Co-operative Executive decided this item on Wednesday 15 January 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
View the decision text for item 13.
Please refer to paragraph 99 of the main report for the recommendations. ______________________________________________________________
Category of Report: OPEN/CLOSED
Page 227 Statutory and Council Policy Checklist
YES/NO Cleared by: Eugene Walker Legal implications
YES/NO Cleared by:
Equality of Opportunity implications YES/NO Cleared by:
Tackling Health Inequalities implications
YES/NO
Human rights implications
YES/NO :
Environmental and Sustainability implications
YES/NO Economic impact
YES/NO
Community safety implications
YES/NO Human resources implications
YES/NO Property implications
YES/NO
Area(s) affected
Relevant Scrutiny Board if decision called in
Overview and Scrutiny Management Committee
Is the item a matter which is reserved for approval by the City Council? NO
Press release
YES/NO
Page 228 2013/14 Budget Monitoring – Month 7
REVENUE BUDGET & CAPITAL PROGRAMME MONITORING AS AT 31 OCTOBER 2013 Purpose of the Report 1. This report provides the Month 7 monitoring statement on the City Council’s Revenue Budget and Capital Programme for October. The first section covers Revenue Budget Monitoring and the Capital Programmes are reported from paragraph 70.
Revenue Budget Monitoring Summary 2. The budget monitoring position at month 6 indicated a forecast overspend of £5.3m, based on expenditure incurred to date and forecasted trends to the year end. The latest monitoring position at month 7 shows a forecast overspend of £3.6m to the year end: i.e. a forecast improvement of £1.7m since last month. This is summarised in the table below: Portfolio Forecast FY FY Movement Outturn Budget Variance from Month 6 £000s £000s £000s CYPF 88,649 88,629 20 ó PLACE 181,518 181,040 478 ó COMMUNITIES 181,450 170,742 10,708 ò POLICY, PERFORMANCE & COMMUNICATION 2,679 2,617 62 ó RESOURCES 62,301 63,816 (1,515) ò CORPORATE (512,974) (506,844) (6,130) ó GRAND TOTAL 3,623 - 3,623 ò
3. The forecast outturn shows a reducing overspend from the £8.3m overspend reported in month 3 to £3.6m in month 7. This improvement reflects Portfolios attempts to reduce spending but also the use of one- off grants to offset the significant pressures with the Communities portfolio. Further work is being undertaken to deliver a balanced position at year end. The position month by month is shown in the following chart:
Page 229 2013/14 Budget Monitoring – Month 7
4. In terms of the month 7 overall forecast position of £3.6m overspend, the key reasons are:
· Place are showing a forecast overspend of £478k, due to an estimated £317k associated with contract negotiations to deliver the waste management savings, additional forecast costs within commercial estate of £164k, a reduction in anticipated markets income of £270k and a potential deficit arising from difficult trading conditions within Sheffield International Venues of £800k . These overspends are partly offset by reductions in forecast spend on the contract and street lighting costs within the Highways Department of £679k.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Revenue Budget and Capital Programme Monitoring 2013/14 (Month 7) as at 31/10/13Report | 314 KB | DownloadRead as text |
Follow Co-operative Executive at Sheffield and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Apr 2022 | The Sheffield Tobacco Control Strategy and Future Commissioning Model 2022-2027.View the decision text for item 8. | Decided | Open |
| 20 Apr 2022 | Parks Tennis ProcurementView the decision text for item 9. | Decided | Open |
| 20 Apr 2022 | Procurement of an Adult Social Care Mental Health Recovery Framework for people with eligible mental health needsView the decision text for item 10. | Decided | Open |
| 20 Apr 2022 | Procurement for the Care and Support services in Extra Care SchemesView the decision text for item 11. | Decided | Open |
| 20 Apr 2022 | Procurement of an Enhanced Supported Living FrameworkView the decision text for item 12. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.