Resolved
View the decision text for item 12.
Strategy and Resources Policy Committee decided this item on Wednesday 17 April 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
View the decision text for item 12.
The purpose of this report is to seek approval to commission a new SDWAN Network Service from an external provider as outlined in this report.
This report explains the current WAN service and it its importance to the Council and schools.
This report goes on to describe the SDWAN network service and its potential benefits to the Council.
Policy Committee Report Page 293 May 2023 Recommendations:
It is recommended that the Strategy & Resources Committee approves the commissioning of a new SDWAN Network Service from an external Provider for a period of 5 years with an estimated value of £3.6M, as set out in this report.
Background Papers: (Insert details of any background papers used in the compilation of the report.)
Lead Officer to complete:-
1 I have consulted the relevant departments Finance: Matthew Ardern, Senior Finance in respect of any relevant implications Manager indicated on the Statutory and Council Commercial: Lucy Matthews, Procurement and Policy Checklist, and comments have Supply Chain Manager been incorporated / additional forms Legal: Richard Marik, Commercial Lawyer completed / EIA completed.
Equalities & Consultation: Richard Bartlett, Senior Equality and Engagement Officer Climate: Devolved approval authority to Head of Service, Jon Rayner, Head of Service ICT Delivery
Legal, financial/commercial and equalities implications must be included within the report and the name of the officer consulted must be included above.
2 SLB member who approved Claire Taylor, Chief Operating Officer submission:
3 Committee Chair consulted: Councillor Tom Hunt
4 I confirm that all necessary approval has been obtained in respect of the implications indicated on the Statutory and Council Policy Checklist and that the report has been approved for submission to the Committee by the SLB member indicated at 2. In addition, any additional forms have been completed and signed off as required at 1. Lead Officer Name: Job Title: Jon Rayner Head of ICT Delivery
Date: 17/04/2024
Page 294 Page 2 of 9 1. PROPOSAL
1.1Virgin Media Business (VMB) Business has been partnering with Sheffield City Council for the provision of high-speed fibre-based internet & wide area network (WAN) connectivity since 2014. The Council’s existing WAN contract for corporate & school connectivity ends 31st May 2024 which coincides very well with the suitability and availability of next generation Software Defined Wide Area Network (SD-WAN) network technology as the replacement.
1.2The current Service provision consists of:
• 255 x IPVPN circuits of which • A managed service covering the delivery, support and maintenance of the above. • A managed Local Area Network (LAN) Service which supports and maintains the network localised within each location.
255 x IPVPN circuits
1.3103 of the 255 IPVPN circuits deliver schools with Simple Internet.
1.4152 of the 255 IPVPN circuits deliver Corporate sites with IPVPN to the core. This solution entails all locations connecting to a central location at Town Hall before breaking out to the Internet.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Network Services Contract Award: Software Defined Wide Area Network (SD WAN) ServiceReport | 195 KB | DownloadRead as text |
Follow Strategy and Resources Policy Committee at Sheffield and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Sep 2026 | 2026/27 Quarter 1 Budget Monitoring ReportView the decision text for item 20. | Decided | Open |
| 2 Sep 2026 | Medium Term Financial Strategy (MTFS) 2027/28 to 2030/31View the decision text for item 21. | Decided | Open |
| 2 Sep 2026 | Future Sheffield Update ReportView the decision text for item 22. | Decided | Open |
| 2 Sep 2026 | Annual Customer Voice Report - 2025/26View the decision text for item 23. | Decided | Open |
| 2 Sep 2026 | Interpretation and Translation Procurement ProposalView the decision text for item 24. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.