Shropshire Council
Cabinet, Wednesday 19 October 2016 at 12.30pm

Highways and Environment Term Maintenance Contract Re-procurement

Approved Executive 4 papers

Cabinet approved this item on Wednesday 19 October 2016. Below is the council's own wording, with the papers it was decided on.

Item64

Resolved

i. That the re-procurement of the Highways and Environmental Maintenance Services using a Term Service Model be approved as set out in this report ii. That authority be delegated to the Head of Infrastructure and Communities, in consultation with the Portfolio Holder for Highways and Transport to undertake the procurement process, including approving the terms of the contract, service specification documentation and associated decisions necessary to undertake the entire procurement process, prior to a final award report to appoint a Contractor being presented to Cabinet in 2017. iii. That authority be delegated to the Head of Infra structure and Communities in consultation with the Portfolio Holder for Highways and Transport to assess and implement future reductions in standards, volumes or specification, a possible cessation of some service requests will be required in order to meet the financial savings within the current Financial Strategy (revenue and capital), with their undoubted impact on Asset Condition and Satisfaction indicators. iv. That authority be delegated to the Head of Infrastructure and Communities, in consultation with the appropriate Portfolio Holder(s), to discuss with Town and Parish Councils grounds maintenance responsibilities in respect of public open spaces, amenity land, play areas and where appropriate highway land, and further to those discussions, to amend the ground maintenance arrangements for inclusion in the procurement process as appropriate. That the proposed procurement of a Term Maintenance Model, to support budget assurance and minimise strategic risk for the Council in delivering its operational and statutory functions, be noted. i. That the re-procurement of the Highways and Environmental Maintenance Services using a Term Service Model be approved as set out in this report ii. That authority be delegated to the Head of Infrastructure and Communities, in consultation with the Portfolio Holder for Highways and Transport to undertake the procurement process, including approving the terms of the contract, service specification documentation and associated decisions necessary to undertake the entire procurement process, prior to a final award report to appoint a Contractor being presented to Cabinet in 2017. iii. That authority be delegated to the Head of Infra structure and Communities in consultation with the Portfolio Holder for Highways and Transport to assess and implement future reductions in standards, volumes or specification, a possible cessation of some service requests will be required in order to meet the financial savings within the current Financial Strategy (revenue and capital), with their undoubted impact on Asset Condition and Satisfaction indicators. iv. That authority be delegated to the Head of Infrastructure and Communities, in consultation with the appropriate Portfolio Holder(s), to discuss with Town and Parish Councils grounds maintenance responsibilities in respect of public open spaces, amenity land, play areas and where appropriate highway land, and further to those discussions, to amend the ground maintenance arrangements for inclusion in the procurement process as appropriate. That the proposed procurement of a Term Maintenance Model, to support budget assurance and minimise strategic risk for the Council in delivering its operational and statutory functions, be noted.
Word for word from the decision Shropshire published for this meeting. Source: www.shropshire.gov.uk

Follow this further

Built from Shropshire's papers

What the report saysPro

Report to Cabinet

Recommendations

It is recommended that Cabinet agree to:

2.1Approve the re-procurement of the Highways and Environmental Maintenance Services using a Term Service Model as set out in this report

2.2Delegate authority to the Head of Infrastructure and Communities, in consultation with the Portfolio Holder for Highways and Transport to undertake the procurement process, including approving the terms of the contract, service specification documentation and associated decisions necessary to undertake the entire procurement process, prior to a final award report to appoint a Contractor being presented to Cabinet in 2017.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
8: Appendix 1 Soft Market Testing Outcome reportAppendix 292 KB Download
PDF
8: Appendix 2 Procurement Project TimetableAppendix 66 KB Download
PDF
8: Appendix 3 ESIIAAppendix 488 KB Download
PDF
Highways and Environment Term Maintenance Contract Re-procurementReport 470 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 11 attended
MP
Malcolm PateLeader, present
SC
Steve CharmleyDeputy Leader, apologies
KC
Karen CalderCommittee Member, present
LC
Lee ChapmanCommittee Member, present
SJ
Simon JonesCommittee Member, present
DM
David MinneryCommittee Member, present
CM
Cecilia MotleyCommittee Member, apologies
MP
Malcolm PriceCommittee Member, apologies
SW
Stuart WestCommittee Member, present
MW
Michael WoodCommittee Member, present
JP
Jane PalmerClerk, expected

More from Shropshire Cabinet

All decisions
MeetingDecisionOutcome
18 Nov 2026 MinutesThat the minutes of the meeting held on 14 October 2026 be confirmed as an accurate record. Decided Open
18 Nov 2026 Crisis & Resilience Fund – 6-month Progress UpdateThat Cabinet: 1. Endorsed the summary of the wider economic environment and the Council’s borrowings and investments ... Decided Open
18 Nov 2026 Council Tax Support - Proposed Changes 2027-28 Consultation ResponsesThat Cabinet: 1. Considered the responses received to the statutory consultation. 2. Agreed the following changes to ... Agreed Open
18 Nov 2026 Financial Monitoring Report Quarter 2 2026/27That Cabinet: A. Supported the Q2 favourable revenue outturn forecast of £0.051m. B. Supported the significant advers... Noted Open
18 Nov 2026 Treasury Management Update Quarter 2 2026/27That Cabinet: 1. Endorsed the summary of the wider economic environment and the Council’s borrowings and investments ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies