Resolved
View the decision text for item 5.
Co-operative Executive decided this item on Thursday 24 March 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
View the decision text for item 5.
SHEFFIELD CITY COUNCIL Removal from Call-in Process ("fast track") Scrutiny Procedure Rule 17
Subject: Gleadless Valley Masterplan Consultation Feedback &
Approval
Decision Maker: Cooperative Executive
Date of Decision: 24th March 2022
Decision to be removed from Call-in process:-
1. Consider carefully the feedback from the community consultation on the draft Masterplan for Gleadless Valley and have regard to it in making decisions on matters addressed in this report.
2. Agrees the Masterplan and Authorises the Director of Housing to make non- material changes to the plan based on the feedback that has been received
3. Authorise the Director of Housing to make arrangements to progress the implementation of Gleadless Valley Masterplan into the delivery of works phase and bring forward individual projects for approval in line with the Councils capital approval process.
4. Authorises the Director of Housing to publish a final Masterplan by end June 2022.
5. Delegates to the Director of Housing in consultation with the Corporate Executive Member for Neighbourhoods and Community Safety and pursuant to the Leaders Scheme of Delegation to:
a. Agree and implement the arrangements for ceasing the letting of empty properties and when to begin the clearance process in accordance with the phasing programme to be determined.
b. Agree and implement the arrangements for awarding priority for rehousing in line with the Allocations Policy for those residents affected by demolition or remodelling in line with the phasing programme to be agreed.
c. Agree and implement a Local Lettings Policy that will give preference to residents with a demolition priority to enable them to stay within the area subject to eligibility.
6. Authorises the Head of Regeneration and Property to verify and validate statutory compensation claims of qualifying tenants and residents displaced under these phased schemes, and thereafter pay qualifying persons (1)
Page 1 of 3 Page 3 discretionary home-loss payments, and (2) discretionary payments to cover any removal expenses.
7. Approves that the Head of Regeneration and Property Services be authorised to (1) negotiate and agree terms for the acquisition of dwellings listed which are not owned by the City Council and, (2) to instruct the Director of Legal and Governance to complete the necessary legal documentation in respect of the acquisition of such properties
8. Approves that the Head of Regeneration and Property Services Property be authorised to make statutory home-loss payments to qualifying owner occupiers and tenants of private landlords and to make other necessary and lawful payments of compensation to owners of property being purchased.
9. Approves that the Regeneration and Property Services be authorised to (1) negotiate the surrender of any commercial leases including electrical substations, telecommunications and other service equipment as required (2) to instruct the Director of Legal and Governance to complete the necessary legal documentation.
Reasons for Urgency
The Cooperative Executive agreed on 19th January 2022 to a 6 week period of consultation on the draft Gleadless Valley Masterplan starting on 24th January 2022 and ending on 4th March 2022. It also gave a commitment to the Gleadless Valley residents that the feedback from the community would be considered by Cooperative Executive in March 2022. A Special Cooperative Executive Meeting has been set up for 24th March 2022 to enable this commitment to be met.
In the 2 weeks since the consultation closed Officers have been collating and analysing the feedback and it is only now in a format suitable and sufficient for the Cooperative Executive to be able to fully consider the information it needs to enable it to make a decision on the Gleadless Valley Masterplan.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Fast Track Form (Updated June 2021) G Valley MP signedReport | 130 KB | DownloadRead as text |
PDF |
Feedback from the Gleadless Valley Masterplan community consultation, proposed changes to the Masterplan and outlines the key delegations needed for implementing the Masterplan.Report | 754 KB | Download |
PDF |
Gleadless Valley Appendix 2Appendix | 950 KB | Download |
PDF |
Reg 11 Notice Template: taking key decisions in cases of special urgency G Valley MP PublicDecisions | 113 KB | Download |
Follow Co-operative Executive at Sheffield and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Apr 2022 | The Sheffield Tobacco Control Strategy and Future Commissioning Model 2022-2027.View the decision text for item 8. | Decided | Open |
| 20 Apr 2022 | Parks Tennis ProcurementView the decision text for item 9. | Decided | Open |
| 20 Apr 2022 | Procurement of an Adult Social Care Mental Health Recovery Framework for people with eligible mental health needsView the decision text for item 10. | Decided | Open |
| 20 Apr 2022 | Procurement for the Care and Support services in Extra Care SchemesView the decision text for item 11. | Decided | Open |
| 20 Apr 2022 | Procurement of an Enhanced Supported Living FrameworkView the decision text for item 12. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.