Sevenoaks Joint Transportation Board, Thursday 26 May 2016 at 7.00pm

Sevenoaks Highway Works Programme - May 2016

Noted Committee 1 paper

Sevenoaks Joint Transportation Board noted this item on Thursday 26 May 2016. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

That the report be noted.
Word for word from the decision Sevenoaks published for this meeting. Source: cds.sevenoaks.gov.uk

Follow this further

Built from Sevenoaks's papers

What the report saysPro

Report to Sevenoaks Joint Transportation Board

To: Sevenoaks Joint Transportation Board

By: KCC Highways and Transportation

Date: 26th May 2016

Subject: Highway Works Programme 2016/17

Classification: Information Only

Summary: This report updates Members on the identified schemes approved for construction in 2016/17

1. Introduction

1(1)This report provides an update and summarises schemes that have been programmed for delivery in 2015/16

2. Footway and Carriageway Improvement Schemes – see Appendix A

3. Drainage Repairs & Improvements – see Appendix B

4. Street Lighting – see Appendix C

5. Transportation and Safety Schemes – see Appendix D

• Casualty Reduction Measures – see Appendix D1 • Integrated Transport Schemes – see Appendix D2 • Local Growth Fund – see Appendix D3 • LTP Public Health Scheme - see Appendix D4

6. Developer Funded Works – see Appendix E

7. Bridge Works – see Appendix F

8. Traffic Systems – see Appendix G

9. Combined Member Fund – see Appendix H

10. Conclusion

10(1) This report is for Members information.

Contacts: Carol Valentine / Julian Cook 03000 418181

Contact Officers:

The following contact officers can be contacted on 03000 418181 Carol Valentine Highway Manager (West) Julian Cook Sevenoaks District Manager Sue Kinsella Street Lighting Manager Katie Moreton Drainage Manager / Structures Manager Alan Casson Resurfacing Manager Toby Butler Traffic Systems Jamie Watson Transportation and Safety Schemes / Combined Member Fund Jamie Hare Developer Funded Work Appendix A – Footway and Carriageway Improvement Schemes

The delivery of these schemes is weather dependent; should it prove not possible to carry out these works on the planned dates, new dates will be arranged and the residents will be informed by a letter drop to their homes.

Machine Resurfacing – Contact Officer [name removed] Name Parish Extent of Works Current Status

From Post Office to the Chinese Restaurant To be A25 Main Road Sundridge (east of Sundridge programmed crossroads) July/August 2016 100m heading towards London Road Farningham roundabout junction with Programmed 25th Dartford Road April 2016

Weald Interchange/ Sections of Weald Programmed 8th Sevenoaks Weald Morley’s Road Interchange June 2016

Lullingstone Ave to Swanley Lane Swanley roundabout junction Completed Bartholomew Way

Grange Close to London Programmed 27th Market Square Westerham Road April 2016

High Street Eynsford Junction with Riverside Programmed 28th April 2016

Wickenden Road to To be St Johns Hill Sevenoaks Hospital Road programmed July 2016 Mount Harry Road up to To be St Johns Hill Sevenoaks and including Barrack programmed July Corner 2016 100m across junction Overden Road Chevening with Chevening and Programmed 10th Sundridge Road June 2016

Farningham Hill Entrance to Farningham Completed Farningham Road Hill Road

Footway Improvement - Contact Officer [name removed] Name Parish Extent and Description Current Status of Works Works to be From its junction with programmed, Garth Road to its currently liaising junction with Beechmont with legal and Road – Completion of Brattle Wood Sevenoaks local resident in postponed replacement regard to allergy of existing asphalt issues. Possible surface and renewal of commencement in kerbs where required June 2016 From its junction with Quebec Avenue Westerham Hollingworth Way to the Works to be end of the Avenue. programmed. (Footway Reconstruction) Entire Length. Works to be Darenth Gardens Westerham (Footway programmed. Reconstruction) Various sections To be between Witches Lane programmed and the London Road (Works subject to Worships Hill Riverhead roundabout. (North side specialist only, Footway protection contractor treatment) assessment)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Sevenoaks Highway Works Programme: May 2016Report 107 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Sevenoaks

Search all
  1. Sevenoaks Highway Works Programme - May 2016This decision
  2. Sevenoaks Highways Works Programme 2017/18Noted
  3. Sevenoaks Highway Works Programme - December 2017Noted
  4. Sevenoaks Highway Works ProgrammeNoted
  5. Sevenoaks Highway Works ProgrammeNoted
  6. Sevenoaks Highway Works Programme 2016/17Noted

More from Sevenoaks Sevenoaks Joint Transportation Board

All decisions
MeetingDecisionOutcome
17 Mar 2026 MinutesThat the minutes of the meeting held 14 October 2025 be approved and signed by the Chairman as a correct record. Approved Open
17 Mar 2026 Petition - Crossing at Bessels GreenThat the concerns raised by the petition be evaluated by Officers and a report brought back to a future meeting of th... Decided Open
17 Mar 2026 Petition - Commuter Parking, Cherry AvenueThat the concerns raised by the petition be evaluated by Officers and a report brought back to a future meeting of th... Decided Open
17 Mar 2026 Sevenoaks 20mph Zone - 1 Year UpdateThat the report be noted. Noted Open