The report will detail the energy tariff options available to the Council from its new electricity supplier (EDF). The report will set out the Renewable Energy Guarantee of Origin (REGO) arrangement the Council has under the contract with its current supplier (which will expire in March 2023) and recommend that the Council purchases the standard product under the contract with its new supplier (which commences in April 2023). The standard product does not involve the purchase of REGOs. The report will set out the Council’s intention that monies previously allocated for the purchase of REGOs is deployed on building a comprehensive communications and engagement package that will allow communities and organisations to learn about and access specific renewable energy funding and investment opportunities, subject to separate Council approval. This decision will allow the Council to realise a significant cost avoidance for the financial year 2023/24 and years moving forward and by allocating the monies to local renewable energy projects it will have a positive effect on the Council’s route to net zero by 2030.
Policy Committee Report Page 135 April 2022 Recommendations:
It is recommended that the Strategy and Resources Committee:
1) approves the Council purchasing the standard option for electricity generation with EDF, as set out in this report; 2) notes the Council’s intention to internally reallocate monies previously allocated for the purchase of REGOs to building a comprehensive communications and engagement package that will allow communities and organisations to learn about and access specific renewable energy funding and investment opportunities.
None
Lead Officer to complete: -
1 I have consulted the relevant departments in Finance: James Lyon respect of any relevant implications indicated on the Statutory and Council Policy Checklist, and comments have been incorporated / Legal: Richard Marik additional forms completed / EIA completed, where required. Equalities & Consultation: Louise Nunn
Climate: Kathryn Warrington
Legal, financial/commercial and equalities implications must be included within the report and the name of the officer consulted must be included above.
2 SLB member who approved submission: Ajman Ali
3 Relevant Policy Committee Strategy and Resources
4 I confirm that all necessary approval has been obtained in respect of the implications indicated on the Statutory and Council Policy Checklist and that the report has been approved for submission to the Decision Maker by the SLB member indicated at 2. In addition, any additional forms have been completed and signed off as required at 1. Lead Officer Name: Job Title: Jason Peck Contract Manager
Date 02/03/2023
Page 136 Page 2 of 14 1. PROPOSAL
1.1This report seeks approval for the Council to purchase the standard option for electricity generation under the service contract with EDF (commencement date 1 April 2023) which carries no premium payment. This option is preferred to other renewable options which carry a premium.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Purchasing Electricity from Renewable SourcesReport | 315 KB | DownloadRead as text |
Follow Strategy and Resources Policy Committee at Sheffield and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Sep 2026 | 2026/27 Quarter 1 Budget Monitoring ReportView the decision text for item 20. | Decided | Open |
| 2 Sep 2026 | Medium Term Financial Strategy (MTFS) 2027/28 to 2030/31View the decision text for item 21. | Decided | Open |
| 2 Sep 2026 | Future Sheffield Update ReportView the decision text for item 22. | Decided | Open |
| 2 Sep 2026 | Annual Customer Voice Report - 2025/26View the decision text for item 23. | Decided | Open |
| 2 Sep 2026 | Interpretation and Translation Procurement ProposalView the decision text for item 24. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.