Finance and Performance Policy Committee, Wednesday 25 February 2026 at 2.00pm

Heart of the City 2 Update

Decided Finance 2 papers

AI summarySheffield's Finance and Performance Policy Committee received a report on Heart of the City 2 asking it to approve procurement of asset and property management services and delegate authority to officers to structure the estate.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedReport asked for approval and delegation
MoneyNot stated
What happens nextNot stated
Who it affectsHeart of the City 2 estateCouncil asset and property management

What was decided

The report asked the Committee to approve procurement of asset and property management services and delegate authority to officers to structure the Heart of the City 2 estate in a way that meets the Council's objectives. Report P6

Why

The Council needs efficient asset and property management to maximise NOI and run the estate effectively, and to structure the estate to maximise financial and investment returns to the Council. Report P6

Implications

  • Legal: The council has wide powers to establish and operate through different delivery models, with regard to effective control, financing, land ownership and operating arrangements, informed by the business plan and detailed legal and financial advice. Report 8.1
  • Climate: No direct climate implications arise from this report, though there may be implications if the Council chooses to retain the estate longer term. Report P3
  • Other: Other implications section marked as N/A in the report. Report P5

Who and where

  • The Heart of the City 2 estate and the Council as recipient of financial returns Report P6
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item104

Resolved

View the decision text for item 104.
Word for word from the decision Sheffield published for this meeting. Source: democracy.sheffield.gov.uk

Follow this further

Built from Sheffield's papers

What the report saysPro

Report to Finance and Performance Policy Committee

Agenda Item 13

Policy Committee Decision Report

Title of Report: Heart of the City 2 Update Date of Decision: 25th February 2026 Report To: Finance & Performance Committee Report Of: Kate Martin – Executive Director, City Futures Philip Gregory – Director of Finance & Commercial Services (S151 Officer)

Report Author: Sean McClean – Director of Regeneration & Development Kerry Darlow – Assistant Director Finance Business Partnering

Executive Summary: This report provides committee members with an update on the financial position of the Heart of the City II project, including the impact of current lettings. It seeks approval to reallocate the surplus capital budget to support development and fit out of unlet units. It also requests delegated authority for Officers to investigate and adopt a policy of retaining the units in a Special Purpose Vehicle (SPV), to maximise commercial opportunity and potentially provide an attractive option for disposal at a later date. Finally, it seeks approval to procure partners to provide Asset and Property Management services for the estate.

Page 243 Council Plan outcomes: A creative and prosperous city full of culture, learning, and innovation A city on the move – growing, connected and sustainable Great neighbourhoods that people are happy to call home.

Policy Committee remit: Include the following: “This report is to be considered by the Finance and Performance Policy Committee as its remit includes: “regular monitoring of data including performance and financial information and for monitoring the performance of services;”

Does the report contain confidential or exempt information? Yes Appendix 2 contains exempt information under Paragraph 3 of Schedule 12A to the Local Government Act 1972, as it includes commercially sensitive information relating to the financial or business affairs of the Council and/or third parties.”

Report Quick Links: 1. Background 2. Proposal 3. Contribute to the Council Plan? 4. Community or partner engagement? 5. Alternative options? 6. Equality, diversity and inclusion considerations? 7. Financial and Commercial Implications 8. Legal Implications 9. Climate and Environmental Implications 10. Other implications 11. Reasons for decision

Page 244 Recommendations:

(a) Note the scale and impact of the Heart of the City II Estate; the successful delivery of the capital works to budget and the successes of letting activity made thus far. (b) Approve the reallocation of the remaining approved capital budgets as per Appendix 1. (c) Note the updated Business Plan and the impact on the 26/27 Revenue Budget. (d) Approve the commission of an Asset Management services provider for the Heart of the City II estate, via direct award. (e) Approve the commission of Property Management services via an open tendering process. (f) Note that officers will explore the creation of the most appropriate vehicle to maximise rental income in the scheme and provide an attractive proposition for investment into this vehicle as part of a potential long-term disposal plan, and approve the commission of financial, legal, and technical advice necessary for that work A further report will be provided to the Committee at a later date.

Financial Implications: Approved by: Kerry Darlow

Legal Implications: Yes Approved by: Legal Officer name Robert Parkin

Equality and Engagement Implications: Approved by: Ed Sexton Previous Full Equalities Impact Assessment completed with EIA number: 926

Climate Change Implications: N/A CIAs were not required when the project was initiated so one has not been completed. This report provides an update on the completed project.

Background Papers: None

Appendices: Appendix 1 - Capital Budget update Appendix 2 (closed) - Heart of the City Model including Radisson Business Plan

Page 245 1. Background to the issue

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Heart of the City 2 UpdateReport 2.3 MB DownloadRead as text
PDF
HoC2 Update report: Appendix 1 Capital BudgetAppendix 60 KB Download

At this meeting

Whole meeting

Who was there

11 of 12 attended
ZN
Councillor Zahira NazChair, apologies, sent representative
ML
Councillor Mike LeveryDeputy Chair, present
MP
Councillor Martin PhippsGroup Spokesperson, apologies, sent representative
GC
Councillor Glynis ChapmanCommittee Member, present
ED
Councillor Elle DoddCommittee Member, present
DJ
Councillor Douglas JohnsonCommittee Member, present
AK
Councillor Abdul KhayumCommittee Member, present
GS
Councillor Gareth SlaterCommittee Member, present
MS
Councillor Martin SmithCommittee Member, present
ME
Councillor Marieanne ElliotSubstitute Member, present as substitute
ML
Councillor Mary LeaSubstitute Member, present as substitute
RM
Rachel MarshallSecretary, expected

On this subject at Sheffield

Search all
  1. Heart of the City 2 UpdateThis decision
  2. Update on Delivery of Heart of the City 2 Development*Decided
  3. Delivery of Heart of the City Phase IIDecided

More from Sheffield Finance and Performance Policy Committee

All decisions
MeetingDecisionOutcome
21 Sep 2026 Capital Approvals 26-27 Month 4View the decision text for item 8. Decided Open
21 Sep 2026 Council Plan Outcomes Framework quarterly reportView the decision text for item 9. Decided Open
21 Sep 2026 Affordable Housing Land Disposals – Phase 1View the decision text for item 10. Decided Open
21 Sep 2026 Budget Monitoring Q1 2026-27View the decision text for item 11. Decided Open
20 Jul 2026 Capital Approvals 26-27 Month 2View the decision text for item 23. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies