Sheffield City Council
Finance and Performance Policy Committee, Monday 20 July 2026 at 2.00pm

Concord Sports Centre New Build

Decided Finance 3 papers

AI summarySheffield City Council Finance and Performance Committee is asked to approve £67.9m capital budget for Concord Sports Centre new build, with construction due to start summer 2027.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedProceed to detailed design and delivery planning
Money£67,887,941 totalMostly from prudential borrowing of £65.95m
What happens nextDetailed design and procurementPre construction services agreement with Willmott Dixon
Who it affectsSheffield residents and usersNew facility built next to existing centre

What was decided

The committee is asked to note the current position and approve the proposed additions and variations to the Capital Programme listed in Appendix 1. Report P9, P10

The Outline Business Case requests approval of £67,887,941 for the Concord Sports Centre Leisure Investment Programme, made up of £65.95m prudential borrowing, £1.8906m revenue contribution to capital and £44.6k historic NCSEM grant. Report P44, P45

Why

The existing Concord Sports Centre is ageing, deteriorating and no longer fit for purpose, leaving the council with ongoing maintenance pressures, a poorer quality facility and reduced ability to support local health and wellbeing outcomes. Report P15, 5.1, P35

The investment supports council plan outcomes on neighbourhoods and caring communities, contributes to tackling health inequalities in an area with poorer health outcomes and lower physical activity, and aligns with the emerging Built Sport and Leisure Strategy. Report P22, P24

What happens next

The project will move into detailed design and delivery planning, entering a pre construction services agreement with Willmott Dixon through the Procurement Hub Framework.

Construction is due to start in summer 2027 with the facility anticipated to be complete in October 2029. Reserve payback is now forecast by 2037/38, later than the original 2034/35 plan. Report P16

The money

  • £67,887,941 Total Outline Business Case budget for the Concord Sports Centre Leisure Investment Programme Report P44, P45, 7.3, P52, P59
  • £65.95m Prudential borrowing, the largest funding source Report P45, P49
  • £1.8906m Revenue Contribution to Capital for 2025/26 and 2026/27 costs Report P44, P50
  • £44.6k Historic National Centre for Sport and Exercise Medicine grant already held Report P44, P51
  • £140m Total affordable borrowing required across the four facilities in the Leisure Investment Programme
  • £22.5m Approximate reserves required by the programme, up from the original £20m forecast approved in November 2021
  • £6.2m per annum Annual revenue charge covering the cost of borrowing at its highest level
  • £12m Approximate revenue shortfall from maintaining the three remaining facilities in their current form over the remainder of the 15 year contract

Options considered

  • Chosen: Demolition of the existing facility and new build adjacent to it, then demolition of the current building and completion of external pitches and landscaping. Allows the existing centre to remain operational during construction, provides a larger site area, supports a building designed to BREEAM Excellent standards, and offers the best chance to deliver community, health, accessibility and sustainability benefits. Report 5.4, P41
  • Rejected: Do nothing. Existing facility is deteriorating and no longer fit for purpose, would leave ongoing maintenance pressures, poorer quality facility, reduced ability to support local health outcomes and increased reputational risk. Report 5.1, P35
  • Rejected: Refurbishment of the existing leisure centre. Building envelope in poor condition; refurbishment would not provide the same long term benefit, would retain layout and condition constraints, and would not deliver the same accessibility, sustainability or site integration benefits. Report 5.2, P37
  • Rejected: Demolition of the existing facility and new build on the current building footprint. Would require the existing centre to close for 2 years or more, causing loss of access for a community in an area of high health inequalities, and would limit the proposed facility mix and wider benefits. Report 5.3, P39

Implications

  • Equalities: A full Equality Impact Assessment has been completed (EIA 2582). The proposal is expected to have a positive impact by improving access for groups facing barriers, including disabled people, older people, families, women and girls, lower socio economic groups and ethnically diverse communities. Report P12, 6.1, P42
  • Climate: A full Climate Impact Assessment has been completed (CIA 438). The new facility will be designed to BREEAM Excellent standards, with improved energy efficiency, active travel provision and biodiversity opportunities, supporting the council's net zero ambitions. Report P12, 9.1, P64
  • Legal: The council has legal powers under the Local Government (Miscellaneous Provisions) Act 1976, the Local Government Act 1972 and the Localism Act 2011. Approval does not authorise construction contracts; any procurement must comply with PCR 2015 or PA 23, subsidy control and planning, building, health and safety, environmental and equality legislation. Report 8.1, P63
  • Financial: Funding is largely through prudential borrowing, with reserves used in earlier years. The wider four facility programme requires £140m of affordable borrowing and approximately £22.5m of reserves, with the new facility to be operated by Everyone Active under the 15 year contract from January 2025. Report P61

Who and where

  • Local residents in the Concord Park area, identified as having poorer health outcomes and lower levels of physical activity Report P22, P26
  • Existing Concord Sports Centre users, who will continue to access the centre while the new facility is built alongside it Report 5.4, P41
  • Disabled people, people with long term health conditions, older people, children and young people, families, women and girls, lower socio economic groups and ethnically diverse communities Report P42
  • Everyone Active as the operator of the new centre under the 15 year leisure operating contract that began in January 2025

Timeline

  • March 2026: Capital approval given for feasibility works on the Concord Sports Centre new build Report P16
  • July 2026: Sheffield's new Built Sport and Leisure Strategy due for adoption at Communities, Parks and Leisure Committee Report P24
  • 20th July 2026: Decision scheduled at Finance and Performance Policy Committee on the Outline Business Case budget of £67,887,941 Report P3, P9, P10
  • Summer 2027: Construction of the new Concord Sports Centre due to start on site (July 2027) Report P16
  • October 2029: Completion of the new facility anticipated
  • 2037/38: Forecast reserve payback year for the Leisure Investment Programme, later than the original 2034/35 plan

