PDF
08 Internal Audit 2015-16: 2nd Progress Report Appendix B: Revised Resource PlanAppendix 19 KB Download
PDF
08 Internal Audit 2015-16: 2nd Progress Report Appendix C: Summary of Final ReportsAppendix 60 KB Download
PDF
08 Internal Audit 2015-16: 2nd Progress Report Appendix D: Audit Opinions: DefinitionsAppendix 22 KB Download
PDF
Internal Audit 2015/16: 2nd Progress ReportReport 35 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Sevenoaks

Search all
  1. Internal Audit 2015/16 - 2nd Progress ReportThis decision
  2. Internal Audit Annual Report and OpinionNoted
  3. Internal Audit Progress Report 2025/26Noted
  4. Internal Audit CharterApproved
  5. Internal Audit StrategyApproved
  6. Internal Audit Progress ReportNoted

More from Sevenoaks Audit Committee

All decisions
MeetingDecisionOutcome
8 Jul 2026 MinutesThat the of the Audit Committee held on 14 April 2026, be signed and approved by the Chairman as a correct record. Approved Open
8 Jul 2026 Member Allowance Scheme MonitoringThat the report be noted. Noted Open
8 Jul 2026 Statement of Accounts 2025/26 - progress update and Establishment of Member Working GroupThat a) the update on progress on the 2025/26 draft Statement of Accounts be noted; b) a member working group be set ... Noted Open
8 Jul 2026 Internal Audit Annual Report and OpinionThat the report be noted. Noted Open
8 Jul 2026 Review of Effectiveness of the Audit CommitteeThat the Self-Assessment Review of the Effectiveness of the Audit Committee (Appendix A) for 2025/26 be approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies