Central Planning Committee, Thursday 3 March 2016 at 2.00pm

Land At Snod Coppice, Rowton, Shrewsbury, Shropshire (15/04011/EIA)

Decided Planning 1 paper

Central Planning Committee decided this item on Thursday 3 March 2016. Below is the council's own wording, with the papers it was decided on.

Item99

Resolved

That, as per the Officer’s recommendation, planning permission be granted, subject to: · The conditions as set out in Appendix 1 to the report, subject to the wording of conditions 3, 4, 5 and 6 being amended as set out in the Schedule of Additional Letters.
Word for word from the decision Shropshire published for this meeting. Source: www.shropshire.gov.uk

Follow this further

Built from Shropshire's papers

What the report saysPro

Report to Central Planning Committee

Committee and date

Central Planning Committee

4 March 2016

Development Management Report

Responsible Officer: Tim Rogers email: [email protected] Tel: 01743 258773 Fax: 01743 252619

Summary of Application

Application Number: 15/05011/EIA Parish: Alberbury With Cardeston

Proposal: Erection of two poultry rearing buildings, four feed bins and other ancillary buildings, landscaping including ground modelling and tree planting.

Site Address: Land At Snod Coppice Rowton Shrewsbury Shropshire

Applicant: Rowton Growers Ltd

Case Officer: Kelvin Hall email: [email protected]

Grid Ref: 338557 - 313011

© Crown Copyright. All rights reserved. Shropshire Council 100049049. 2015 For reference purposes only. No further copies may be made.

Recommendation:- Grant Permission subject to the conditions set out in Appendix 1.

Contact: Tim Rogers (01743) 258773 Land At Snod Coppice, Rowton, Central Planning Committee – 4 March 2016 Shrewsbury, Shropshire

REPORT

1.0THE PROPOSAL 1.1 The planning application seeks permission for the extension of the existing poultry rearing development at Snod Coppice. The existing development comprises four large poultry rearing buildings, seven feed bins and a biomass boiler shed. The proposed development would include the erection of two additional poultry sheds, four feed bins and other ancillary buildings, together with landscaping including ground modelling and tree planting. The existing development has capacity for 179,000 birds in the four sheds. The proposed development would increase the capacity of the site by 96,000 birds to 275,000 bird places.

1.2Each poultry shed would be constructed with a solid concrete floor, metal portal frame and roof and side wall cladding. They would have a shallow pitched roof and measure 94.71 metres x 24.68 metres with a ridge height of 4.84 metres. The fan outlets would protrude from the roof plane to a height of 5.75 metres. The biomass boiler building would be positioned between the existing and proposed poultry buildings. It would measure 23.63 metres x 11.63 metres, with an eaves height of 3.95 metres and 5.56 metres to ridge. It would house a 600kW biomass boiler and include space for woodchip storage.

1.3The four feed bins would be positioned on concrete plinths between the proposed sheds. They would be 8.94 metres high and 3.5 metres in diameter. It is proposed that the colour of the buildings and feed bins would be reserved for agreement with the local planning authority. A concrete service pad would be constructed at the south-western side of the proposed poultry buildings, to be used for manoeuvring of HGVs.

1.4Production process: Prior to the crop cycle the sheds would be pre-warmed to 310c in preparation for chick delivery. Chicks would be ‘thinned’ when they reach around five weeks old. This would involve the catching and transport of a proportion of chicks over a two day period. When the birds are around six weeks old the remainder would be caught and removed from the site. Bird catching and removal would take place during the day time and night time over two days. At the end of the growing period the used litter would be taken away and stored in fields off-site prior to spreading on agricultural land. Wash down and disinfection would then take place ready for the next crop. The wash water would be collected in underground tanks before being spread to agricultural land. The biomass boiler would provide heat for the poultry sheds, using wood chip or straw as fuel.

1.5As detailed in section 6.1.1 below, the planning application is accompanied by an Environmental Impact Assessment (EIA), and this includes a detailed set of reports assessing the potential impacts of the development. The scope of the EIA is based upon formal advice provided by the local planning authority in a Scoping Report issued in November 2015.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Land At Snod Coppice, Rowton, Shrewsbury, Shropshire (15/04011/EIA)Report 283 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 11 attended
VB
Vernon BushellChairman, present
TC
Ted ClarkeVice Chairman, present
AB
Andrew BannermanCommittee Member, present
TB
Tudor BebbCommittee Member, apologies
DC
Dean CarrollCommittee Member, present
RE
Roger EvansCommittee Member, present
AL
Amy LiebichCommittee Member, present
PM
Pamela MoseleyCommittee Member, present
PN
Peter NuttingCommittee Member, present
KP
Kevin PardyCommittee Member, present
DR
David RobertsCommittee Member, present

More from Shropshire Central Planning Committee

All decisions
MeetingDecisionOutcome
4 Jul 2019 MinutesThat the of the meeting of the Central Planning Committee held on 6 th June 2019 be approved as a correct record and ... Approved Open
4 Jul 2019 Land North East of Kinton, Shrewsbury - 18/00130/EIAThat consideration of the application be deferred to a future meeting of this Committee at the request of the applicant. Deferred Open
4 Jul 2019 Land Off Manor Lane, Longden, Shrewsbury - 16/02395/FULThat authority be delegated to the Head of Planning Services to refuse planning permission subject to further consult... Refused Open
4 Jul 2019 School House Farm, Sheinton, Shrewsbury - 18/04266/FULThat planning permission be granted as per the Officer’s recommendation subject to the conditions set out in Appendix 2. Decided Open
4 Jul 2019 Maesbrook Nursing Home, Church Road, Shrewsbury - 19/01132/FULThat planning permission be granted as per the Officer’s recommendation subject to the conditions set out in Appendix 1. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies