Resolved
That the minutes of the Committee held on 18 April 2017 be agreed and signed as a correct record.
Audit Committee agreed this item on Tuesday 13 June 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
That the minutes of the Committee held on 18 April 2017 be agreed and signed as a correct record.
AUDIT COMMITTEE
Minutes of the meeting held on 18 April 2017 commencing at 7.00 pm
Present: Cllr. Grint (Chairman)
Cllrs. Clack, Halford, McArthur, Purves, Reay and Searles
Apologies for absence were received from Cllrs. Edwards-Winser and Layland
Cllr. Scholey was also present.
38. Minutes
Resolved: That the minutes of the Committee held on 10 January 2017 be agreed and signed as a correct record.
39. Declarations of Interest
There were none.
40. Actions from Previous Meeting
There were none.
41. Responses of the Council, Cabinet or Council Committees to the Committee's reports or recommendations
There were none.
42. Internal Audit 2016/17 - 3rd Progress report
The Principal Auditor presented a report which set out progress of the Internal Audit Team in delivering the Annual Audit Plan 2016/17 and outcomes of final Internal Audit reports issued since the meeting of the Committee in January 2017. Since the report was published two further reviews had been finalised bringing the total to 18, with a further three audits at the feedback stage. Eight audits had been removed and four of these reviews would be carried forward to the 2017/18 plan. Members were also advised that since the publication of the agenda a further two audit reports had been issued bringing the total to 11.
Members discussed each of the summaries of the findings of the final reports and recommendations agreed with service management. It was questioned whether there was a procurement policy to encourage smaller businesses and local suppliers and if help was provided for the completion of the documents.
19 Audit Committee - 18 April 2017
Action 1: Chief Officer Environmental and Operational Services to circulate information regarding procurement in particular regarding the approach to local suppliers.
The Committee expressed their thanks to the Audit team for the progress made. It was requested that a letter be sent to the Chief Executive from the Chairman of the Audit Committee expressing thanks for the work of Officers.
Public Sector Equality Duty
Members noted that consideration had been given to impacts under the Public Sector Equality Duty.
Resolved: That
a) the report and progress made by the Internal Audit Team in delivering the 2016/17 Annual Internal Audit Plan be noted; and
b) the Chairman of Audit Committee write to the Chief Executive expressing thanks for the work of Officers.
43. Report on Internal Audit recommendations outstanding
The Principal Auditor presented a report which updated Members on progress of the implementation of Internal Audit Recommendations agreed with management and to report on the outstanding recommendations due for implementation by 31 January 2017. Members were advised that the Council Tax Support recommendation was now complete and remaining feedback would be reported to the Committee in June 2017. Members were advised that as there was a new person in post for Emergency planning, an update on the recommendation made from this review would also be reported to the Committee in June 2017.
Public Sector Equality Duty
Members noted that consideration had been given to impacts under the Public Sector Equality Duty.
Resolved: That
a) no further information or explanation was required; and
b) the reasons for delayed implementation, be noted and the revised dates for implementation provided by management be endorsed, as set out in Appendix B to the report.
44. Internal Audit Plan 2017/18
The Principal Auditor presented the report which incorporated the Annual Internal Audit Plan and Programmed Reviews for 2017/18. The objective of the plan was to ensure that Internal Audit resources were deployed in order to add value to the
20 Audit Committee - 18 April 2017
Council’s objectives, whilst delivering reasonable assurance to the Council, regarding the effectiveness of internal control governance and risk management processes in fulfilment of the Council’s statutory responsibilities.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MinutesMinutes | 43 KB | DownloadRead as text |
Follow Audit Committee at Sevenoaks and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Jul 2026 | MinutesThat the of the Audit Committee held on 14 April 2026, be signed and approved by the Chairman as a correct record. | Approved | Open |
| 8 Jul 2026 | Member Allowance Scheme MonitoringThat the report be noted. | Noted | Open |
| 8 Jul 2026 | Statement of Accounts 2025/26 - progress update and Establishment of Member Working GroupThat a) the update on progress on the 2025/26 draft Statement of Accounts be noted; b) a member working group be set ... | Noted | Open |
| 8 Jul 2026 | Internal Audit Annual Report and OpinionThat the report be noted. | Noted | Open |
| 8 Jul 2026 | Review of Effectiveness of the Audit CommitteeThat the Self-Assessment Review of the Effectiveness of the Audit Committee (Appendix A) for 2025/26 be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.