Agenda Item 11
Policy Committee Decision Report
Title of Report: Commissioning of professional services to support delivery of the council’s capital programme Date of Decision: 17th February 2025 Report To: Finance and Performance Policy Committee Report Of: Sean McClean – Director of Regeneration and Development Report Author: Adam Midgley – Head of Capital Delivery Service
Executive Summary: Sheffield City Council has an ongoing capital programme of approximately ~£80m per annum. The Capital Delivery Service (CDS) includes a range of professional services for the delivery of capital projects. Due to the fluctuating nature of the capital programme, CDS operates a “core and flex” delivery model. There is a “core” in-house team supplemented by “flexible” external professional services. Current contracts are due to expire so CDS is seeking to commission contract(s) for professional services to support delivery of the Council’s capital programme. The re-procurement of these professional services contract(s) will provide additional flexible resource to support CDS and is considered to be the most cost- effective means of providing a flexible resource base.
Page 77 Council Plan outcomes: A place where all children belong and all young people can build a successful future Great neighbourhoods that people are happy to call home People live in caring, engaged communities that value diversity and support wellbeing A creative and prosperous city full of culture, learning, and innovation A city on the move – growing, connected and sustainable
Policy Committee remit: This report is to be considered by the Finance and Performance Policy Committee as its remit includes agreeing the commission or purchasing decision and the budget on any given requirement for contracts over £250,000 and with a service delivery period of over 4 years for matters reserved to them, in this case matters relating to the Capital Programme. Does the report contain confidential or exempt information? No
Page 78 Recommendations: The Finance and Performance Policy Committee is recommended to: 1. Approve the commissioning of contracts for the provision of professional services to support the Capital Delivery Service’s delivery of the Capital Programme, for a period of a minimum of 5 years (with option(s) to extend up to 10 years) with a maximum estimated value of up to £30m, to commence on the expiration of the current arrangement in 2025.
Financial Implications: Yes Approved by: Phil Moorcroft
Legal Implications: Yes Approved by: Gemma Beecroft
Equality and Engagement Implications: No
Climate Change Implications: No
Background Papers: None
Appendices: None
Page 79 1. Background to the issue
1.1Sheffield City Council has an ongoing capital programme of approximately ~£80m per annum. The Capital Delivery Service (CDS) is the Council’s in-house multi-disciplinary built environment project and programme delivery service, sitting in the City Futures portfolio area. This service is available to all Council directorates to ensure that capital projects are delivered to minimise the Council’s exposure to risk, and maximise the conditions for success.
1.2CDS includes a range of professional services including Programme and Project Management, Contract Administration, Cost Management and Procurement, and Design and Technical Services for the delivery of capital projects.
1.3The service is a fully traded service and has a cost recovery target of circa £6m per annum. This is realised through the professional fees charged to the capital projects to recover staff costs and associated overheads.
1.4Due to the fluctuating nature of the capital programme, CDS operates a “core and flex” delivery model. The “core” in-house team is resourced to deliver a sustainable workload based on the known forward programme. This is supplemented by “flexible” external professional services to deliver peaks in workload. Specialist services which are not cost-effective to maintain in-house are also resourced externally.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Commissioning of Professional Services to Support Delivery of the Council’s Capital ProgrammeReport | 186 KB | DownloadRead as text |
Follow Finance and Performance Policy Committee at Sheffield and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Sep 2026 | Capital Approvals 26-27 Month 4View the decision text for item 8. | Decided | Open |
| 21 Sep 2026 | Council Plan Outcomes Framework quarterly reportView the decision text for item 9. | Decided | Open |
| 21 Sep 2026 | Affordable Housing Land Disposals – Phase 1View the decision text for item 10. | Decided | Open |
| 21 Sep 2026 | Budget Monitoring Q1 2026-27View the decision text for item 11. | Decided | Open |
| 20 Jul 2026 | Capital Approvals 26-27 Month 2View the decision text for item 23. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.