2016/17 Budget Monitoring – Month 10
REVENUE BUDGET & CAPITAL PROGRAMME MONITORING AS AT 31 JANUARY 2017
Purpose of the Report 1. This report provides the Month 10 monitoring statement on Sheffield City Council’s Revenue Budget and Capital Programme for January 2017. Paragraphs 2 – 20 cover Revenue Budget Monitoring, and the Capital Programmes are reported from paragraph 21.
REVENUE BUDGET MONITORING
Summary 2. Previously we have presented the Council’s financial position in two elements, namely the underlying position on the services commissioned/provided by the Council, and the position on services that are commissioned and funded jointly with the health service. For the purpose of this report, we have presented the financial position as just one element; the Council’s overall position.
3. As at month 10, the Council is showing a forecast overspend of £3.3m. This is an improved position of £733k since the Month 9 monitoring report. It should be stressed that this is prior to mitigating savings that are currently being identified by Portfolios to reduce this overspend by year end.
4. The month 9 Budget Monitoring report presented to Cabinet on the 15 th February, highlighted that should this outturn position not improve or the Council continues to overspend, to avoid going below the £12m absolute minimum on the General Fund Reserve, we will un-earmark NHB reserves to cover the overspend. This proposal is to be finalised at year end.
5. The overall Council position is summarised in the table below.
Portfolio FY FY FY Movement Outturn Budget Variance from Month £000s £000s £000s 9 CYPF 73,578 67,032 6,546 ñ COMMUNITIES 145,308 138,580 6,728 ò PLACE 144,325 144,901 (576) ò POLICY, PERFORMANCE & COMMUNICATION 2,480 2,237 243 ó RESOURCES 55,614 56,728 (1,114) ó CORPORATE (417,964) (409,478) (8,487) ò GRAND TOTAL 3,341 - 3,340 ò
Page 145 2016/17 Budget Monitoring – Month 10
6. They key reasons for the Month 10 forecast overspend position of £3.3m are: · Children, Young People and Families (CYPF), based on trends to date, are forecasting to overspend by £6.5m. Placements are reporting a £3.9m overspend; this reflects the full year impact on the current number of placements and the costs for the remainder of the year. Fieldwork Services forecast overspend of £1.1m results from pressures on social workers as a result of increased number of caseloads. Other areas of forecast overspend include delayed savings of £796k on Short Break and Direct payments and £750k relating to health care services because agreement has not yet been secured on joint contributions with the CCG for Children’s Services Payments.
· Communities, based on trends to date, are forecasting an overspend of £6.7m. This is primarily due to a £4.8m overspend as a result of demand pressures in Care and Support relating to Learning Disability Services and Long Term Support. In addition, there is a forecast overspend of £2.9m relating to commissioned services, due mainly to an emerging overspend against Commissioned Mental Health Services. These overspends are partly offset by a number of reductions in spending across the service – a fuller delineation of spending in each service is available in Appendix 1.
· Place are forecasting an underspend of £576k primarily due to additional property rent income.
· Policy, Performance and Communications are forecasting an overspend of £243k due to lower than anticipated advertising income as a result of contract delays.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Budget Monitoring (2)Report | 465 KB | DownloadRead as text |
PDF |
Revenue Budget and Capital Programme 2016/17 Month 10 as at 31 January 2017Report | 128 KB | Download |
Follow Co-operative Executive at Sheffield and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Apr 2022 | The Sheffield Tobacco Control Strategy and Future Commissioning Model 2022-2027.View the decision text for item 8. | Decided | Open |
| 20 Apr 2022 | Parks Tennis ProcurementView the decision text for item 9. | Decided | Open |
| 20 Apr 2022 | Procurement of an Adult Social Care Mental Health Recovery Framework for people with eligible mental health needsView the decision text for item 10. | Decided | Open |
| 20 Apr 2022 | Procurement for the Care and Support services in Extra Care SchemesView the decision text for item 11. | Decided | Open |
| 20 Apr 2022 | Procurement of an Enhanced Supported Living FrameworkView the decision text for item 12. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.