i. That the nature, scope and extent of engagement work required to develop a specification for Healthwatch Shropshire to ensure it is effective and resilient into the future be investigated in the first instance by Commissioning Development Manager. ii. That the emerging commissioning models set out in Section 6 below should be investigated. iii. That the involvement of the Health and Wellbeing Board in the recommissioning of Healthwatch Shropshire be supported.
Word for word from the decision Shropshire published for this meeting.Source: www.shropshire.gov.uk
1. Summary 1.1 This report sets out the steps required to secure a Local Healthwatch for Shropshire beyond 2018, options for achieving this and seeks advice from the health and Wellbeing Board as to the scope and extent of the engagement activity to support this process.
2. Recommendations 2.1. Feedback is given on the nature, scope and extent of the engagement work required to develop a specification for Healthwatch Shropshire to ensure it is effective and resilient into the future. 2.2. Feedback is given as to whether any, or all, of the emerging commissioning models set out in Section 6 below should be investigated. 2.3. Feedback is given as to the nature of the involvement of the Health and Wellbeing Board in the recommissioning of Healthwatch Shropshire
REPORT
3. Risk Assessment and Opportunities Appraisal 3.1 Risk Assessment A risk register will be established and updated as the commissioning project progresses. Healthwatch Shropshire (HWS) have also created and maintained their own operational and strategic risk assessment. Ongoing risks are common to both HWS and the Health and Wellbeing Board. Risks include uncertainty over future available funding for the Healthwatch function and capacity for HWS to be able to effectively deliver all their statutory functions whilst at the same time gathering and sharing views on the wide range of health and care changes and activities currently under way.
3.2Human Rights It is unlikely that there are any relevant Human Rights issues impacting this project.
3.3Equalities An Equalities and Social Inclusion Impact Assessment (ESIIA) will be established and updated as the commissioning project progresses. The ESIIA will be informed by the engagement activity undertaken to support the commissioning of Local Healthwatch.
3.4Communities Local Healthwatch exists to ensure that individuals and communities are able to have their views heard and shared with health and care services and commissioners. Through its own engagement activity, which involves many volunteers, members and stakeholders, Healthwatch has a positive impact on communities throughout Shropshire.
3.5Environment It is unlikely that there are any relevant environmental issues impacting this project.
4. Financial Implications 4.1 The IHCAS contract is fully funded and the Healthwatch contract is partly funded from the Local Reform and Community Voices Grant. The balance is funded out of the Local Government Finance Settlement. Current contract values are £24,000 per annum for IHCAS and £191,487 (plus a potential further £8,000 per annum to support a research grants programme) for Healthwatch.
4.2Engagement and commissioning activity will incur costs associated with staff time, publicity and, if required, venue hire.
5. Background 5.1 Healthwatch is the independent consumer champion for health and social care and was created under the Health and Social Care Act 2012 legislation to replace the LINks (Local Involvement Networks). Each local authority area is required to have a Local Healthwatch. Healthwatch Shropshire Ltd was formed in 2013 and is funded by Shropshire Council through a contract which runs until 31st March 2018. Healthwatch Shropshire (HWS) also delivers the Independent Health Complaints Advocacy Service (IHCAS) for Shropshire, again contracted until March 2018.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
HWBB Strategy 2028- 33 - proposalsto note the proposed timetable, milestones and consultation arrangements for the refresh of the Joint Health and Well...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.