Resolved
That funding for the Otford Tower be taken from the Budget Stabilisation Fund and not from the General Fund Reserve.
Cabinet decided this item on Thursday 9 June 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
That funding for the Otford Tower be taken from the Budget Stabilisation Fund and not from the General Fund Reserve.
PROVISIONAL OUTTURN 2015/16
Cabinet - 9 June 2016
Report of: Chief Finance Officer
Status: For recommendation to Cabinet
Also considered by: Finance Advisory Committee – 24 May 2016
Key Decision: No
This report supports the Key Aim of Effective Management of Council Resources
Portfolio Holder Cllr. Searles
Contact Officer Head of Finance – Helen Martin ext 7483
Recommendation to Finance Advisory Committee: That
(a) the outturn report for 2015/16 be noted;
(b) the recommendations below to Cabinet, be endorsed.
Recommendation to Cabinet: It be RESOLVED that:
(a) Funding for the Otford Palace Tower be taken from the Budget Stabilisation Fund and not from the General Fund Reserve.
Introduction
1 Provisional Financial Outturn figures for 201/16 are attached at Appendix A. These results will be presented to Cabinet at its meeting on 9 June 2016.
2 A favourable variance of £30,000 has been achieved. A summary of this variance, which represents is 0.2% of the net service expenditure budget, is given as Appendix A.
3 It was approved by Cabinet on 4 February 2016 that any favourable variances achieved on the 2015/16 budget be put into the Budget Stabilisation Reserve.
4 Revenue carry forward requests were considered at the previous meeting of this Advisory Committee and were approved by Cabinet.
5 A provisional amount of £150,000 has been included for retained business rates. This figure is still provisional as the information from the Valuation Office was not received early enough to allow the Collection Fund accounts to be completed in time for this meeting. Cabinet (21 April 2016) agreed that additional income arising in 2015/16 from business rate retention could be transferred to a Corporate Projects Reserve.
6 Main reasons for the year end variances are given in the following paragraphs and detailed explanations are provided as Appendix B.
High Level Analysis of Variances
7 Property Investment Strategy Income was a new source of income in 2015/16 and represented income derived from the acquisition of commercial property in Sevenoaks and Swanley. A total of £422,000 was received which included income from early surrender of one of the leases.
8 Revenues and Benefits – within Finance, additional resources were used to help address the Benefits workload and to be pro-active in contacting Council Tax support customers. The funding of that additional cost was shared with Dartford.
9 Income from Car Parks, On Street Parking and Planning exceeded Budget. There was a surplus on the On Street Parking budget and this can only be spent on permitted purposes within the Traffic Management Act 2004. As agreed by Cabinet on 5 February 2015, this surplus had been transferred to the On Street Parking Reserve.
10 Pay costs were slightly below budget due to the pay award for the year being below budget, vacant posts being higher than expected and tight control over overtime costs.
11 The surplus on the Direct Services Trading account was £149,000 better than expected due to additional income, savings on fuel and staffing costs.
Funding from Reserves - Otford Palace –
12 Cabinet (20th July 2015) recommended to Council that a sum of £130,699 from the General Fund Reserve be approved for stabilisation works at the Otford Palace Tower. It is now recommended that the funding for this project is taken from the Budget Stabilisation Reserve. This will enable the General Fund Reserve to remain at £1,500,000 which is considered a prudent level relative to our net service expenditure.
Key Implications
Financial
There are no financial implications arising from this report Legal Implications and Risk Assessment Statement.
Under section 151 of the Local Government Act 1972, the section 151 officer has statutory duties in relation to the financial administration and stewardship of the authority.
Equality Assessment
The decisions recommended through this paper have a remote or low relevance to the substance of the Equality Act. There is no perceived impact on end users.
Conclusions
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
06 Provisional Outturn 2015-16Report | 31 KB | DownloadRead as text |
PDF |
06 Provisional Outturn Appendix AAppendix | 18 KB | Download |
PDF |
06 Provisional Outturn Appendix B...Appendix | 93 KB | Download |
PDF |
Provisional Outturn 2015/16Report | 16 KB | Download |
Follow Cabinet at Sevenoaks and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Sep 2026 | MinutesThat the of the Cabinet meeting held on 7 July 2026 and the Special Cabinet meeting held on 14 July, be approved and ... | Approved | Open |
| 22 Sep 2026 | Appointments to Advisory Committees & BoardsThat the membership for the municipal year 2026/27, as set out in the supplementary agenda to the report, be approved. | Approved | Open |
| 22 Sep 2026 | Safeguarding Policy 2026 - 2030That it be recommended to Full Council that the contents of the report be noted and the safeguarding policy 2026-2030... | Noted | Open |
| 22 Sep 2026 | Financial Monitoring to end of July 2026That the report be noted. | Noted | Open |
| 22 Sep 2026 | Treasury Management 2025/26 Annual ReportThat the Treasury Management report for 2025/26, be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.