Plain English for the jargon

  • BREEAM Excellent: A high level sustainability rating for buildings set by BRE (Building Research Establishment).
  • EIA 2582: The reference number for the full Equality Impact Assessment completed for the Concord Sports Centre Leisure Investment Programme.
  • CIA 438: The reference number for the full Climate Impact Assessment completed for the Concord Sports Centre proposal.
  • NCSEM: National Centre for Sport and Exercise Medicine; healthcare co located with leisure provision.
  • Outline Business Case: A stage of the council's capital approval process setting out scope, costs and funding for a scheme before detailed design.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item25

Resolved

View the decision text for item 25.
Word for word from the decision Sheffield published for this meeting. Source: democracy.sheffield.gov.uk

Follow this further

Built from Sheffield's papers

What the report saysPro

Report to Finance and Performance Policy Committee

Agenda Item 10

Policy Committee Decision Report

Title of Report: Concord Sports Centre New Build Date of Decision: 20th July 2026 Report To: Finance and Performance Committee Report Of: Ajman Ali, Executive Director of Neighbourhoods Report Author: Tammy Barrass, Head of Sport, Leisure & Major Events / Kate Clark, Service Manager, Physical Activity Sport & Health

Executive Summary: The report provides a detailed overview of the Concord Sports Centre new build proposal to support the proposed additions and variations to the Capital Programme.

Page 117 Council Plan outcomes: [List the relevant outcomes as set out in section 3] A place where all children belong and all young people can build a successful future Great neighbourhoods that people are happy to call home People live in caring, engaged communities that value diversity and support wellbeing A creative and prosperous city full of culture, learning, and innovation A city on the move – growing, connected and sustainable

Policy Committee remit: This report is to be considered by the Finance and Performance Policy Committee as its remit includes: Subject to decisions being not contrary to the Capital Strategy, agreement of reports on the implementation of the capital programme provided under the Capital Programme Financial Reporting and Control Procedures, including:- (a) approval of all new schemes; except expenditure relating to feasibility works up to the value of £100,000 in accordance with the Financial Procedure Rules;

(b) approval of a variation to an existing scheme which increases the value of the scheme by more than £100,000; and (c) acceptance and issue of capital grant funding (and where appropriate associated revenue grant funding) to enable capital scheme implementation. Does the report contain confidential or exempt information? No

Report Quick Links: 1. Background 2. Proposal 3. Contribute to the Council Plan? 4. Community or partner engagement? 5. Alternative options? 6. Equality, diversity and inclusion considerations? 7. Financial and Commercial Implications 8. Legal Implications 9. Climate and Environmental Implications 10. Other implications 11. Reasons for decision

Page 118 Recommendations:

(a) Note the current position and approve the proposed additions and variations to the Capital Programme listed in Appendix 1.

Financial Implications: Yes: Approved by: Damian Watkinson (capital) Louise Hibbert (Revenue).

Legal Implications: Yes: Approved by: Legal Officer Leonie Wallace and Renaldo De Costa. Equality and Engagement Implications: Yes: Approved by: Louise Nunn. Full Equalities Impact Assessment completed with EIA number: 2582 Climate Change Implications: Yes: Approved by Sustainability Officer: Matthew Hutton. Full Climate Impact Assessment completed with CIA number: 438

Background Papers: Decision - Leisure and Entertainment Facility and Services Review | Sheffield City Council Decision - Contract Award for a New Operator for Sheffield City Council's Sport and Leisure Facilities. | Sheffield City Council Decision - Capital Approvals 25-26 Month 6 | Sheffield City Council, Capital Approvals Appendix 1 – Springs Leisure Centre Outline Business Case budget approval Agenda item - Capital Approvals 25-26 Month 10 | Sheffield City Council, Capital Approvals Appendix 1 Concord Sports Centre Initial Business Case budget approval

Appendices: Capital Approvals Appendix 1 M02 Concord 2627.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Approvals Appendix 1 M02 Concord 2627Appendix 121 KB Download
PDF
Concord Sports Centre New BuildReport 701 KB DownloadRead as text
PDF
EIA 2582: Sport and Leisure Rebuild and RefurbishmentsReport 169 KB Download

At this meeting

Whole meeting

Who was there

8 of 9 attended
ED
Councillor Elle DoddChair, present
IU
Councillor Ibby UllahDeputy Chair, apologies, sent representative
AA
Councillor Angela ArgenzioGroup Spokesperson, present
ML
Councillor Mike LeveryGroup Spokesperson, present
JB
Councillor Jack ByromCommittee Member, present
GC
Councillor Glynis ChapmanCommittee Member, present
MS
Councillor Maia Salman-LordCommittee Member, present
RB
Councillor Rob BannisterSubstitute Member, present as substitute
RM
Rachel MarshallSecretary, expected

More from Sheffield Finance and Performance Policy Committee

All decisions
MeetingDecisionOutcome
21 Sep 2026 Capital Approvals 26-27 Month 4View the decision text for item 8. Decided Open
21 Sep 2026 Council Plan Outcomes Framework quarterly reportView the decision text for item 9. Decided Open
21 Sep 2026 Affordable Housing Land Disposals – Phase 1View the decision text for item 10. Decided Open
21 Sep 2026 Budget Monitoring Q1 2026-27View the decision text for item 11. Decided Open