Resolved
That the recommendations detailed in the report be noted.
Performance Management Scrutiny Committee noted this item on Monday 15 June 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
That the recommendations detailed in the report be noted.
1.1The purpose of this report is to inform Members of the final outturn position for the Council’s 2014/15 capital programme and the current position regarding the 2015/16 to 2017/18 capital programme taking into account the slippage following the closure of the 2014/15 programme, and any budget increases/decreases for 2014/15 and future years. The report reflects:
§ The re-profiled 2014/15 budget of £66.4m and the future years capital programme budget; § The outturn capital expenditure of £54.2m, representing 81.7% of the re-profiled budget for 2014/15; § An underspend of £12.2m, of which £12.1m has been slipped to 2015/16 and £100k of which is no longer required/available to the capital programme; and § The current funding of the programme and its future affordability.
Members are asked to:
A. Approve budget variations of £209,067 to the 2014/15 capital programme, detailed in Appendix 1/Table 1 and the re-profiled 2014/15 capital budget of £66.4m.
B. Approve the re-profiled capital budgets of £66.6m for 2015/16, including slippage of £12.1m from 2014/15, £34.6m for 2016/17 and £27.5m for 2017/18 as detailed in Appendix 1/Table 4.
C. Accept the outturn expenditure set out in appendix 1 of £54.2m, representing 81.7% of the revised capital budget for 2014/15.
1 Cabinet 10 June 2015, Performance Management Scrutiny Committee 15 June 2015, Audit Committee 25 June 2015, Council 23 July 2015: Capital Outturn – 2014/15
D. Approve retaining a balance of capital receipts set aside of £14.1m as at 31st March 2015 to generate a Minimum Revenue Provision saving of £564,000 in 2015/16.
REPORT
3. Risk Assessment and Opportunities Appraisal
3.1Risk assessments are undertaken as part of the evaluation of all capital bids.
3.2Capital receipt levels and the timing of receipts are dependant on planning approvals and prevailing market conditions.
3.3Environmental appraisals are carried out for individual schemes as appropriate.
3.4Community consultations are carried out for individual schemes as appropriate.
4.1This report considers the capital spend within the capital programme for 2014/15 and considers the impact that slippage within the programme will have on the financing of the capital programme in the future, including any future revenue implications.
5.1The capital programme for 2014/15 and future years, was updated as part of the Business Plan and Financial Strategy 2014/15 to 2016/17 report, approved by Council 27 February 2014. This included updated allocations of capital grants and a review of and delivery schedule for schemes.
5.2The Council’s capital programme is subject to regular review and an updated programme was included in the Business Plan and Financial Strategy 2015/16 to 2016/17, approved by Council on 26 February 2015.
6. Original and latest proposed capital programme for 2014/15
6.1The capital budget for 2014/15 is subject to change, the largest element being slippage from 2014/15 and re-profiling into future years. In Quarter 4 there has been a net budget decrease of £209k, compared to the position reported at Quarter 3 2014/15. Table 1 summarises the overall movement, between that already approved, and changes for Quarter 4 that require approval.
2 Cabinet 10 June 2015, Performance Management Scrutiny Committee 15 June 2015, Audit Committee 25 June 2015, Council 23 July 2015: Capital Outturn – 2014/15
Table 1: Revised Capital Programme Quarter 4 2014/15 Service Area Agreed Slippage and Quarter 4 Revised Capital budget changes budget 2014/15 Programme approved to changes to Capital - Council Quarter 3 14/15 be approved Programme 27/02/14 Quarter 4 General Fund
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
8A Appendix 1: Capital Monitoring Period 12Appendix | 685 KB | Download |
PDF |
Capital Outturn 2014-15Report | 191 KB | DownloadRead as text |
Follow Performance Management Scrutiny Committee at Shropshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Jul 2020 | Financial StrategyThat the Medium Term – July 2020 – 2020/21 to 2025/26, be noted. | Noted | Open |
| 8 Jul 2020 | Financial Monitoring Report, Quarter 4 2019/20That the report be noted. | Noted | Open |
| 8 Jul 2020 | Future Work Programmei) That Climate Change and SEND be considered by the Committee at its meeting in July; and ii) That the Financial Str... | Decided | Open |
| 10 Jun 2020 | Minutes of the meeting held on 20th May 2020that the minutes of the Performance Management Scrutiny Committee meeting held on 20 th May 2020 be approved as a cor... | Approved | Open |
| 10 Jun 2020 | Quarter 4, 2019/20 Corporate Performance ReportThat the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.