i) That Connecting Shropshire commences a formal OJEU ‘open procurement’ process defined as Phase 2b, as soon as practically possible, using the funding (£11.7m) and defined preferences (<15Mbps) as laid out in its recently adopted Broadband Strategy. ii) That the Director for Place and Enterprise, in consultation with the Deputy Leader and Portfolio Holder for Business and Economy be granted authority to agree the OJEU tender specification and evaluation criteria that will meet with the broadband strategic objectives as defined in the Local Broadband Plan Shropshire for 2016-2020 approved by Cabinet on 13 July 2016. iii) That a report on the outcome of the procurement process is prepared and presented back to Cabinet to seek a decision on a contract award. i) That Connecting Shropshire commences a formal OJEU ‘open procurement’ process defined as Phase 2b, as soon as practically possible, using the funding (£11.7m) and defined preferences (<15Mbps) as laid out in its recently adopted Broadband Strategy. ii) That the Director for Place and Enterprise, in consultation with the Deputy Leader and Portfolio Holder for Business and Economy be granted authority to agree the OJEU tender specification and evaluation criteria that will meet with the broadband strategic objectives as defined in the Local Broadband Plan Shropshire for 2016-2020 approved by Cabinet on 13 July 2016. iii) That a report on the outcome of the procurement process is prepared and presented back to Cabinet to seek a decision on a contract award.
Word for word from the decision Shropshire published for this meeting.Source: www.shropshire.gov.uk
The report sets out the recommended procurement approach for Phase 2b of the Connecting Shropshire Programme which is in line with the recent Broadband Strategy that was approved at Cabinet on 13th July 2016.
Recommendations
It is recommended that Cabinet:
2.1Agree that Connecting Shropshire commences a formal OJEU ‘open procurement’ process defined as Phase 2b, as soon as practically possible, using the funding (£11.7m) and defined preferences (<15Mbps) as laid out in its recently adopted broadband strategy.
2.2That the Director for Place and Enterprise, in consultation with the Deputy Leader and Portfolio Holder for Economic Growth are given authority to agree the OJEU tender specification and evaluation criteria that will meet with the broadband strategic objectives as defined in the Local Broadband Plan Shropshire for 2016- 2020 approved by Cabinet on July 13th, 2016.
2.3That a report on the outcome of the procurement process is prepared and presented back to cabinet to seek a decision on a contract award.
REPORT 3. Risk and Opportunities
3.1The Open Market Review relies on the market providing an honest and balanced view of their current and projected commercial coverage area. The objective is to protect their commercial market from overbuild by a state-aided project. There is no contract obligation on the commercial provider to deliver 30Mbps to these projected areas. Connecting Shropshire will manage this risk by engaging and encouraging suppliers to complete their commercial coverage by 2020. If the supplier market fails to deliver their projections there may be further premises without access to superfast broadband.
3.2The aspiration to provide access to 30Mbps to all premises in the intervention area, with the funding that is available (£11.7m), will remain challenging.
3.3There is a risk that some Suppliers may not be prepared to bid for the OJEU tender because the State Aid conditions may be deemed commercially unfavorable.
3.4BDUK funding of £6.68m has been assured as available formally by the government. No formal funding agreement is yet in place for this funding.
3.5An Open Procurement exercise will create some competitive tension which will potentially attract a more favorable supplier contribution than Phase 2.
Financial implications
4.1The Council has £11.7m of public funding for Phase 2b comprising £6.68m from Broadband Delivery UK, and £5.02m from the Marches LEP Local Growth Fund.
4.2£110,880 annual base budget revenue funding remains in place to support the Connecting Shropshire programme office beyond September 2016. However, in addition to the base budget funding, phase 1 of the project has been reliant on contributions from the transformation and New Homes Bonus reserves and there is currently no commitment to maintain these contributions beyond 2016/17. A decision on use of these reserves to maintain support for the Broadband programme would need to be taken in light of the Council’s financial strategy, assessing the use for this purpose against the council’s other priorities and need to balance its budget.
4.3Undertaking a further phase of contract delivery beyond Phase 1 and 2 is likely to incur revenue expenditure over and above the base budget available. A report will be prepared for Cabinet at the end of the Phase 2b procurement (estimated as winter 2016) to outline the revenue implications and how the revenue budget requirement will be met.
Background
5.1Connecting Shropshire has laid out its aspirations for broadband delivery in the Local Broadband Plan reported to Cabinet on 13th July, 2016. The key aspirations are:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.