That planning permission be granted as per the Officer’s recommendation, subject to: · A Section 106 Legal Agreement to secure the developer contributions and provisions as outlined in paragraph 6.9 of the report; and · The conditions as set out in Appendix 1 to the report.
Word for word from the decision Shropshire published for this meeting.Source: www.shropshire.gov.uk
Application Number: 13/05124/FUL Parish: Shrewsbury Town Council
Proposal: Mixed residential development of 75 dwellings (including 8 affordable units), formation of vehicular access; provision of open space and associated landscape and infrastructure improvements
Site Address: Land Opposite Ellesmere Drive Ellesmere Road Shrewsbury Shropshire
Contact Tim Rogers on 01743 258773 Land Opposite Ellesmere Drive, Central Planning Committee – 26 June 2014 Ellesmere Road, Shrewsbury
Recommendation:- Grant Permission subject to the conditions set out in Appendix 1 and a s106 agreement to secure the developer contributions and provisions outlined in paragraph 6.9 of this report.
REPORT
This application was deferred at the 29 May 2014 of the Central Planning Committee to enable the applicant to provide information on the reason for the gas monitoring on site together with any information they have with regard to the nature and extent of any contamination on the site. At the meeting and in response to questions and comments of Members, the Area Planning and Building Control Manager drew Members’ attention to paragraph 4.1.6 of the report which indicated that no issues of land contamination had been identified. He further explained that the pond and provision of open space accorded with the Interim Planning Guidance. Shrewsbury Town Council had been consulted and shown a willingness to adopt the public open space and play area and any concerns with regard to the proximity of the pond would have been raised during discussions and that the provision, maintenance and management of the on-site play area would be covered via the S106 Agreement. In response to the matters raised by members the applicant has confirmed the following:
1. Standpipe / Ground Investigations
The Committee queried why there were standpipes located on the site and that this raised suspicions as to the ground conditions and the potential presence of gas. Crest Nicholson can confirm that the temporary standpipes relate to the developer’s own ground investigation works which it will carry out as a matter of course for any potential development site. In December 2011 Crest Nicholson commissioned a geotechnical desk study and ground investigation works at the site. The purpose of these works was to properly assess the land conditions and provide an adequate level of detail to regulators as part of the development proposals. The desk study which included environmental searches concluded the land to be of agriculture use, dating back to at least 1884 and remaining the same to the present day. Investigation works included the installation of standpipes to monitor groundwater and gases, as well as trial pitting to assess ground conditions and the presence of contamination.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.