2018/19 Budget Monitoring – Month 9
REVENUE BUDGET & CAPITAL PROGRAMME MONITORING AS AT 31st DECEMBER 2018 Purpose of the Report
1. This report describes the budget monitoring position on the City Council’s Revenue Budget and Capital Programme as at Month 9.
REVENUE BUDGET MONITORING Summary 2. The Council’s revenue budget is displaying a forecast overspend of £10.9m. 3. The Month 6 Report described a £14.2m position, so this represents a £3.3m improvement and as such is to be welcomed. It should be noted that the bulk of the improvement, as described below, is due to one-off improvements in Corporate budgets. Cost pressures within social care services continue to drive budget overspends, reflecting the nationwide issues within that particular sector. 4. The Council will build upon efforts to mitigate this forecast overspend, including further reviews of Corporate expenditure, accelerating some savings plans where possible and continuing to review non-essential spend. It is unlikely that this overspend will be addressed fully before year end, making an overspend position at year end the likely outcome. 5. The position split by Portfolio is summarised in the table below.
Portfolio FY FY FY Movement Outturn Budget Variance from Month £000s £000s £000s 6 PEOPLE 231,620 215,622 15,998 PLACE 189,553 190,612 (1,059) PPC 2,460 2,131 329 RESOURCES 43,803 44,010 (208) CORPORATE (456,574) (452,376) (4,199) GRAND TOTAL 10,861 - 10,861
6. In terms of the forecast outturn position of £10.9m overspend, the key reasons are:
People are forecasting a £16.0m overspend. The key reasons for this position are: o An overspend of £9.4m within Care & Support. The key reasons for this are the effects of increased volume and cost of activity within home care provision of £5.1m, supported living cost increases of £2.6m, the impact of
Page 353 2018/19 Budget Monitoring – Month 9
unachievable savings of £2.6m, with some smaller movements both positive and adverse within the service. o An overspend within Community Services of £82k due to the impact of a delayed MER scheme of £458k, partially offset by a vacancy saving for Community Support workers of £112k, reductions in spend in the 100 Apprenticeship Scheme of £111k and project slippage of £120k. o An overspend of £6.6m against Children & Families budgets. This is mainly due to the impact of delayed savings totalling £4.1m, increased staffing and non-staffing costs within Fieldwork services of £1.5m and £600k respectively, and the full year impact of the 2017/18 overspend of £460k. o An overspend with Commissioning, Inclusion and Learning Services of £307k. This is due to £531k unachieved savings within the tri-partite risk share agreement between the Council, CCG and Care Trust and a £125k underspend within Carer’s Breaks due to contract variation. o A reduction in spend of £324k within Business Strategy, mainly due to a forecast reduction in staffing costs and over-recovery of income within the service. o There are a number of smaller movements within this position. Appendix 1 provides a fuller picture on a service-by-service basis, including commentary as to the movement since Month 6.
The Place Portfolio is forecasting a £1.1m underspend. The key variances include slippage in the delivery of planned budget savings on ‘Place Change Programmes’ and Housing General Fund (£3.5m), offset by both sustainable and one-off reductions in expenditure budgets which will not affect service delivery and staff savings from a voluntary early severance/retirement scheme (£4.5m), resulting in a net £1.0m forecast underspend
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Budget Monitoring (2)Report | 2.2 MB | DownloadRead as text |
PDF |
Revenue Budget and Capital Programme Monitoring 2018/19 Month 9Report | 188 KB | Download |
Follow Co-operative Executive at Sheffield and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Apr 2022 | The Sheffield Tobacco Control Strategy and Future Commissioning Model 2022-2027.View the decision text for item 8. | Decided | Open |
| 20 Apr 2022 | Parks Tennis ProcurementView the decision text for item 9. | Decided | Open |
| 20 Apr 2022 | Procurement of an Adult Social Care Mental Health Recovery Framework for people with eligible mental health needsView the decision text for item 10. | Decided | Open |
| 20 Apr 2022 | Procurement for the Care and Support services in Extra Care SchemesView the decision text for item 11. | Decided | Open |
| 20 Apr 2022 | Procurement of an Enhanced Supported Living FrameworkView the decision text for item 12. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.