That Planning Permission be granted in accordance with the Officer’s recommendation, subject to the conditions set out in Appendix 1 and an additional condition to ensure the timber posts for the fence and pole mounted security cameras were maintained and if required replacement were replaced with timber posts. (Councillor Wynn rejoined the meeting at this point.)
Word for word from the decision Shropshire published for this meeting.Source: www.shropshire.gov.uk
Proposal: Installation and operation of a solar farm and associated infrastructure, including photovoltaic panels, mounting frames, inverters, transformers, substations, communications building, fence and pole mounted security cameras.
Site Address: Hadley Farm Wrexham Road Whitchurch Shropshire SY13 3AB
Recommendation:- Grant delegated powers to the Area Planning Manager / Principal Planning Officer to issue permission subject to:
- Resolution of Ecological matters
- The conditions set out in Appendix 1..
1.0THE PROPOSAL 1.1 The application seeks permission for the installation of a solar farm comprising arrays of solar panels with associated buildings and infrastructure. The proposal would comprise the installation of 25,737 solar panels generating 6.56MW of electricity. The panels would be installed within west-east orientated rows. They would be mounted on fixed frames, of either galvanized aluminium or steel, in a double portrait configuration. They would be angled at between 15 and 30 degrees, with the highest edge at a maximum height of 2.2 metres and the lowest at 0.6 metre.
1.2Buildings and other infrastructure proposed comprises the following: - 4no. inverter buildings: 5.9 metres x 1.3 metres x 2.4 metres high (2.6 metres including plinth) - 2no. transformer buildings: 4.5 metres x 4.1 metres x 3.4 metres high (3.6 metres including plinth) - 1no. client substation: 8 metres x 2.4 metres x 2.7 metres high (3.2 metres including plinth) - 1no. communications building: 4 metres x 2.4 metres x 2.7 metres high (3.2 metres including plinth) - 1no. production substation: 5 metres x 2.4 metres x 2.7 metres high (3.2 metres including plinth)
1.3The buildings would be sited in two discrete areas, both centrally located, with: one towards the north and one towards the south of the site. It is proposed that the substations would be constructed of polyurethane, and the inverters and transformers of steel. All would be Moss Green in colour. They would be accessed by an access track running along the centre of the site. It is understood that the DNO substation building would need to be located on a different site and would form the basis of a separate planning application.
1.4A 2 metre high timber post and wire fence would be installed around the perimeter of the solar farm, for security purposes. CCTV security cameras would be erected around the site perimeter. These would be on timber poles, approximately 3 metres in height. Once the panels have been erected the land is proposed to be grazed by sheep. It is proposed that the panels would be removed at the end of their operational life.
2.0SITE LOCATION/DESCRIPTION 2.1 The application site is located on land forming part of Hadley Farm, approximately North Planning Committee – 21 October 2014 Agenda Item 7 Hadley Farm Wrexham Road Whitchurch
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.