Resolved
That planning permission be grantedsubject to the conditions set out in Appendix 1 of the Planning Officer’s report.
Northern Planning Committee decided this item on Tuesday 12 December 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
That planning permission be grantedsubject to the conditions set out in Appendix 1 of the Planning Officer’s report.
Committee and Date Item
North Planning Committee 5 12th December 2017 Public
Development Management Report
Responsible Officer: Tim Rogers Email: [email protected] Tel: 01743 258773 Fax: 01743 252619
Officer Appraisal Report
Summary of Application
Application Number: 16/05501/MAW Parish: Welshampton And Lyneal
Proposal: Proposed Construction of 7 x 995KW Biomass Plant
Site Address: Wood Lane Quarry, Spunhill, Ellesmere, SY12 0HY
Applicant: Tudor Griffiths Ltd
Case Officer: Graham French email: [email protected]
Recommendation:- Grant Permission subject to the conditions set out in Appendix 1. North Planning Committee – 12th December 2017 Agenda Item 5 – Wood Lane Quarry, Spunhill, Ellesmere
REPORT
1.0THE PROPOSAL
1.1Planning permission is sought for the construction of a portal framed building (87 x 32 metres and 14.7 metres to the ridge) to house a biomass plant which would be used for the drying of timber reclaimed in connection with the applicant’s recycling business. The current application follows the withdrawal in 2016 of a previous application (16/03239/MAW) for a Combined Heat and Power plant (CHP) following a change in the Government renewable heat subsidy regime which rendered the CHP plant unviable.
1.2The need for suitable drying facilities remains the same and the applicant, Tudor Griffiths Ltd (TG), is now proposing to substitute the CHP plant for a series of smaller biomass boilers (7x995Kw). This has an additional benefit of a slight reduction in the overall footprint of the proposed building. As the boilers and fans would be accommodated in lean-tos at each end of the building it would also reduce the length of the building that would be at the full proposed height.
1.3The plant would be fuelled by chipped and/or shredded virgin and/or Grade A (i.e. clean) timber compliant with PAS 111:2012. Heat from the boilers would be fed to perforated drying floors containing various timber products. This would reduce the moisture content of virgin and/or Grade A wood for use as fuel on or off site or as timber products. The material to be dried would include logs sourced from the Applicants own woodlands which would be sold through the Builders Merchants. The floor would also have the capability of drying crops such as cereal. All virgin timber would be sourced from sustainable renewable sources.
1.4Timber to fuel the boilers would be housed in the biomass building. Approximately 9,000 tonnes would be required per annum. Imported timber would be dried to a moisture content of 20 - 25% (suitable for biofuel use) using heat from the biomass boilers. The facility requires far less maintenance than the originally proposed CHP engine. The applicant advises that there is a sufficient market for all products within the local area and high confidence that long-term contracts will be achievable.
1.5Traffic: The company estimates that approximately 5,000 tonnes/annum of Grade A timber to fuel the boilers would be recovered from the existing incoming waste stream. An additional 4,000 tonnes would be required, equating to 250 incoming loads per year. A further 5,000 tonnes would be delivered annually, resulting in 200 importation movements and 150 export movements (given the reduced weight of dried loads). This would yield 600 extra movements per year which equates to approximately 12 per week or 2- 3 per day. Other materials that may be brought to site, including cereals and logs for air drying, would result in small numbers of vehicle movements, potentially in the region of 65 – 70 loads per annum. The possibility exists to reducing traffic movements by exporting wood chip in the delivery vehicles North Planning Committee – 12th December 2017 Agenda Item 5 – Wood Lane Quarry, Spunhill, Ellesmere
(‘backhauling’). The company would have an economic incentive to do this and it would also lead to environmental advantages.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Wood Lane Quarry, Spunhill, Ellesmere, SY12 0HY (16/05501/MAW)Agenda | 33 pages | DownloadRead as text |
Follow Northern Planning Committee at Shropshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Jul 2026 | MinutesThat the of the meeting of the North Planning Committee held on 21 st April and 14 th May 2026 be approved as a corre... | Approved | Open |
| 21 Jul 2026 | Proposed Residential Development Land Between Aston Road and Church Lane, Wem, Shropshire. (25/02775/OUT)Deferred by the Development Manager, in consultation with Legal, under 17.4 of the Local Protocol for Councillors and... | Deferred | Open |
| 21 Jul 2026 | Proposed Residential Development Land To The West Of Crosemere Crescent Cockshutt Shropshire (25/04083/FUL)To delegate authority to officers to grant planning permission, subject to further investigation for options to impro... | Decided | Open |
| 21 Jul 2026 | Proposed Residential Development NW Of Kingfisher Way Morda Shropshire (26/00772/FUL)That Planning Permission be granted subject to the conditions set out in Appendix 1 of the report | Decided | Open |
| 21 Jul 2026 | Application to Register The Glebelands, Bayston Hill as a Village GreenThat an independent barrister be appointed to act as an Inspector to undertake, if necessary, a non-statutory public ... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.