a) That the budget variations of £17,700 to the 2013/14 capital programme, detailed in Appendix 1/Table 1 and the re-profiled 2013/14 capital budget of £47.4m be approved. b) That the re-profiled capital budgets of £71.4m for 2014/15, including slippage of £6.6m from 2013/14, £13.7m for 2015/16 and £5.3m for 2016/17 as detailed in Appendix 1/Table 4 be approved. c) That the outturn expenditure set out in appendix 1 of £40.7m, representing 85.9% of the revised capital budget for 2013/14 be accepted. d) That the Highways & Transport programme of schemes for delivery in 2014/15 be approved and that authority be delegated to the Area Commissioner South in consultation with the Portfolio Holder to approve any changes to the implementation plan of schemes for delivery in 2014/15, within the parameters of the outline capital programme. e) That the setting aside of capital receipt of £1.35m to replace the self-financed prudential borrowing previously applied to finance the Solar PV schemes be approved. This will generate an ongoing revenue saving from 2014/15. f) That retaining a balance of capital receipts set aside of £13.25m as at 31st March 2014 to generate a Minimum Revenue Provision saving of £530,000 in 2014/15 be approved.
Word for word from the decision Shropshire published for this meeting.Source: www.shropshire.gov.uk
1.1The purpose of this report is to inform Members of the final outturn position for the Council’s 2013/14 capital programme and the current position regarding the 2014/15 to 2016/17 capital programme taking into account the slippage following the closure of the 2013/14 programme, and any budget increases/decreases for 2014/15 and future years. The report reflects:
§ The re-profiled 2013/14 budget of £47.4m and the future years capital programme budget; § The outturn capital expenditure of £40.7m, representing 85.9% of the re-profiled budget for 2013/14; § An underspend of £6.7m, of which £6.56m has been slipped to 2014/15 and £115k of which is no longer required/available to the capital programme; and § The current funding of the programme and its future affordability.
Recommendations
Members are asked to:
A. Approve budget variations of £17,700 to the 2013/14 capital programme, detailed in Appendix 1/Table 1 and the re-profiled 2013/14 capital budget of £47.4m.
B. Approve the re-profiled capital budgets of £71.4m for 2014/15, including slippage of £6.6m from 2013/14, £13.7m for 2015/16 and £5.3m for 2016/17 as detailed in Appendix 1/Table 4.
C. Accept the outturn expenditure set out in appendix 1 of £40.7m, representing 85.9% of the revised capital budget for 2013/14.
1 Council, 17 July 2014: Capital Outturn – 2013/14 D. Approve the Highways & Transport programme of schemes for delivery in 2014/15 and delegate authority to the Area Commissioner South in consultation with the Portfolio Holder to approve any changes to the implementation plan of schemes for delivery in 2014/15, within the parameters of the outline capital programme.
E. Approve the setting aside of capital receipt of £1.35m to replace the self- financed prudential borrowing previously applied to finance the Solar PV schemes. This will generate an ongoing revenue saving from 2014/15.
F. Approve retaining a balance of capital receipts set aside of £13.25m as at 31st March 2014 to generate a Minimum Revenue Provision saving of £530,000 in 2014/15.
REPORT
3. Risk Assessment and Opportunities Appraisal
3.1Risk assessments are undertaken as part of the evaluation of all capital bids.
3.2Capital receipt levels and the timing of receipts are dependant on planning approvals and prevailing market conditions.
3.3Environmental appraisals are carried out for individual schemes as appropriate.
3.4Community consultations are carried out for individual schemes as appropriate.
Financial implications
4.1This report considers the capital spend within the capital programme for 2013/14 and considers the impact that slippage within the programme will have on the financing of the capital programme in the future, including any future revenue implications.
Background
5.1The capital programme for 2013/14 and future years, was updated as part of the Capital Strategy 2013/14 to 2016/17 report, approved by Council 28 February 2013. This included updated allocations of capital grants and followed a review of internally financed schemes to re-prioritise schemes based on current priorities and to ensure the programme is affordable based on the projected level of capital resources available to the Council. The Council’s capital programme is subject to regular review and an updated Capital Strategy 2014/15 to 2016/17 was approved by Council on 27 February 2014.
6. Original and latest proposed capital programme for 2013/14
6.1The capital budget for 2013/14 is subject to change, the largest element being slippage from 2012/13 and re-profiling into future years. In Period 12 there
2 Council, 17 July 2014: Capital Outturn – 2013/14 has been a net budget decrease of £17,700, compared to the position reported at Period 11 2013/14. Table 1 summarises the overall movement, between that already approved, and changes for Period 12 that require approval.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.