RESOLVED That in accordance with the provision of Schedule 12A of the Local Government Act 1972 and paragraph 10.2 of the Council’s Access to Information Procedure Rules, the public and press be excluded during consideration of the remainder of the item. 21.5 Members received an update on the waste collection redesign currently being undertaken. 21.6 RESOLVED a. That progress of the ERF to its adoption as a contract facility be noted; and b. That a further report on the waste collection service redesign be considered by the committee in early 2016
Word for word from the decision Shropshire published for this meeting.Source: www.shropshire.gov.uk
Report to Environment and Services Scrutiny Committee
Summary
1.1This report provides an update on progress regarding the construction and commissioning of the Battlefield Energy Recovery Facility (ERF) and collection service re-design work following on from the Shropshire Energy and Growth Solutions (SEGS) project.
1.2The background information on the ERF compliments the information that will provided by Veolia and Shropshire Council staff on the Scrutiny Committees visit to the plant on 28th September. .
Recommendations
Members of Environment and Services Scrutiny Committee are asked to:
2.1Note progress of the ERF to its adoption as a contract facility.
2.2Comment on the work done to date on waste collection service redesign following the verbal update at the meeting.
2.3Receive a further report on the waste collection service redesign in early 2016. REPORT
Battlefield Energy Recovery Facility
The most significant recent development for waste management services in Shropshire has been the successful commissioning of the Energy Recovery Facility (ERF) at Battlefield, Shrewsbury. The construction of the ERF is a landmark project for Shropshire Council and will be key to the treatment of Shropshire’s household waste throughout the life of the council’s waste PFI contract and beyond. The project has also included improvement works to the adjoining household recycling centre and exit road. The plant became a PFI contract facility on 10th September 2015.
The commissioning process began on 23rd December 2014, when the first load of waste was loaded into the chamber. The various stages of the process were then tested and refined over the following months, including the export of energy to the national grid which began in March 2015. All commissioning tests were completed and the facility handed over from construction contractors CNIM/Clugston to Veolia on 14th May. The facility has also been issued with a Certificate of Construction Completion by an independent certifier. Waste input is now around 270 tonnes per day, and by August 26.7m kilowatt hours of electricity had been exported to the national grid, enough to power around 6,500 homes.
A community liaison group was formed shortly after the facility received planning permission. The group comprises of local stakeholders and has met quarterly on site throughout the build phase. On 16th July the ERF was able to host a meeting of this group, the first visit by non-construction/Veolia staff. All present agreed positively upon the professional way in which the project had been undertaken by Veolia and their contractors.
Nearly 1 million ‘man’ hours have been deployed during the build phase with no major and just two minor health and safety incidents occurring despite at peak times there being up to 200 staff on site at a time. Despite the constrained size of site and its adjacency to the household waste recycling centre, impacts to the public using the HWRC, neighbouring businesses and passing traffic has been minimal.
Subject to planning approval, the ERF will be complemented by an art installation on the adjacent roundabout. The proposed installation is currently the subject of a planning consultation process, it is hoped the installation will take place later this year. Preparation is being made by Veolia for the official opening of the ERF, the opening ceremony will be fitting to the significance of the facility and likely to be held Spring 2016. 3. Risk Assessment and Opportunities Appraisal
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment and Services Scrutiny Committee at Shropshire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.