What was decided
Cabinet noted that recent energy sector regulatory changes have affected the lease being negotiated, requiring a switch to a commercial lease arrangement with South Eastern Water and ESL.
Cabinet approved granting either a long lease with an annual rent and turnover percentage, or an upfront lump-sum premium, as set out in Appendix B.
Cabinet asked the council, with South Eastern Water and ESL, to consider a cooperative model for renewable energy generation and, if viable, include it in the Power Purchase Agreement option.
Why
Recent regulatory changes in the energy sector have impacted the lease the council was negotiating, meaning the agreement must be amended to reflect a commercial lease arrangement.
What happens next
The council will consider, with South Eastern Water and ESL, whether a cooperative model for renewable energy generation is financially viable and could form part of the Power Purchase Agreement option.
The Strategic Head of Property and Commercial Services, in consultation with the Deputy Chief Executive and Chief Officer Finance and Trading and the Head of Legal and Democratic Services, is delegated authority to enter into the necessary legal agreements for granting a long lease of the former Otford Road site.
Options considered
- Approved: Long lease with annual rent and turnover percentage, with later option to acquire locally generated renewable energy. Responds to recent regulatory changes that have affected the original lease being negotiated
- Approved: Upfront lump-sum payment (a premium). Set out in Appendix B as an alternative to the rent and turnover share approach
- To be considered: Cooperative model for renewable energy generation with South Eastern Water and ESL. To be explored for financial viability and, if viable, included in the Power Purchase Agreement option
Implications
- Legal: Authority to enter into the necessary legal agreements is delegated to the Strategic Head of Property and Commercial Services, working with finance and legal officers.
- Financial: Income from the site would take the form of either an annual rent plus a percentage of turnover or an upfront premium, with a later option to acquire locally generated renewable energy subject to legislative changes.
- Other: A cooperative model with South Eastern Water and ESL is to be considered for renewable energy generation, subject to financial viability.
Who and where
- South Eastern Water
- ESL
- Sevenoaks District Council
Timeline
- 2026-06-16: Cabinet decision taken at the meeting on this item
Plain English for the jargon
- ESL: A party to the proposed lease and cooperative discussions alongside the council and South Eastern Water; full name not stated in the decision text.
- Power Purchase Agreement: A contract for the sale and purchase of electricity, here mentioned as an option that could include a cooperative model.
- Premium: An upfront lump-sum payment for granting a lease, offered as an alternative to annual rent and a turnover share.
- Turnover percentage: A share of the revenue generated on the site, paid in addition to an annual rent under the long lease option.