That it be recommended to Cabinet, that a) in principle, a joint agreement be entered into with TWBC and T&MBC to establish a West Kent CCTV hub, based at the Sevenoaks offices; b) the preferred monitoring arrangements be Option A as set out within the report ‘24 hour CCTV coverage and out of hours service for all 3 Councils. This model includes a dedicated Supervisor and 12 operators. This provides, mainly for three operators to be on duty, but at certain less busy times this will be reduced to 2 operators. Estimated Cost: £104,933 per Council; and c) a one-off Capital budget of £37,300 be approved, representing 50% of the cost of enlarging the existing Sevenoaks CCTV control room.
Word for word from the decision Sevenoaks published for this meeting.Source: cds.sevenoaks.gov.uk
Page 1 of 25 Document Revision History Revision Date Status Description Issued By Signature 1 21/1/15 First Stage Report G Ross
Initial Proposal Completed by: Graeme Ross
Signature:
In the capacity of: Projects Manager
Dated:
Acorn House, Acorn Close, Five Oak Green, Tonbridge, Kent TN12 6RH
Email: [email removed]
Tel: 01892 832112 – Fax: 01892 836651
Page 2 of 25 1. Preamble
Sevenoaks Borough Council have issued an instruction to complete a feasibility study for the ‘merging’ of 3 control room operations into one. The basis of this merger is prescriptive at this stage and seeks to achieve the aim with the minimal investment and disruption to the existing systems. This document presents the most effective actions required to achieve these aims.
The original brief provided has given two options for moving forward; -
Option 1 – Merge into one control room while maintaining current (Control Equipment Room) CER arrangements
Option 2 – Merge into one control room but moving Tunbridge Wells CER into another nearby building
The document is divided into 6 Sections; -
Section 1 (This Section) provides a description of the basis of the directive and how the document has been developed and presented in order to achieve that directive. Section 2 – Lists the full operational requirements as identified by the three boroughs. Section 3 – Provides the initial observations from these Operational Requirements and hence sets the scene for moving forward with the study. Section 4 – Provides details of surveys made at the three current locations and what conclusions can be brought form the result of those surveys. Section 5 – Provides the conclusions that are derived from Sections 2 – 4 and hence the basis of providing a full and final solution.
Within Section 5 we will take each location and work through each of the two options individually, obviously cross-referring where the options ‘intersect’ and the activities are basically the same. Where there are multiple considerations regarding he actions that could be taken, we will provide all those considerations and offer a conclusion on the one we believe to be the best after all points have been considered. This way you will have the opportunity to follow out train of thought and decide on any other options you wish to consider for stage two of the report.
Stage 2 of this report, should you choose to commission it will provide far more detail on the works that will be undertaken to achieve the final agreed solution, based upon the final conclusions and any post-report dialogue.
Page 3 of 25 2. Operational Requirements 2.1. Basis of enquiry 2.2. The Tri-Council CCTV operation (TCCO) formed by Tonbridge & Malling District Council, Tunbridge Wells Borough Council and Sevenoaks District Council are seeking to rationalise their control room operations into one location. 2.3. There are two basic options; - 2.3.1. The Tunbridge Wells Control Equipment Hub to remain where it is 2.3.2. The Tunbridge Wells Control Equipment Hub to move to a new location within 500m of the current location.
2.4Operational Requirements 2.5. The control room would have 3 separate workstations with their own associated wall monitors to allow Tonbridge, Tunbridge Wells and Sevenoaks to operate separately. 2.6. There is no requirement for the systems to operate as a single integrated solution at this time. 2.7. There is no requirement for use as a silver command for the police 2.8. At this stage there is no operational requirement to replace the existing control & recording systems. 2.9. The current arrangement at Tonbridge can be retained 2.10. Downloads will be carried out using two separate review systems on one PC, one for Sevenoaks and one for Tonbridge/Tunbridge Wells. 2.11. Training and use of operatives across both systems will continue as they currently are and will be managed by Sevenoaks.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.