Review of Highway Asset Management Plan including Pothole Repairs and Forward Repair Plan

Decided Committee 2 papers

AI summarySheffield committee receives performance update on Streets Ahead road maintenance and street cleansing contract, with data on pothole repairs, cyclical cleansing trial results, and fly tipping increases.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedThe committee received a presentation on Streets Ahead environmental services performance; no formal decision was recorded in the papers provided
MoneyNot stated
What happens nextCyclical street cleansing trial continues until December 2026. The 12-month trial began in December 2025 with a review underway
Who it affectsSheffield road users and residentsThe condition of roads and street cleansing standards affect all residents and highway users across the city

What was decided

The committee received the presentation as an information item; no decision wording or resolution was recorded in the papers supplied Report P3

Why

This was a performance update following unprecedented rainfall in January and February 2026 which caused significant damage to road surfaces across the Sheffield network Report P4

The report provided data on the cyclical street cleansing trial which began in December 2025 and will run for 12 months, with a review underway Report P21

What happens next

The lifecycle road resurfacing programme will continue until March 2027 Report P7

The Area Highway Representatives programme continues with councillor engagement and service improvements planned Report P68, P71

Implications

  • Other: Fly tipping has increased by 38% year on year, with July 2025 recording 1,481 enquiries rising to 2,037 in July 2026 Report P42
  • Climate: The change to preventative road maintenance is estimated to save approximately 20,000 tonnes of CO2 over the remaining contract term Report P10
  • Other: Sheffield's roads remain in better condition than the vast majority of other UK authorities according to Department for Transport Road Condition Indices Report P5
  • Other: The cyclical street cleansing trial has achieved 96.65% on litter and detritus acceptable combined score compared to 94.45% national average Report P27

Who and where

  • Road users across Sheffield Report P4, P5
  • Residents receiving street cleansing services Report P20, P21
  • Councillors receiving Area Highway Representative support Report P59, P61

Timeline

  • December 2025: Cyclical street cleansing trial began with agreement to run for 12 months Report P21
  • January and February 2026: Unprecedented rainfall caused significant damage to road surfaces across the Sheffield network Report P4
  • End of March 2026: Category 1 defects returned to normal levels following spike from weather damage Report P6
  • March 2026: Lifecycle road resurfacing programme commenced Report P7
  • September 2026: Area Highway Representatives newsletter launches Report P61
  • 18th September 2026: Committee received the performance update presentation Report P1
  • Until March 2027: Lifecycle road resurfacing programme will continue Report P7

Plain English for the jargon

  • Category 1 defects: Urgent potholes requiring temporary repair within 24 hours and permanent repair within 28 days
  • Category 2 defects: Non-urgent road defects planned for repair through the lifecycle programme
  • PFI: Private Finance Initiative, the contractual arrangement under which Amey delivers the Streets Ahead contract for Sheffield's roads
  • NI195: National Indicator 195, a measure of street cleansing standards
  • AHR: Area Highway Representative, a named contact for councillors on local highway matters
  • Glyphosate: A herbicide used in weed management programmes
  • LIP: Lifecycle Investment Programme for preventative road maintenance
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

View the decision text for item 6.
Word for word from the decision Sheffield published for this meeting. Source: democracy.sheffield.gov.uk

Follow this further

Built from Sheffield's papers

What the report saysPro

Report to Environmental Services and Regulation Policy Committee

Sheffield Streets Ahead Environmental Services and Regulation Policy Committee Meeting

18th September 2026 Page 1

Agenda Item 6 Introduction

• Weather conditions in January and February saw unprecedented levels of rainfall which caused significant damage to road surfaces across the UK, including the Sheffield network. • Amey are committed to providing the people of Sheffield with the best service possible and have taken the situation very seriously.

• Sheffield's roads remain in far better condition than the vast majority of other authorities in the UK as reported by the Department of Transport in its annual Road Condition Indices. Page 2

• Amey immediately employed additional resources to tackle spikes in potholes. This saw priority been given to urgent category 1 defects dealt with first and made safe within 24 hours with a temporary repair, followed by a permanent repair within 28 days. These defects were at a normal level by the end of March.

• This led to a spike in non-urgent Category 2 defects of circa 4,000 around the end of March. Our resources subsequently concentrated on these defects which are now approx. 1,280 and reducing. • In parallel with the reactive maintenance above, a more extensive lifecycle road resurfacing programme is underway tackling further category 2 defects and wider road deterioration, which is normally expected. This commenced in March and will continue until March 2027. This treats wider areas of planned maintenance in accordance with the contract.

• Additionally, Amey have implemented a significant programme of preventative maintenance in 2024 and 2025 (over and above what is required by the contract) which has proved highly effective in preventing more highway damage. The programme is now concluding for 2026. Sheffield DfT Carriageway Condition Scoring 2017 – 2025 Primary, Secondary, Link & Local Page 3 Percentage of Roads where maintenance should be considered 2007 - 2025 Local A Roads Page 4 Percentage of Roads where maintenance should be considered 2007 - 2025 B & C Classified Roads Page 5 Lifecycle Investment Programme (LIP) – Preventative Maintenance Treatments

• Amey are working to protect and preserve the significant investment made in the City’s roads over the last 14 years, since the start of the PFI. • Additional preventative maintenance techniques will preserve the integrity and extend the life of the road. These are in addition to the traditional road resurfacing programme each year. • Shown opposite are examples of some of the high-quality preventative maintenance schemes undertaken since Page 6

treatments began in 2024. • The additional quantity delivered to date is approx. 1M m2 . This is over and above contract compliance where traditional surfacing of circa 250,000m2 is delivered each year. • The change to preventative maintenance is estimated to save c20,000t of CO2 over the remaining contract term. • These treated roads are far more resistant to Potholes forming. • This is a two-stage process, needing traffic action to ‘bed’ in the stones after the initial application, prior to the second application which seals the surface with further bitumen binders.

6 Pothole Position (CAT1 defects) – Historical and Current Trends

Planning for CAT1 Enquiry Inlaid Repair CAT1 Enquiries Raised: Raised Temp Repair Permanent Reinstatement completed

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Committee Presentation 18th Sept 2026 V2.0 1Report 3.4 MB DownloadRead as text
PDF
Review of Highway Asset Management Plan including Pothole Repairs and Forward Repair PlanReport 224 KB Download

At this meeting

Whole meeting
4Public Petitions, Questions and StatementsOn the agenda 5Members' QuestionsOn the agenda
6Review of Highway Asset Management Plan including Pothole Repairs and Forward Repair PlanThis decision

Who was there

7 of 7 attended
MR
Councillor Mark RuslingChair, present
ML
Councillor Mary LeaDeputy Chair, present
CG
Councillor Christine Gilligan KuboGroup Spokesperson, present
TH
Councillor Tim HugganGroup Spokesperson, present
MA
Councillor Mustafa AhmedCommittee Member, present
AH
Councillor Alan HooperCommittee Member, present
SM
Councillor Sean MaloneyCommittee Member, present

More from Sheffield Environmental Services and Regulation Policy Committee

All decisions
MeetingDecisionOutcome
11 Sep 2026 ESR Committee Forward Look 2026/27View the decision text for item 18. Decided Open
11 Sep 2026 2026/27 Q1 Budget MonitoringView the decision text for item 19. Decided Open
11 Sep 2026 Hackney Carriage Fares ReviewView the decision text for item 20. Decided Open
11 Sep 2026 Determination of General Licensing Fees and Charges 2026/27View the decision text for item 21. Decided Open
11 Sep 2026 Markets Strategy Task and Finish GroupView the decision text for item 22. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies