Resolved

That the progress made in the delivery of a new Council website be noted.
Word for word from the decision Sevenoaks published for this meeting. Source: cds.sevenoaks.gov.uk

Follow this further

Built from Sevenoaks's papers

What the report saysPro

Report to Policy & Performance Advisory Committee

WEBSITE & TRANSPARENCY UPDATE

Policy and Performance Advisory Committee Meeting - 1 March 2016

Report of: Chief Officer Corporate Support

Status: For Consideration

Key Decision: No

This report supports the Council’s promise to provide value for money

Portfolio Holder Cllr. Fleming

Contact Officers Amy Wilton Ext. 7280 & Lee Banks Ext. 7161

Recommendation to Policy and Performance Advisory Committee:

To note the progress made in the delivery of a new Council website

Reason for recommendation: To ensure that Members remain aware of the progress being made in the delivery of a new website for the Council.

Introduction and Background

1 During 2014 the Council set out a number of corporate projects that it wanted to achieve to support the commitments it made within its Corporate Plan. These projects included one focused on the customer experience which incorporated the delivery of a new council website.

2 Members have received regular updates over the last year on progress of this project. At the meeting of this Committee in September last year it was reported that the Council had appointed Jadu to provide the new website and a project start meeting had taken place. A project plan has been provided to the Council which sets out in detail what is required of both the Council and the supplier to ensure the new website is delivered in agreed timescales.

3 This report provides Members with an update on progress with the project as well as the work the Council has planned to improve the way in which it publishes the range of data required under the Local Government Transparency Code.

Website Update

4 The design phase of the website is now complete and has been signed off. There are two phases currently under way. The build phase, which is in progress with Jadu. This is the technical phase of designing the structure of the new website. The other phase is content migration. Internally, officers are reviewing all of the information on the Council’s current website, in order to create new content that fits with the customer focussed aims of the new website.

5 Overall project management is being provided by Jadu, with regular weekly calls between the Jadu project manager and the Corporate Customer Services & Delivery Manager. The project is running to plan and is on track to achieve all deadlines.

6 The Corporate Customer Services & Delivery Manager will provide a verbal update to the Advisory Committee at the meeting to bring Members up to date with the very latest progress on the project.

Local Government Transparency Code

7 Under the Local Government Transparency Code 2015 the Council is required by Regulations to publish 13 different sets of data and to make this data available free for re-use. The data sets required are currently published on the Council website at www.sevenoaks.gov.uk/transparency, and include expenditure exceeding £500, procurement information, local authority land and senior officer salaries. A full record of the data required to be published is available within the background papers highlighted at the end of this report.

8 Currently the Council publishes its data to the minimum required standard by publishing in an Excel document format and /or a PDF document format. Although this satisfies the requirements of the Regulations it is less helpful to customers and others that may wish to re-use the data, for reasons which may include developing applications to support residents to more clearly understand the Council’s data.

9 To enable the Council to improve its overall approach to transparency and the provision of open data sets a plan is in place to develop a secondary website which will be designed deliberately to host data and information in a format that may not be possible within the existing plans for the new Council website.

10 Examples available elsewhere for Members information include:

• Nottingham City Council - http://www.opendatanottingham.org.uk/Default.aspx

• Greater London Authority - http://data.london.gov.uk/

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Transparency and website updateReport 32 KB DownloadRead as text

At this meeting

Whole meeting

More from Sevenoaks Policy & Performance Advisory Committee

All decisions
MeetingDecisionOutcome
29 Nov 2018 MinutesThat the of the meeting of the Advisory Committee held on 20 September 2018 be approved and signed by the Chairman as... Approved Open
29 Nov 2018 Communications ReviewThat the report be noted . Noted Open
29 Nov 2018 Budget 2019/20: Service Dashboard and Service Change Impact Assessments (SCIAs)That a) no growth and savings proposals had been identified; and b) the following saving suggestions be discussed fur... Agreed Open
20 Sep 2018 MinutesThat the of the meeting of the Advisory Committee held on 21 June 2018 be approved and signed by the Chairman as a co... Approved Open
20 Sep 2018 Customer RedesignThat the report be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies