Cabinet, Thursday 21 April 2016 at 7.00pm

Asset maintenance - White Oak Leisure Centre, Swanley

Approved Executive 3 papers

Cabinet approved this item on Thursday 21 April 2016. Below is the council's own wording, with the papers it was decided on.

Item97

Resolved

That a) the works identified in the report, at an estimated cost of £90,000, be undertaken, and this expenditure be funded by a combination of asset maintenance budgets (£25,860) and by a supplementary estimate (£64,140); b) any underspend in the 2015/16 leisure asset maintenance budget be carried forward into 2016/17; c) authority be granted to the Finance Portfolio Holder to authorise any expenditure above the approved asset maintenance budget to secure the continued safe operation of the White Oak Leisure Centre for the short to medium term; and d) recommended to Council that the works identified to be carried out at White Oak Leisure Centre, at an estimated cost of £64,140 be funded by a supplementary estimate.
Word for word from the decision Sevenoaks published for this meeting. Source: cds.sevenoaks.gov.uk

Follow this further

Built from Sevenoaks's papers

What the report saysPro

Report to Cabinet

ASSET MAINTENANCE – WHITE OAK LEISURE CENTRE, SWANLEY

Cabinet – 21 April 2016

Report of Chief Officer Environmental and Operational Services

Status: For decision

Also considered by: Finance Advisory Committee – 18 April 2016 Council – 26 April 2016

Key Decision: Yes

Executive Summary: This report highlights maintenance works required to the White Oak Leisure Centre (WOLC), Swanley for continued, safe operation in the short to medium term.

This report supports the Key Aim of a safe and healthy environment.

Portfolio Holder Cllr. Searles

Contact Officer Kevin Tomsett Ext. 7368

Recommendation to Finance Advisory Committee:

It be recommended to Cabinet that:-

(a) The works identified in the report, at an estimated cost of £90,000, be undertaken, and this expenditure be funded by a combination of asset maintenance budgets (£25,860) and by a supplementary estimate (£64,140).

(b) That any underspend in the 2015/16 leisure asset maintenance budget be carried forward into 2016/17.

(c) That authority be granted to the Finance Portfolio Holder to authorise any expenditure above the approved asset maintenance budget to secure the continued safe operation of the WOLC for the short to medium term.

Recommendation to Cabinet:

(a) That the works identified in the report, at an estimated cost of £90,000, be undertaken and it be recommended to Council, that £64,140 of expenditure be funded by a supplementary estimate.

(b) That any underspend in the 2015/16 leisure asset maintenance budget be carried forward into 2016/17. (c) That authority be granted to the Finance Portfolio Holder to authorise any expenditure above the approved asset maintenance budget to secure the continued safe operation of the WOLC for the short to medium term.

Recommendation to Council:

(a) That works identified to be carried out at White Oak Leisure Centre, at an estimated cost of £64,140, be funded by a supplementary estimate.

Reason for recommendation: The maintenance works identified in the report are required to the White Oak Leisure Centre, Swanley, to ensure the continued, safe operation in the short to medium term.

Introduction and Background

1 White Oak Leisure Centre in Swanley was constructed in the mid 1960s. The flumes were added in the 1980s and the main reception and café areas were refurbished in 2000 at a cost of £3m.

2 The centre provides a 33 metre pool with diving pit, teaching pool, gym & exercise studio, 6 court sports hall, martial arts rooms, practice hall, 3 squash courts, soft play area, crèche, cafeteria and a 3-ride flume.

3 The centre is leased to Sencio Community Leisure for a period of 25 years from 2004 to 2029 with the District Council remaining responsible for maintaining the structure and main plant; all other maintenance and improvement is the responsibility of Sencio.

4 Members asked Officers to undertake a feasibility study for the replacement of the leisure centre on one of two sites, the Olympic site and the existing Whiteoak site. The feasibility study has commenced and is nearing completion. However, following the decision to commission a masterplan for Swanley, Officers were asked to pause the feasibility study in order to consider any further options that might become available. Work into the feasibility of the provision of a new facility will re-commence once this is complete.

Proposed Works

5 It is essential, in order to keep the Leisure Centre, particularly the pool, operational in the short to medium term, and until its future is determined, that the following works are undertaken with some urgency. Failure to undertake these works would require closure of parts or all of the pool operation. Certain works, namely the pool ceiling, have health and safety implications if not carried out. This work and the work to the flume housing and repair of roof leaks will be funded by approved asset maintenance budgets.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
16 Asset Maintenance: White Oak Leisure Centre Swanley: FAC 18.04.16Report 33 KB DownloadRead as text
PDF
16 Cover minute TFReport 12 KB Download
PDF
Asset maintenance: White Oak Leisure Centre, SwanleyReport 19 KB Download

At this meeting

Whole meeting

On this subject at Sevenoaks

Search all
  1. Asset maintenance - White Oak Leisure Centre, SwanleyThis decision
  2. Capital Programme and Asset Maintenance 2026-29Noted
  3. Capital Programme and Asset Maintenance 2025-28Noted
  4. Capital Programme and Asset Maintenance 2024-27Noted
  5. Capital Programme and Asset Maintenance 2023-26Noted
  6. Capital Programme & Asset Maintenance 2022/25Noted

More from Sevenoaks Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 MinutesThat the of the Cabinet meeting held on 7 July 2026 and the Special Cabinet meeting held on 14 July, be approved and ... Approved Open
22 Sep 2026 Appointments to Advisory Committees & BoardsThat the membership for the municipal year 2026/27, as set out in the supplementary agenda to the report, be approved. Approved Open
22 Sep 2026 Safeguarding Policy 2026 - 2030That it be recommended to Full Council that the contents of the report be noted and the safeguarding policy 2026-2030... Noted Open
22 Sep 2026 Financial Monitoring to end of July 2026That the report be noted. Noted Open
22 Sep 2026 Treasury Management 2025/26 Annual ReportThat the Treasury Management report for 2025/26, be approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies